Thailand’s Power Development Plan: 2018 Update Expected to Focus on Renewable Energy

Voyageur – A Publication of CanCham Thailand

Introduction

In 2015, the Ministry of Energy revised its Power Development Plan in order to provide a blueprint for Thailand’s energy priorities over the coming two decades. The PDP2015, as the Power Development Plan was called, was itself an update on previous development plans created by the Ministry of Energy in conjunction with the Electricity Generating Authority of Thailand (EGAT), which had last been updated in 2012. Consistent with this pattern, the Power Development Plan will be updated again in 2018 to revise the Ministry’s objectives in light of new facts on the ground.

The PDP2015 was devised as a government master plan alongside the Energy Efficiency Development Plan, the Alternative Energy Development Plan (AEDP), the Natural Gas Supply Plan, and the Petroleum Management Plan. The overarching objectives of the Ministry of Energy’s plans were set as: (1) energy security; (2) economy, and specifically maintaining appropriate costs of power generation and implementing energy efficiency; and (3) ecology, with a particular focus on reducing environmental and social impacts by lessening carbon dioxide intensity of power generation. In order to achieve these objectives, the Ministry of Energy realized that renewable energy sources would have to play a significant role.

AEDP2015

At the end of 2014, Thailand had installed capacity of 7,400.43 megawatts (MW) from renewable energy sources, including hydroelectricity. Of this, solar capacity amounted to 1,298.51 MW, whereas installed wind capacity only amounted to 224.47 MW. The Ministry of Energy set targets for renewable energy constituting approximately 20% of Thailand’s installed capacity by 2036. Targets for 2036 installed capacity for wind and solar were set at 3,002 MW and 6,000 MW, respectively. Given the state of renewables in Thailand at the time, these goals seemed fairly ambitious and many questioned whether the targets were overly optimistic.

By the end of 2017, it has become clear that the naysayers’ pessimism was misplaced. At the end of 2017, installed capacity for wind power had nearly tripled from 2014 levels, to 627.82 MW. Capacity for solar power was 2,692.26 MW at the end of 2017, which amounts to a doubling of generating capacity from 2014. The three years from 2014 to 2017 also saw increased capacity for power plants fueled by biomass, biogas, and municipal solid waste.

With Thailand already nearly halfway to its goal of 6,000 MW of installed solar capacity by 2036, and both demand and supply of solar power showing no signs of slowing down, the target appears to require upward revision. A revised target should be expected in the PDP2018. A report issued in November 2017 by the International Renewable Energy Agency (IRENA) puts 17,200 MW of installed solar photovoltaic (PV) capacity by 2036 as a realistic objective.

Policy Hurdles

Thailand is in the midst of a renewable energy revolution. Just three years ago it seemed fanciful to imagine renewable sources of energy accounting for approximately 20% of Thailand’s installed capacity by 2036; now, it seems feasible to imagine nearly half of the country’s installed capacity coming from renewables in 20 years. Given the abundance of solar energy potential, it is clear that solar PV will be the most significant driver of this revolution. Other renewable sources, such as wind and biomass, will also play significant roles in Thailand’s diversified energy mix. This will present the Ministry of Energy with a number of challenges which will require apt policy-making.

First is the problem of intermittency. Some renewable sources, most notably solar and wind power, can only produce electricity when weather conditions permit. Without sufficient baseload sources of energy, an overreliance on intermittent electricity generating sources may result in rolling blackouts. Technological advances with respect to energy storage, such as through more efficient batteries or pumped storage hydroelectricity, have the potential to reduce the impact of intermittency. The Ministry of Energy has taken the initiative to address this concern by instituting new firm or semi-firm capacity requirements in power purchase agreements (PPAs) with small power producers or very small power producers. The commitments in these PPAs essentially require the power producer to commit to certain specific feed-in targets. This may spur innovation with respect to storage, or lead to further hybrid power producing facilities with multiple fuel sources.

Secondly, the Ministry of Energy must contend with the untapped potential of rooftop solar PV installments in Thailand. At the moment, the inability of most producers to sell electricity generated by rooftop solar PV cells to a power distributor makes it economically difficult to justify incurring the still significant expense of installing PV panels. For factories or large business centres, where electricity use is highest during daylight hours, the economic case is much clearer as most of the electricity which is generated will be consumed immediately. For most residential buildings, by contrast, electricity use is generally higher when the sun is not shining. Without the ability to sell the electricity back to a distributor, there is little incentive for households to install rooftop solar PV panels. The Ministry of Energy has indicated a willingness to introduce a net metering scheme; the challenge will be to ensure that the feed-in-tariff rate is neither too low so as to not properly incentivize households, nor too high so as to cause a strain on government resources.

