Vietnam’s New Bankruptcy Law Sets Clear Rules for Pending Arbitrations

Vietnam’s Law on Bankruptcy and Rehabilitation No. 142/2025/QH15, passed by the National Assembly on December 11, 2025, does something many regional counterparts do not yet attempt: it instructs parties and arbitral tribunals on exactly what happens to an arbitration once a debtor becomes insolvent. Together with the Law on Commercial Arbitration No. 54/2010/QH12, the new law improves upon what used to be an uncertain area of practice, now providing an explicit, mandatory sequence of procedures.

Suspension and Termination of Arbitration Proceedings

Under article 40(2) of the law, once a Vietnamese court accepts a bankruptcy petition, any arbitration that concerns the debtor’s financial obligations must be temporarily suspended as soon as the tribunal receives the court’s notification. If the court subsequently issues a decision commencing bankruptcy proceedings, article 59(2) takes a further step: the suspended arbitration is terminated outright, and the underlying case file is transferred to the court handling the insolvency for resolution. The two provisions work as a sequence: first suspension, then termination and transfer, rather than as independent triggers. Meanwhile, article 60(4) reinforces this effect by vesting the bankruptcy court with exclusive jurisdiction over all claims against the debtor from the date the petition is accepted.

Notably, this mechanism operates automatically, without the need for the insolvency court to issue a separate anti-arbitration order. The tribunal simply suspends or terminates the proceeding by operation of law once notified; however, Vietnamese law currently provides no procedure by which a party can apply to the insolvency court for permission to continue the arbitration despite the statutory effect. Practitioners with a Vietnamese counterparty in arbitration should treat notification of a bankruptcy filing as something to flag to the tribunal immediately since continuing to arbitrate a claim that has become subject to article 40(2) or 59(2) risks producing an award vulnerable to annulment for want of jurisdiction.

Scope of the Suspension: Bankruptcy, Not Rehabilitation

This mechanism only targets disputes concerning a debtor’s financial obligations, not every proceeding in which the debtor is a party. However, Vietnamese law does not precisely define what is classified as a “financial obligation” for this purpose, leaving room for case-by-case argument on the margins. It also applies only within bankruptcy or liquidation proceedings, not to Vietnam’s separate rehabilitation process. Because rehabilitation is a phase subject to creditor votes only after a court has accepted a bankruptcy petition, an arbitration that was suspended before rehabilitation was proposed will typically remain suspended through rehabilitation. Rehabilitation itself does not independently trigger this statutory effect. The law also draws no distinction between an arbitration already pending when a petition is accepted and one commenced later. Further, it makes no difference whether the debtor is a claimant or respondent.

Effect on the Underlying Arbitration Agreement

Under article 51, the insolvency court has the power to suspend or terminate the performance of a contract signed before the bankruptcy filing, where continuing would harm the debtor, regardless of whether that contract contains an arbitration clause. This raises an important question: does terminating a contract terminate the arbitration agreement within that contract? Vietnamese law answers no. The principle of separability under article 19 of the Law on Commercial Arbitration keeps the arbitration agreement independent of the underlying contract, and termination of that contract is not among the grounds on which an arbitration agreement can be invalidated under article 18. Nor can the insolvency administrator or insolvency court suspend or terminate the arbitration agreement itself, but only the contract’s performance. In short, a suspended or terminated contract does not by itself void the parties’ agreement to arbitrate future or related disputes, even though any arbitration already in progress may still be swept up by articles 40(2) and 59(2) if it concerns financial obligations.

