December 15, 2025

Vietnam Issues Amended Law on Construction

On December 10, 2025, the National Assembly of Vietnam officially passed the amended Law on Construction, marking the culmination of a multiyear reform process aimed at modernizing Vietnam’s construction legal framework, streamlining administrative procedures, and aligning with digital transformation and sustainability goals.

The amended law, which replaces the current Law on Construction No. 50/2014/QH13, will take effect on July 1, 2026. The Ministry of Construction (MOC) is also preparing several guiding decrees covering project classification, digital submissions and database management, and technical standards for design documentation.

Key Changes in the Amended Law

While the executed version of the amended Law on Construction has yet to be released to the public, reports have confirmed that it includes the following key changes introduced under the latest draft submitted by the MOC in September:

  • Project classification: The amended Law on Construction classifies construction projects by investment form (public, PPP, business investment, and others), which aligns with the Law on Public Investment, the Law on Investment, and the Law on PPP Investment. This reduces regulatory overlap and clarifies responsibilities.
  • Project preparation and appraisal: The requirement for prefeasibility reports for business investment projects is abolished, as this requirement is now governed by the Law on Investment and the Law on Public Investment. This change shortens the preparation timeline and reduces duplication of procedures. In addition, the authority’s appraisal is streamlined to a single feasibility stage. Also eliminated is the appraisal process conducted following basic design approval, shifting more responsibility to investors and consultants, with targeted post-audit mechanisms for high-risk projects.
  • Construction permits: One of the most significant new changes of the amended Law on Construction is the expansion of exemptions from construction permit requirements to the following eight distinct groups of construction works:
    1. State-secret works, emergency or urgent constructions, works under special public investment projects or projects following special procedures, temporary works, and works located on national defense or security land.
    2. Works under public investment projects approved by competent authorities such as the prime minister, heads of central agencies, leaders of supreme judicial bodies, the State Audit Office, the Office of the President, the Office of the National Assembly, ministries, political-social organizations, and chairpersons of People’s Committees at all levels.
    3. Works constructed along routes spanning two or more provinces, or those outside designated urban development areas as per approved plans or accepted route proposals.
    4. Offshore works under investment projects with authorized sea area allocation, airports, airport-related works, and works ensuring flight operations outside airports.
    5. Advertising structures exempt under the Law on Advertising—such as small, compact signs and billboards (under 20 m² per side), signs and billboards with simple structures (not metal frames), and freestanding billboards under 40 m² in area—and passive telecommunications infrastructure.
    6. Works under investment projects whose feasibility study reports or adjustments have been appraised and approved by competent authorities according to regulations.
    7. Grade 4 constructions and individual residential buildings under seven stories with a total floor area under 500 m2, provided they are not located in areas with specific architectural management regulations—such as functional zones, urban areas, rural residential zones, provincial/city urban development areas, national economic or tourism zones, or areas with established architectural management rules.
    8. Works involving internal repairs or external renovations that do not adjoin urban roads subject to architectural management, as long as such repairs do not alter the building’s purpose or function, affect structural safety, or compromise fire safety, environmental protection, or technical infrastructure.

According to the MOC, forthcoming government decrees will further simplify construction permit procedures. The entire permitting process is expected to be conducted online, with a maximum processing time of 7 to 10 days—reducing both time and costs by at least 30% as mandated by the government. The new regulations will also increase the responsibility of design consultants to ensure construction safety.

Other Notable Reforms

The amended law also reforms requirements and procedures in several other areas, as detailed below.

Cost Management and Contractual Principles

The amended law introduces clearer and more practical provisions on construction cost management and contractual arrangements, with a particular focus on risk allocation and contract adjustment. Accordingly, it distinguishes between force majeure events and fundamental changes of circumstances, following the Civil Code 2015, aiming to provide a fair and transparent legal basis for contract adjustment in exceptional situations.

Force majeure in this context refers to events that are entirely beyond the parties’ control and directly disrupt construction activities, such as natural disasters, environmental catastrophes, fires, epidemics, wars, national emergencies, strikes, blockades, or other situations determined by the prime minister for public investment and PPP projects. By contrast, a fundamental change of circumstances arises when external conditions make contract performance excessively difficult or economically imbalanced—for instance, changes in state policies or laws, unforeseeable geological conditions, or abnormal fluctuations in construction material prices.

Digital Transformation, Innovation, and Smart Construction Governance

For the first time, the amended Law on Construction establishes a legal basis for a National Construction Information and Database System, creating a digital foundation for state management of construction activities. This system will collect, store, and update data throughout the project lifecycle, serving as an official source to support functions such as project appraisal, permit issuance, and quality supervision. It will also connect with other national databases on land, planning, investment, and infrastructure, enabling data sharing and consistency across sectors.

In parallel, the law promotes the use of science, technology, and innovation in construction, including the adoption of green technologies and building information modeling (BIM).

Green and Sustainable Construction Policy

The amended law incorporates sustainability principles, requiring construction activities to comply with environmental protection standards and encouraging the use of local, recyclable, and energy-efficient materials. It promotes research and application of advanced technologies and green building solutions to reduce resource consumption and environmental impact. These provisions aim to align construction practices with Vietnam’s broader green growth strategy and support the transition toward sustainable development.

