Vietnam Issues Amended Law on Construction

On December 10, 2025, the National Assembly of Vietnam officially passed the amended Law on Construction, marking the culmination of a multiyear reform process aimed at modernizing Vietnam’s construction legal framework, streamlining administrative procedures, and aligning with digital transformation and sustainability goals.

The amended law, which replaces the current Law on Construction No. 50/2014/QH13, will take effect on July 1, 2026. The Ministry of Construction (MOC) is also preparing several guiding decrees covering project classification, digital submissions and database management, and technical standards for design documentation.

Key Changes in the Amended Law

While the executed version of the amended Law on Construction has yet to be released to the public, reports have confirmed that it includes the following key changes introduced under the latest draft submitted by the MOC in September:

  • Project classification: The amended Law on Construction classifies construction projects by investment form (public, PPP, business investment, and others), which aligns with the Law on Public Investment, the Law on Investment, and the Law on PPP Investment. This reduces regulatory overlap and clarifies responsibilities.
  • Project preparation and appraisal: The requirement for prefeasibility reports for business investment projects is abolished, as this requirement is now governed by the Law on Investment and the Law on Public Investment. This change shortens the preparation timeline and reduces duplication of procedures. In addition, the authority’s appraisal is streamlined to a single feasibility stage. Also eliminated is the appraisal process conducted following basic design approval, shifting more responsibility to investors and consultants, with targeted post-audit mechanisms for high-risk projects.
  • Construction permits: One of the most significant new changes of the amended Law on Construction is the expansion of exemptions from construction permit requirements to the following eight distinct groups of construction works:
    1. State-secret works, emergency or urgent constructions, works under special public investment projects or projects following special procedures, temporary works, and works located on national defense or security land.
    2. Works under public investment projects approved by competent authorities such as the prime minister, heads of central agencies, leaders of supreme judicial bodies, the State Audit Office, the Office of the President, the Office of the National Assembly, ministries, political-social organizations, and chairpersons of People’s Committees at all levels.
    3. Works constructed along routes spanning two or more provinces, or those outside designated urban development areas as per approved plans or accepted route proposals.
    4. Offshore works under investment projects with authorized sea area allocation, airports, airport-related works, and works ensuring flight operations outside airports.
    5. Advertising structures exempt under the Law on Advertising—such as small, compact signs and billboards (under 20 m² per side), signs and billboards with simple structures (not metal frames), and freestanding billboards under 40 m² in area—and passive telecommunications infrastructure.
    6. Works under investment projects whose feasibility study reports or adjustments have been appraised and approved by competent authorities according to regulations.
    7. Grade 4 constructions and individual residential buildings under seven stories with a total floor area under 500 m2, provided they are not located in areas with specific architectural management regulations—such as functional zones, urban areas, rural residential zones, provincial/city urban development areas, national economic or tourism zones, or areas with established architectural management rules.
    8. Works involving internal repairs or external renovations that do not adjoin urban roads subject to architectural management, as long as such repairs do not alter the building’s purpose or function, affect structural safety, or compromise fire safety, environmental protection, or technical infrastructure.

According to the MOC, forthcoming government decrees will further simplify construction permit procedures. The entire permitting process is expected to be conducted online, with a maximum processing time of 7 to 10 days—reducing both time and costs by at least 30% as mandated by the government. The new regulations will also increase the responsibility of design consultants to ensure construction safety.

Other Notable Reforms

The amended law also reforms requirements and procedures in several other areas, as detailed below.

Cost Management and Contractual Principles

The amended law introduces clearer and more practical provisions on construction cost management and contractual arrangements, with a particular focus on risk allocation and contract adjustment. Accordingly, it distinguishes between force majeure events and fundamental changes of circumstances, following the Civil Code 2015, aiming to provide a fair and transparent legal basis for contract adjustment in exceptional situations.

Force majeure in this context refers to events that are entirely beyond the parties’ control and directly disrupt construction activities, such as natural disasters, environmental catastrophes, fires, epidemics, wars, national emergencies, strikes, blockades, or other situations determined by the prime minister for public investment and PPP projects. By contrast, a fundamental change of circumstances arises when external conditions make contract performance excessively difficult or economically imbalanced—for instance, changes in state policies or laws, unforeseeable geological conditions, or abnormal fluctuations in construction material prices.

