January 3, 2024

Thailand’s New Pool Gas Scheme

Thailand’s Energy Regulatory Commission (ERC) has issued the Notification on the Criteria for Regulating the Licensed Pool Manager B.E. 2566 (2023), which took effect on November 30, 2023. It followed an earlier notification, which took effect on October 13, 2023, that added the new license for the country’s pool gas manager. The new notification aims to regulate natural gas sale agreements and promote competition among players in the regulated natural gas market—that is, those who utilize natural gas for electricity generation under the Electricity Generating Authority of Thailand (EGAT) scheme, including industrial and NGV (natural gas for vehicles) consumers who rely on natural pool gas.

The establishment of the pool gas scheme is aimed at encouraging new shippers to enter the market and providing new natural gas shippers with fair opportunities to compete with existing shippers, as all licensed shippers in the regulated market are subject to the same natural gas costs under this new scheme.

Under this pool gas scheme, the pool manager plays a critical part in reselling natural gas in the country. Some of its responsibilities include the following:

  • Purchasing natural gas or liquid natural gas (LNG) from licensed shippers in the regulated market at the rate at which the shippers procured the natural gas, including incidental expenses such as pipeline transportation and LNG station fees;
  • Collecting data on the quantity and price of the gas purchased from the licensed shippers and calculating the pool gas price as specified in the ERC-approved manual, which is basically the average price of the natural gas procurement cost of all shippers in the pool; and
  • Reselling natural gas or LNG to licensed shippers at the pool gas pricing rate in the quantity distributed to the pool by each shipper.

Apart from its function in facilitating the primary procedures of the pool gas scheme, the pool manager is responsible for preparing the standard natural gas sale agreement to be used by all licensed shippers in the regulated market.

The ERC is in the process of establishing an independent agent to act as the licensed pool manager. In the interim, PTT Public Company Limited is acting as the licensed pool manager, with a ring-fenced department handling the pool-managing duties.

Given the significance of the pool manager, PTT’s appointment as interim pool manager and the future establishment of an independent agent are important developments for the industry. The increase in competition in the natural gas market that is expected to follow the establishment of the new pool gas scheme will also need to be watched closely.

For more details on the pool gas scheme, or on any aspect of energy activities in Thailand, please contact Supasit Boonsanong at [email protected], Kobchai Nitungkorn at [email protected], or Thananya Pholchaniko at [email protected].

RELATED INSIGHTS​ 

September 1, 2020
With interest in renewable and sustainable energy sources rapidly increasing worldwide, the nations of the Mekong region are beginning to incorporate innovative power generation options into their electrical grids and, more significantly, into their growth plans for the future. As a result, wind energy, formerly one of the least-utilized options in the hydro and solar dominated region, is beginning to see a considerable uptick in interest from investors and governments in the region alike.
August 19, 2020
In order to qualify as a VSPP, a power producer must generate no more than 10 MW per project, and must comply with the requirements and restrictions set by the Executive Committee of Power Purchase from Community Power Plant Projects. Furthermore, prospective VSPPs may only use one of the following:BiomassBiogas from wastewater or wasteBiogas from biofuelA hybrid of biomass or biogas  with solar power
August 19, 2020
On March 2, 2020, the Department of Mineral Fuels (DMF) issued its Notification Re: the Determination of Exploration Blocks for the Bidding for Petroleum Exploration and Production B.E. 2563 (2020). This notification, which repeals the Notification of the Department of Mineral Fuels Re: the Determination of Exploration Blocks for the Bidding for Petroleum Exploration and Production B.E. 2561 (2018), allocates the areas to be used as exploration blocks for the 23rd round of bidding for petroleum and exploration production.