Outlook for Investors and Developers

While the amended Law on Construction takes a progressive step forward, it also brings several practical challenges that investors and other stakeholders should be mindful of. Pending the issuance of implementing decrees, the decentralization of appraisal and permitting authority could lead to different interpretations and enforcement practices among provinces, which may affect project timelines and create uncertainty in compliance.

The move from state preapproval to postconstruction accountability, though intended to streamline oversight, also places greater responsibility on investors to manage safety, design, and technical risks. This shift will likely require stronger internal controls and more reliable professional assurance systems.

Another issue lies in the transition period. Projects that start under the currently effective Law on Construction but continue after the new law takes effect may face uncertainty over which procedures, documents, or appraisal standards apply until detailed guidance is issued.

Finally, the success of the National Construction Information and Database System will depend heavily on how well government agencies coordinate, how reliable the shared data proves to be, and how secure the digital infrastructure is. Building strong digital capacity across stakeholders will be essential to ensure the system works as intended in practice.

Investors and developers should keep a close watch on forthcoming regulations that clarify the division of appraisal authority between central and local levels, the technical framework for database integration, and transitional procedures for projects that bridge the old and new legal regimes.

RELATED INSIGHTS​ 

April 30, 2026
Thailand’s Long-Term Resident (LTR) Visa regime offers an attractive immigration pathway for qualifying foreign nationals, providing a 10-year renewable permission to stay in Thailand. Following amendments under Board of Investment (BOI) Announcement No. Por. 3/2568 dated February 4, 2025, the regime now more explicitly accommodates property investment as a qualifying vehicle—a development of particular relevance to foreign nationals already considering real estate acquisitions in Thailand. The LTR Visa is available to several categories of applicants, including wealthy global citizens with global assets of at least USD 1 million, and wealthy pensioners aged 50 or older with an annual pension or fixed income of at least USD 40,000. Property as a Qualifying Investment For both categories, property investment is recognized as one of three eligible investment types alongside Thai government bonds (with at least five years remaining to maturity) and direct investments in Thai companies or approved venture capital or private equity vehicles. The minimum qualifying property investment is USD 500,000 for wealthy global citizens and USD 250,000 for wealthy pensioners. Eligible property types include freehold condominiums, buildings, or villas, as well as leasehold properties with a remaining lease term of at least 10 years. Health Coverage Requirement Beyond the investment threshold, applicants must demonstrate adequate health coverage. This requirement can be satisfied through a health insurance policy covering at least USD 50,000 in Thai medical expenses with at least 10 months of remaining coverage, evidence of social security benefits covering Thai medical costs, or a bank deposit of at least USD 100,000 retained for 12 months. Practical Considerations For foreign nationals already considering property acquisitions in prime residential markets—where investment values commonly meet or exceed the USD 500,000 threshold—the visa pathway effectively transforms a real estate purchase into a dual-purpose investment, combining asset ownership with long-term residence rights that
April 7, 2026
Real estate law specialists from Tilleke & Gibbins provided the chapter on Vietnam for Practical Law’s Commercial Real Estate Global Guide 2026, a comparative jurisdictional guide in Q&A format giving a high-level overview of real estate investment structures, restrictions on foreign ownership, and other important issues of real estate law. The main topics include the following: Real estate investment Title to real estate Sale of real estate Real estate tax Real estate finance Real estate leases Planning and development controls To read the Vietnam chapter, please visit the Practical Law website and enroll in the free Practical Law trial to gain full access.
February 25, 2026
In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions. Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam. While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam. What’s New? Article 86.2 of the 2025 Law on Construction provides (emphasis added): “Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.” This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2. Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the
January 20, 2026
Thailand’s Board of Investment (BOI) has imposed new restrictions on foreign-majority shareholding and land ownership for companies in certain promoted activities. The changes took effect on September 1, 2025, but were not published in the Government Gazette until December 30, 2025, under Notification of the Board of Investment No. Sor. 7/2568 on the Amendment to List of Activities Eligible for Investment Promotion under Notification of the Board of Investment No. 9/2565, dated July 22, 2025. Foreign Land Ownership Restrictions Generally, foreign land ownership is one of the privileges granted to BOI-promoted companies, allowing them to own land to engage in the promoted activities. However, with these new restrictions, the BOI will no longer grant land-ownership privileges to foreign-majority-owned companies that conduct business activities in the following categories: Rolling, drawing, casting, or forging of nonferrous metals (category 5.4.9) Manufacturing of ferrous metal products or ferrous metal parts (category 5.4.11.2) Manufacturing of nonferrous metal products and/or nonferrous metal parts for industrial use (category 5.4.11.4) Manufacturing of other metal products, including other metal parts for industrial use (category 5.4.11.5) Manufacture of chemical products for industry (category 6.2) Manufacture of plastic products for industrial goods and parts (category 6.4.1) These restrictions do not apply to existing BOI-promoted companies that have at least three projects granted promotion under the same juristic person during the past 15 years (2011–2025) with total investment of at least THB 5 billion, excluding the cost of land and working capital. Foreign Shareholding Restrictions For companies to be eligible for BOI promotion in three other categories of business activities, at least 51% of the company’s registered capital must be held by Thai individual shareholders, unless the BOI-promoted activity is located within a special border economic zone as designated by the BOI. These three categories are: Manufacture of bags made of