Foreign-Seated Arbitration and Enforcement

The new law does not address whether articles 40(2) and 59(2) apply only to Vietnam-seated arbitrations or also reach foreign-seated arbitrations. In principle, a tribunal seated abroad is governed by the law of its own seat, not by Vietnamese insolvency legislation. However, that does not settle the issue. If a foreign award is rendered against a Vietnamese entity while that entity is undergoing a court-supervised bankruptcy process, Vietnamese courts may refuse to recognize or enforce the award on public policy grounds or as inconsistent with the mandatory principles of the Law on Bankruptcy and Rehabilitation. The practical effect is that a foreign-seated tribunal can proceed with the arbitration, but the resulting award may have questionable value in Vietnam. In addition, Vietnam has not adopted the UNCITRAL Model Law on Cross-Border Insolvency, so there is no formal channel for a foreign insolvency representative to seek recognition or relief in Vietnam.

Practical Considerations

A handful of related points round out the picture. Interim measures remain available in principle under article 49 of the Law on Commercial Arbitration even after a bankruptcy filing, but that power is overridden in practice once article 40(2) or 59(2) requires suspension or termination. The debtor’s legal name and its capacity to participate are unaffected by a bankruptcy filing, and Vietnamese law does not clearly allocate authority between the debtor and the insolvency administrator to settle a dispute or to represent the debtor in arbitration. Confidentiality is likewise unaffected since bankruptcy proceedings create no exception to the ordinarily private nature of arbitral hearings under the Law on Commercial Arbitration.

Because the statutory mechanism is still new, having taken effect only in the past year, there is no body of case law yet interpreting how broadly “disputes concerning financial obligations” will be read. Parties currently in arbitration with a Vietnamese counterparty, or drafting arbitration clauses for contracts likely to be performed in Vietnam, should treat this as an evolving rather than a settled area of legal interpretation.

