Public-Private Partnerships: Thailand’s Plan for Infrastructure Development

Bangkok Post, Corporate Counsellor Column

The government of Thailand has made it clear that it intends to fully utilize public-private partnerships (PPPs) in order to implement the country’s upcoming infrastructure development goals. The adoption of the Private Investment in State Undertakings Act B.E. 2556 (2013) (PISUA) and the announcement of the Strategic Plan on Private Investment in State Undertakings in 2015 demonstrate the specific policy objectives the government intends to achieve through using PPPs.

In Thailand, for PPP projects that fall under the PISUA, the governmental work units in charge of a particular project are required to offer terms of a joint investment agreement which have been approved by the State Enterprise Policy Office and the Policy Board on Allowing Private Entities to Make Joint Investment in the State’s Business. At minimum, the joint investment agreement is required to contain the period of the project, details concerning the implementation of the project or services to be performed, rates on the service fees and method of payment, assets of the project company and land ownership, as well as other standard clauses such as force majeure, termination and liquidated damages, guarantee and insurance, and dispute resolution.

Although the discussion around PPPs makes it seem as though there is a common contractual framework for each type of project, the reality is that the terms of the agreement between the government agency or ministry and the private investor are quite varied. The agreement form and structure will depend largely on the existence and allocation of various risk factors inherent in PPP projects.

Demand Risk

For instance, the demand by end users for a particular project may be less than what is originally projected—this is often referred to as “demand risk.” For motorway or railroad projects, there is always a great deal of uncertainty surrounding the degree to which the public will make use of additional transport infrastructure. Although part of the technical due diligence of any project will be an assessment of likely demand, it is impossible to predict with absolute certainty the actual demand by consumers once the project is operational. By contrast, demand for power generation in specific geographical areas tends to be more predictable, as current shortfalls and forecasts for increased energy consumption are often more readily apparent. Private parties to energy PPP agreements often mitigate against demand risk by insisting on guaranteed feed-in-tariff rates, or “take-or-pay” terms in the power purchase agreement.

In the concession model—which in Thailand is utilized in a number of sectors such as upstream petroleum production—the agreement allocates the majority of the risks and benefits of successful project implementation to the private entity. This generally includes complete assumption of the demand risk by the concessionaire. By contrast, when the PPP agreement takes the form of an operating and maintenance agreement, the demand risk remains with the public sector while the private entity acts mainly as a service contractor.

In comparison to these more extreme types of PPP arrangements, a “Design-Build” or “Design-Build-Operate” (DBO) model allows the public sector to maintain ownership over the project while allocating the design and construction tasks to a private entity. If the private sector entity is operating the project, it often does so in exchange for fixed fees while the public sector recoups its costs through pay-as-you-go fees from the public. The DBO is a common structure—though not the only structure available—in toll-road projects.

A “Build-Operate-Transfer” (BOT), “Build-Transfer-Operate” (BTO), or “Build-Operate-Own” (BOO) structure shifts ownership, either temporarily or indefinitely, to the private party. Along with the shift in ownership comes greater risk and the potential for greater rewards. The private partners in BOT or BOO contracts are generally responsible for financing the project development. Such structures are commonly used in greenfield power generation projects, particularly when the government or a state-owned entity acts as the off-taker.

According to a report released earlier this year by the ASEAN Secretariat, the Thai Department of Highways (DOH) has been considering the trade-offs between alternative PPP structures with respect to highway toll projects. The DOH is conscious that tolls collected by private investors under a BTO model may be insufficient to cover the costs of the project, and may therefore not be sufficiently attractive to the private sector. On the other hand, a DBO model, or a modification thereof, requires the government to assume a greater degree of risk in the event the highway is underused by the public.

Other Risks

There are other risks which a private investor must consider when bidding on a PPP contract. Political risk and regulatory risk often refer to the possibility of expropriation to the detriment of the private investor, or a change in regulations which would adversely affect the profitability of the private participant. It is difficult to completely mitigate this in the PPP agreement, since these risks are more fundamental to the host state’s capacity and willingness to promote private investment, particularly with regard to public infrastructure works. Thailand has been a model for a number of developing economies, as successive Thai governments have actively encouraged both private investment and PPP projects in general.

Additional risks include environmental risk, insurance risk, social risk, and exchange rate risk. These are only some of the factors which both public and private parties must consider when entering into PPP agreements. Since the public sector generally develops the contractual framework for a particular project prior to offering the tender, it will need to carefully consider which contractual form will best promote the public policy objective while attracting sufficient interest for private investment. Terms which allocate most risks to the private party may be unattractive in some situations, particularly where the rewards of successful project implementation cannot justify the assumption of such risks.