Digital Transformation, Innovation, and Smart Construction Governance

For the first time, the amended Law on Construction establishes a legal basis for a National Construction Information and Database System, creating a digital foundation for state management of construction activities. This system will collect, store, and update data throughout the project lifecycle, serving as an official source to support functions such as project appraisal, permit issuance, and quality supervision. It will also connect with other national databases on land, planning, investment, and infrastructure, enabling data sharing and consistency across sectors.

In parallel, the law promotes the use of science, technology, and innovation in construction, including the adoption of green technologies and building information modeling (BIM).

Green and Sustainable Construction Policy

The amended law incorporates sustainability principles, requiring construction activities to comply with environmental protection standards and encouraging the use of local, recyclable, and energy-efficient materials. It promotes research and application of advanced technologies and green building solutions to reduce resource consumption and environmental impact. These provisions aim to align construction practices with Vietnam’s broader green growth strategy and support the transition toward sustainable development.

Outlook for Investors and Developers

While the amended Law on Construction takes a progressive step forward, it also brings several practical challenges that investors and other stakeholders should be mindful of. Pending the issuance of implementing decrees, the decentralization of appraisal and permitting authority could lead to different interpretations and enforcement practices among provinces, which may affect project timelines and create uncertainty in compliance.

The move from state preapproval to postconstruction accountability, though intended to streamline oversight, also places greater responsibility on investors to manage safety, design, and technical risks. This shift will likely require stronger internal controls and more reliable professional assurance systems.

Another issue lies in the transition period. Projects that start under the currently effective Law on Construction but continue after the new law takes effect may face uncertainty over which procedures, documents, or appraisal standards apply until detailed guidance is issued.

Finally, the success of the National Construction Information and Database System will depend heavily on how well government agencies coordinate, how reliable the shared data proves to be, and how secure the digital infrastructure is. Building strong digital capacity across stakeholders will be essential to ensure the system works as intended in practice.

Investors and developers should keep a close watch on forthcoming regulations that clarify the division of appraisal authority between central and local levels, the technical framework for database integration, and transitional procedures for projects that bridge the old and new legal regimes.

