May 19, 2023

Vietnam Approves New Power Development Plan

On May 15, 2023, Vietnam’s Deputy Prime Minister Tran Hong Ha signed Decision No. 500 of the Prime Minister approving the National Power Development Plan for the period 2021-2030, with a vision to 2050 (“PDP VIII”), following extensive public consultations and multiple rounds of review since the first draft version was circulated in 2021. The plan was approved in the context that in the past few years, a number of large power projects have been behind schedule for operation, while new projects have not been able to be implemented due to waiting for additional planning.

PDP VIII is the master plan for the development of the power source and transmission grid at 220kV or higher; services in renewable energy and new energy in Vietnam; and works connecting the power grids of Vietnam and neighboring countries.

We set out below some quick updates regarding PDP VIII.

1. Development Targets

Key development targets are summarized in the table below:

Investors in coal, domestic gas, and LNG projects may need to have a conversion plan ready given the 2050 targets to convert to other sources of energy.

2. Solar Projects

A list of 27 solar power projects that were planned for the period of 2021-2030 but which have not been assigned to investors are not allowed to be deployed but can be considered after 2030, except in the case of deployment in the form of self-production and self-consumption (Appendix IV). These projects represent 4,136.25 MW of capacity that will be left on the sidelines until 2030.

3. Hydropower Projects

A list of 14 potential hydropower projects can be considered if economic and technical conditions allow for more hydropower development (Appendix III). These projects represent 1,244 MW of capacity that can be added to the hydropower targets for 2030.

4. Projects Prioritized for Investment

Certain important projects will be prioritized for investment (Appendix II), including:

  • 13 LNG-fired power projects are expected to be completed by 2030, and two projects by 2035.
  • Six coal-fired power projects are expected to be completed by 2030.
  • Five coal-fired power projects are behind schedule, facing difficulties in changing shareholders and arranging capital. These projects are expected to be completed by 2030.
  • Four cogeneration power sources and power sources using residual heat, blast furnace gas, and by-products of technological lines in industrial facilities are expected to be completed by 2030, and three projects by 2035.
  • 10 domestic gas-fired power projects are expected to be completed by 2030.
  • 25 medium and large hydropower sources are expected to be completed by 2030.
  • Two pumped storage hydropower plants are expected to be completed by 2030, and two plants by 2035.

5. Electricity Importation

Vietnam will build out 500kV and 220kV transmission lines connecting to Laos to import electricity from power plants in Laos according to the memorandum of understanding signed between the two governments.

6. Total Investment Capital

For the period 2021-2030, the total investment capital for power sources and grid systems is targeted to be USD 134.7 billion, in which investment capital for power sources will be USD 119.8 billion (averaging USD 12 billion per year), and for grid systems will be USD 14.9 billion (averaging USD 1.5 billion per year).

For the period 2031-2050, the total investment capital for power sources and grid systems is targeted to be USD 399.2-523.1 billion, in which investment capital for power sources will be USD 364.4-511.2 billion (averaging USD 18.2-24.2 billion per year), and for grid systems will be USD 34.8-38.6 billion (averaging USD 1.7-1.9 billion per year).

7. Next Steps

The Ministry of Industry and Trade will submit the Implementation Plan for PDP VIII to the Prime Minister in June 2023 and formulate and submit to the government the amended Law on Electricity and the new Law on Renewable Energy for submission to the National Assembly in 2024. PDP VIII also specifies that a direct power purchase agreement (DPPA) pilot program will be issued but is silent on the timeline.

For more details on PDP VIII, or on any aspect relating to Vietnam’s energy sector, please contact Tram Ngoc Bich Nguyen at [email protected], Duong Duy Nguyen at [email protected], or Duc Minh Pham at [email protected].

RELATED INSIGHTS​ 

December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.
August 12, 2024
With the growing prominence of ESG (Environmental, Social, and Governance) factors, businesses in Vietnam are increasingly recognizing their importance in driving global demand, societal impact, and economic value. A comprehensive acknowledgment of ESG-related legal requirements is critical for investors and companies operating in Vietnam to meet stakeholder expectations and ensure compliance. Our guide provides a basic overview of the rapidly evolving ESG landscape in Vietnam, covering a range of key issues for companies doing business in the country: What is ESG, and what does the ESG legal framework look like in Vietnam? Who needs to follow ESG regulations in Vietnam? What are the benefits of ESG compliance? How can enterprises enhance ESG best practices in Vietnam? Please click on the link below to view the full article.
June 6, 2024
On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly. One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector. Annual payment of land rental Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment. As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning. Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged. Obtaining land Under the Land Law 2024,
June 4, 2024
Thailand’s Department of Mineral Fuels (DMF) is in the process of preparing a notification that will open the application period for onshore petroleum exploration and production rights in the country’s 25th bidding round. The 25th round of bidding will cover nine petroleum blocks, including the northeastern areas (blocks L1/66, L2/66, L3/66, L4/66, L5/66, L7/66, and L9/66) and central areas (blocks L6/66 and L8/66). The DMF estimates that application submissions will commence around the middle of 2024, and the successful bidder will be announced at the end of the same year. Based on previous rounds of bidding, applicants must meet the following key criteria: The applicant is a company with the purpose of carrying out petroleum exploration and production; The applicant commands the necessary assets, machinery, equipment, tools, and specialists to explore for, produce, sell, and dispose of petroleum; The applicant has not abandoned its operations under a concession or been subject to revocation of a concession in Thailand; and None of its personnel, shareholders, directors, or authorized directors is listed as a person who has abandoned its operations under a concession, or has been subject to revocation of a concession in Thailand. If the applicant does not itself possess all the qualifications under (2) above, it must have another government-approved company that possesses all the qualifications under (2) and has a capital or management relationship with the applicant, and the applicant must supply guarantees that the company will make available to the applicant all necessary assets, machinery, equipment, tools, and specialists for the applicant to explore for, produce, sell, and dispose of petroleum. Companies with a vested interest in petroleum exploration and production in Thailand must remain vigilant for updates. The DMF is expected to provide an update and more details on the bidding very soon. For more details