RELATED INSIGHTS​ 

October 2, 2026
On July 24, 2026, a new 12.5% Section 301 tariff took effect on most imports from Thailand into the United States. The tariff was imposed by the Office of the US Trade Representative (USTR) under Section 301 of the Trade Act of 1974, following a finding that Thailand had failed to impose and effectively enforce a prohibition on imports of goods produced with forced labor. The new tariff replaced the temporary 10% Section 122 surcharge that had applied since February 24, 2026, following the US Supreme Court’s invalidation of the prior tariffs imposed under the International Emergency Economic Powers Act (IEEPA). The 12.5% tariff is not the only potential source of additional US duties on Thai-origin goods. Thailand is also subject to a separate Section 301 investigation concerning structural excess manufacturing capacity, which could result in additional duties. Unlike the Section 122 surcharge, which was capped at 15% and limited to 150 days, Section 301 provides a more flexible framework for imposing and maintaining trade measures. Section 301 actions are generally subject to a four-year termination rule but may continue following a review if continuation is requested. The new tariff therefore represents a potentially longer-term change in the tariff treatment of Thai-origin goods entering the US market. This article explains the legal and policy developments that led to the new tariff, how the Section 301 tariff differs from the tariff regimes that preceded it, Thailand’s response and ongoing negotiations with the United States, and the practical implications for businesses that manufacture, export, import, or distribute goods between Thailand and the United States. From IEEPA to Section 122 to Section 301 IEEPA Era (April 2025–February 2026) Beginning in April 2025, the US administration imposed sweeping tariffs under the International Emergency Economic Powers Act (IEEPA), invoking national emergencies relating to trade
September 28, 2026
Thailand has expanded the mandatory use of the Electronic Government Procurement (e-GP) system to cover submissions of procurement appeals to all government agencies subject to the Public Procurement and Supplies Administrative Act B.E. 2560 (2017) (Government Procurement Act). The expansion, which was set out in an official circular dated September 16, 2026, from the Public Procurement and Supplies Administrative Ruling Committee, takes effect on October 1, 2026. Notable Changes Under the expanded framework, bidders challenging an e-bidding or selective-method procurement result must file their appeal exclusively through e-GP within seven working days of the result being announced by the Comptroller General’s Department. While the system accepts filings around the clock during that window, submissions on the final day must be fully completed by 16:30 according to the e-GP system clock—merely starting a draft or uploading materials before the cutoff does not count as a confirmed submission. Government agencies that disagree with an appeal, in whole or in part, will also report their findings and supporting documents to the Appeals Committee through e-GP using the prescribed Appeal Opinion Report, also within seven working days of receipt. Withdrawals of appeals must likewise follow prescribed e-GP steps that vary depending on whether the matter is still under agency review, has been forwarded to the Appeals Committee, or has already been resolved. Excluded Categories Certain categories of procurement are not subject to the new guidelines on filing appeals electronically. These include: Procurement of supplies for confidential government use. Procurement conducted by government agencies operating overseas where the bidder is a foreign legal entity with no legal representative in Thailand, or where the bidder is a non-Thai national. Consulting service procurement under chapter 7 of the Government Procurement Act Design or construction supervision procurement under chapter 8 of the Government Procurement These exclusions apply
September 23, 2026
Arbitration under Thai law rests on consent. Section 11 of the Arbitration Act B.E. 2545 (2002) requires an arbitration agreement to be in writing and signed by the parties. This may also be satisfied by communications, an unchallenged allegation in pleadings, or incorporation by reference to a document containing an arbitration clause. A non-signatory cannot, as a general rule, be compelled to arbitrate merely because it participated in the transaction, received a benefit, or belongs to the corporate group of a signatory. Thai law nevertheless permits arbitration agreements and awards to affect third parties indirectly in limited circumstances. Under section 24, an arbitration clause is separable from the main contract; the invalidity of the contract does not invalidate the clause. In Supreme Court Judgment No. 3918/2563, an apparent sales contract concealed a construction contract and was void under the Civil and Commercial Code. However, the concealed construction contract and written arbitration clause remained effective. The tribunal had jurisdiction, and its award was enforceable under the Arbitration Act. Under the Arbitration Act, when a claim or liability is validly transferred, the transferee is bound by the related arbitration agreement. This includes assignment, transfer of obligations, legal succession, and subrogation. Depending on the facts and contract and agency law, consent may arise through execution by an authorized agent, ratification, assumption of obligations, or conduct accepting the contract and its arbitration clause. Thai law respects separate corporate personality. The group-of-companies doctrine has no statutory basis under the Arbitration Act, while alter egos or sham allegations require compelling evidence and an identifiable legal basis. Supreme Court Judgment No. 9161/2568 illustrates the procedural treatment of non-signatories. A consultancy contract required LCIA arbitration seated in Dubai. When the employer sued a consultant and his spouse in Thailand concerning a housing loan, the court disposed of
September 15, 2026
The Myanmar Investment Commission (MIC) has issued a notification that gives investors with projects in Myanmar clearer guidance for securing approval and for changing, expanding, or exiting an approved project. Issued on August 19, 2026, MIC Notification No. 5/2026 replaces MIC Notification No. 26/2021 and sets procedures for state or regional investment committees to review, approve, and supervise investment projects, including project amendments, investment increases, land-use rights applications, compliance inspections, and suspension or termination of approved businesses. Endorsement Application Timeline and Deemed Acceptance In Myanmar, prospective investors seeking approval under the Myanmar Investment Law generally do so through an MIC permit or an MIC endorsement, depending on the nature of the investment. While certain large-scale investment projects require an MIC permit, projects that are not required to obtain an MIC permit may instead apply for an MIC endorsement. Investors seeking MIC endorsement for their planned projects typically submit their applications to the relevant state or regional investment committee. These committees are established under the Myanmar Investment Law and are authorized to approve investments of less than USD 5 million, subject to the project’s nature and location. MIC Notification No. 5/2026 specifies that upon receiving an endorsement application, the relevant investment committee office will check it for completeness and determine whether it can be considered at the state or regional level or must be referred to the MIC; if it must be forwarded to the MIC, this will be done within 10 working days. If an application is within its purview, the committee may reject the endorsement application within 15 working days of receipt; otherwise, the application is deemed accepted. If approved, the endorsement certificate will be issued within 10 working days of the approval decision, subject to applicable procedures. Endorsement Certificate Amendment The notification clarifies which amendments a state