RELATED INSIGHTS​ 

January 8, 2026
Thailand’s Board of Investment (BOI) has tightened criteria for BOI-promoted companies to own land for residential use and introduced new procedures for land ownership applications under a new notification. Officially titled Notification of the Office of the Board of Investment No. Por. 9/2568 Re: Amended Criteria and Conditions for Permitting Foreign Juristic Persons Receiving Investment Promotion to Own Land for Office and Residence for Operational-Level Workers to Operate Business Granted Investment Promotion, dated July 18, 2025, the new notification was published in the Government Gazette on January 6, 2026, and is applicable to all applications submitted since the date of the notification (July 18, 2025). The new notification introduces an online application process for BOI-promoted companies seeking to own land for office use or residential purposes via the e-Land system, the BOI’s electronic system for land rights and benefits. Applications are reviewed virtually, and any requested amendments or additional documents must be submitted within seven business days. Failure to amend the application or submit any additional requested documents within this period will result in automatic rejection and removal of the application from the system. The new notification builds on the requirements specified in the previous notification on land ownership allowances for foreign companies, issued in 2024, by introducing additional qualification requirements for residences for operational-level workers (i.e., unskilled laborers). In this regard, such a residence must not be: Part of a land development project (housing estate), A condominium unit, or Classified as a house or commercial building.
December 25, 2025
On December 11, 2025, Vietnam’s National Assembly issued Resolution No. 254/2025/QH15 (Resolution No. 254) to address practical difficulties encountered in implementing the Law on Land 2024. The resolution provides specific mechanisms and policies to resolve issues related to land allocation, land leasing, and conversion of land-use purposes, while also addressing land valuation principles, timing of information collection, and land valuation methods. The resolution takes effect on January 1, 2026. Key provisions affecting investors are discussed below. Land Use Terms for Transferred Investment Projects The National Assembly has addressed situations where the remaining term of a transferred investment project is insufficient for the transferee’s business or financial plans. Resolution No. 254, along with the Law on Investment 2025, introduces aligned regulatory solutions. Under the Law on Investment 2025 (4th version submitted to the National Assembly for promulgation), if an investment project implemented prior to March 1, 2026, has been transferred and the transferor holds a Land Use Rights Certificate, has fulfilled all land-related financial obligations, and is not subject to termination, the competent authority may determine a new operating term if the remaining operating term does not meet the transferee investor’s financial or business plan. This adjustment occurs when approving or adjusting the investment policy or issuing or amending the investment registration certificate. The revised operating term is calculated from the date of the approval or issuance and must not exceed the statutory maximum of 70 years for projects in economic zones and 50 years for projects outside economic zones. Resolution No. 254 also permits adjustment of the land use term for transferred investment projects involving land, provided that the transferee investor pays additional land rent in accordance with applicable law, thereby ensuring consistency with the Law on Investment 2025. Land Rent Payment Options Resolution No. 254 generally expands the
December 16, 2025
Tilleke & Gibbins has contributed the Cambodia, Laos, Myanmar, Thailand, and Vietnam chapters to Infrastructure and Construction in Southeast Asia, a comparative guide developed by Drew Network Asia (DNA). The publication brings together insights from leading ASEAN law firms to address common legal and practical issues faced by participants in the construction and engineering sector across the region. Covering nine major Southeast Asian jurisdictions, the guide provides concise answers to frequently encountered questions relating to infrastructure and construction projects. Topics addressed include the regulatory environment, procurement practices, project structuring, risk allocation, contracting terms, dispute resolution mechanisms, and the enforcement of arbitral awards. Each jurisdictional chapter follows a consistent question-and-answer format, enabling readers to compare legal approaches and market practices across countries. This structure highlights both areas of convergence and key differences between jurisdictions, supporting more informed decision-making in cross-border projects and investments. While the guide offers a practical regional overview, it also underscores that legal frameworks and market practices vary significantly between jurisdictions and may be shaped by local principles and industry norms. Readers seeking jurisdiction-specific advice are encouraged to contact the practitioners listed at the end of each chapter. The full guide is available for download through the button below or directly from the DNA website.
November 28, 2025
On November 26, 2025, the government of Vietnam issued Resolution No. 8/2025/NQ-CP to extend and expand the pilot program allowing Vietnamese citizens who meet certain conditions to gamble at three integrated casino resorts in Vietnam: Corona Resorts & Casino Phu Quoc (An Giang Province) – Effective immediately, and continuing an ongoing pilot program that started in 2019. The Grand Casino Ho Tram (Ho Chi Minh City) – New pilot program for five years starting November 26, 2025. Van Don Integrated Casino & Tourism Complex (Quang Ninh Province) – New pilot program for five years from the date the casino receives its license. The pilot program was originally established under Decree No. 03/2017/ND-CP on casino business, which also sets out the specific eligibility conditions for Vietnamese citizens. After the pilot period, these projects must stop allowing Vietnamese players until the government issues further decisions. This expansion of the pilot program comes after Vietnam’s Ministry of Finance (MOF) released a draft decree earlier this year proposing significant changes to the regulatory framework governing casino operations. These revisions, which focus on increasing fiscal contributions from local players and strengthening compliance obligations for casino operators nationwide, are detailed below. Proposed Increase in Casino Entry Fees for Vietnamese Players The draft decree increases the entry fees applicable to Vietnamese citizens permitted to play at casinos. Under the current regulations, Vietnamese players are required to pay an entry fee of VND 1 million (approx. USD 38) for 24 consecutive hours or VND 25 million (approx. USD 950) per month. The draft decree proposes increasing these fees to VND 2.5 million (approx. USD 95) for 24 consecutive hours and VND 50 million (approx. USD 1,900) per month, effectively doubling the existing amounts and marking the first major fee revision since the pilot program allowing Vietnamese players