The use of PPPs by states to promote infrastructure development is increasing in popularity not only in Southeast Asia, but across the world. When properly executed, PPPs can be an efficient means to allocate state resources in order to promote economic growth and benefit the public at large. For private investors, the increased use of PPPs in Thailand represents an economic opportunity. Understanding the allocation of risk in PPP agreements and developing strategies to mitigate is a key component to a successful project.

RELATED INSIGHTS​ 

January 27, 2025
Thailand’s Ministry of Energy (MOE) has announced the launch of the 25th bidding round for petroleum exploration and production. This round offers nine greenfield onshore blocks—seven in northeastern Thailand and two in central Thailand—encompassing over 33,000 km². The bids can be submitted from July 1 to July 16, 2025. The sizes and locations of these blocks are: Northeast Thailand Block L1/66: 3,223.51 km² (Khon Kaen, Nong Bua Lam Phu, Udon Thani) Block L2/66: 3,917.03 km² (Kalasin, Sakon Nakhon, Udon Thani) Block L3/66: 3,918.22 km² (Kalasin, Khon Kaen, Maha Sarakham, Udon Thani) Block L4/66: 3,656.65 km² (Amnat Charoen, Mukdahan, Nakhon Phanom, Yasothon) Block L5/66: 3,436.01 km² (Chaiyaphum, Khon Kaen, Nakhon Ratchasima) Block L7/66: 3,438.51 km² (Buri Ram, Maha Sarakham, Nakhon Ratchasima, Roi Et, Surin, Khon Kaen) Block L9/66: 3,885.44 km² (Nakhon Ratchasima) Central Thailand Block L6/66: 3,966.86 km² (Chaiyaphum, Lop Buri, Phetchabun) Block L8/66: 3,957.41 km² (Kanchanaburi, Nakhon Pathom, Ratchaburi, Suphan Buri) Bidding Process Interested companies must submit their bids to the Department of Mineral Fuels (DMF) between July 1 and July 16, 2025. Bids should include: Application form (ChorThor/Por1) Proof of eligibility: Corporate documentation, audited financial statements, and proof of resources Technical and commercial proposals: Exploration plans, geological surveys, financial and work commitments, and special benefits such as signing bonuses of at least USD 100,000. There is a nonrefundable THB 50,000 application fee per block, and applicants must provide a bid bond of THB 3 million per block via an unconditional bank guarantee from a commercial bank with branches in Thailand, valid for at least one year from the bidding submission date. The guarantee will be returned to unsuccessful bidders upon request and to successful bidders upon the signing of the concession agreement. Eligibility Bidders must meet the following main eligibility criteria: Bidders must be limited companies with the following qualifications: The company must have the objective of
January 23, 2025
In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges. In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports. The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models. Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include: Allowing additional planning where projects do not violate national security. Allowing rectification of projects’ violations in land and construction process as per law. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered. For items (iv) and (v), the authority will issue regulations
January 14, 2025
Thailand’s Department of Industrial Works (DIW) has issued a new regulation (Ministerial Regulation Re: Designation of Type, Kind, and Size of Factories (No. 3) B.E. 2567 (2024)), which removes the factory license requirement for electricity generation from solar energy installations on rooftops, roof decks, or any part of a building used for residential or other purposes, regardless of capacity. The new rules took effect on December 28, 2024. Under the previous regulations, solar rooftop installations had to seek approval from the DIW if their capacity exceeded 1,000 kW (1 MW), which added time and administrative costs when adopting renewable energy solutions. Benefits and Further Compliance The updated regulation benefits industrial operators by facilitating faster installation times and lower costs, as solar rooftops can now be installed without the need for prior approval of a factory license from the DIW. Operators can now more easily contribute to environmental sustainability and carbon reduction efforts. Despite the lifting of the factory licensing requirement, other compliance obligations, such as an energy business license (or exemption from an energy business license), a controlled energy production license, and a construction permit, may still apply. Reason for the Change Removing the classification of rooftop or building-installed solar power plants as factories aligns with Thailand’s renewable energy goals and reduces regulatory burdens for industrial operators. Additionally, it supports the achievement of energy policies aligned with the UN’s Sustainable Development Goals and Thailand’s international commitments to reduce greenhouse gas emissions through the participation of all sectors. For further details on how this change affects business operations or to explore strategies for renewable energy implementation, please contact Supasit Boonsanong at [email protected], Charuwan Charoonchitsathian at [email protected], or Phareeya Yongpanich at [email protected].
December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.