Conclusion

In 2015, the Ministry of Energy set ambitious targets for renewable energy development in Thailand. It appears now that the 2015 targets were too conservative, and that they will be met ahead of schedule. Thailand’s pivot toward renewables satisfies each of the stated objectives in the PDP2015, namely energy security, economy, and ecology. While a number of policy challenges remain, the potential for continued growth in Thailand’s renewable energy sector is evident.

RELATED INSIGHTS​ 

August 12, 2024
With the growing prominence of ESG (Environmental, Social, and Governance) factors, businesses in Vietnam are increasingly recognizing their importance in driving global demand, societal impact, and economic value. A comprehensive acknowledgment of ESG-related legal requirements is critical for investors and companies operating in Vietnam to meet stakeholder expectations and ensure compliance. Our guide provides a basic overview of the rapidly evolving ESG landscape in Vietnam, covering a range of key issues for companies doing business in the country: What is ESG, and what does the ESG legal framework look like in Vietnam? Who needs to follow ESG regulations in Vietnam? What are the benefits of ESG compliance? How can enterprises enhance ESG best practices in Vietnam? Please click on the link below to view the full article.
June 6, 2024
On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly. One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector. Annual payment of land rental Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment. As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning. Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged. Obtaining land Under the Land Law 2024,
June 4, 2024
Thailand’s Department of Mineral Fuels (DMF) is in the process of preparing a notification that will open the application period for onshore petroleum exploration and production rights in the country’s 25th bidding round. The 25th round of bidding will cover nine petroleum blocks, including the northeastern areas (blocks L1/66, L2/66, L3/66, L4/66, L5/66, L7/66, and L9/66) and central areas (blocks L6/66 and L8/66). The DMF estimates that application submissions will commence around the middle of 2024, and the successful bidder will be announced at the end of the same year. Based on previous rounds of bidding, applicants must meet the following key criteria: The applicant is a company with the purpose of carrying out petroleum exploration and production; The applicant commands the necessary assets, machinery, equipment, tools, and specialists to explore for, produce, sell, and dispose of petroleum; The applicant has not abandoned its operations under a concession or been subject to revocation of a concession in Thailand; and None of its personnel, shareholders, directors, or authorized directors is listed as a person who has abandoned its operations under a concession, or has been subject to revocation of a concession in Thailand. If the applicant does not itself possess all the qualifications under (2) above, it must have another government-approved company that possesses all the qualifications under (2) and has a capital or management relationship with the applicant, and the applicant must supply guarantees that the company will make available to the applicant all necessary assets, machinery, equipment, tools, and specialists for the applicant to explore for, produce, sell, and dispose of petroleum. Companies with a vested interest in petroleum exploration and production in Thailand must remain vigilant for updates. The DMF is expected to provide an update and more details on the bidding very soon. For more details
June 4, 2024
As Vietnam continues its rapid economic development, the demand for sustainable and reliable energy sources has never been more critical. Solar power has emerged as a key component of Vietnam’s strategy to diversify its energy portfolio and reduce its carbon footprint. Recent developments of the regulatory framework governing solar power projects in Vietnam, as discussed below, highlight the country’s commitment to renewable energy and its efforts to create a conducive environment for solar power investments. Objectives for the Development of Solar Power Projects On May 15, 2023, the Prime Minister issued Decision No. 500/QD-TTg, approving the National Power Development Plan for 2021-2030 with a vision to 2050 (“PDP VIII”). Following this, on April 1, 2024, the Prime Minister promulgated the Implementation Plan for PDP VIII (“Implementation Plan”). These documents underscore Vietnam’s commitment to promoting renewable energy, particularly solar. They emphasize self-production and self-consumption of solar power, the development of rooftop solar systems, and the promulgation of the direct power purchase mechanism. The integration of solar power with battery storage is also encouraged, contingent upon economic viability. PDP VIII sets ambitious capacity targets for solar power. By 2030, the capacity is projected to reach approximately 12,836 MW, accounting for 8.5% of the total power capacity. This includes 10,236 MW from concentrated solar power and 2,600 MW from self-production and self-consumption solar power. By 2050, the capacity is expected to rise to between 168,594 MW and 189,294 MW, representing 33.0-34.4% of the total power capacity. Additionally, PDP VIII and the Implementation Plan list 27 solar power projects, totaling 4,136.25 MW, slated for implementation after 2030. However, these projects may be advanced under self-production and self-consumption arrangements. Draft Decree on Direct Power Purchase Agreements On April 15, 2024, the Ministry of Industry and Trade (“MOIT”) released a draft decree on direct power