Public-Private Partnerships: Thailand’s Plan for Infrastructure Development

Bangkok Post, Corporate Counsellor Column

The government of Thailand has made it clear that it intends to fully utilize public-private partnerships (PPPs) in order to implement the country’s upcoming infrastructure development goals. The adoption of the Private Investment in State Undertakings Act B.E. 2556 (2013) (PISUA) and the announcement of the Strategic Plan on Private Investment in State Undertakings in 2015 demonstrate the specific policy objectives the government intends to achieve through using PPPs.

In Thailand, for PPP projects that fall under the PISUA, the governmental work units in charge of a particular project are required to offer terms of a joint investment agreement which have been approved by the State Enterprise Policy Office and the Policy Board on Allowing Private Entities to Make Joint Investment in the State’s Business. At minimum, the joint investment agreement is required to contain the period of the project, details concerning the implementation of the project or services to be performed, rates on the service fees and method of payment, assets of the project company and land ownership, as well as other standard clauses such as force majeure, termination and liquidated damages, guarantee and insurance, and dispute resolution.

Although the discussion around PPPs makes it seem as though there is a common contractual framework for each type of project, the reality is that the terms of the agreement between the government agency or ministry and the private investor are quite varied. The agreement form and structure will depend largely on the existence and allocation of various risk factors inherent in PPP projects.

Demand Risk

For instance, the demand by end users for a particular project may be less than what is originally projected—this is often referred to as “demand risk.” For motorway or railroad projects, there is always a great deal of uncertainty surrounding the degree to which the public will make use of additional transport infrastructure. Although part of the technical due diligence of any project will be an assessment of likely demand, it is impossible to predict with absolute certainty the actual demand by consumers once the project is operational. By contrast, demand for power generation in specific geographical areas tends to be more predictable, as current shortfalls and forecasts for increased energy consumption are often more readily apparent. Private parties to energy PPP agreements often mitigate against demand risk by insisting on guaranteed feed-in-tariff rates, or “take-or-pay” terms in the power purchase agreement.

In the concession model—which in Thailand is utilized in a number of sectors such as upstream petroleum production—the agreement allocates the majority of the risks and benefits of successful project implementation to the private entity. This generally includes complete assumption of the demand risk by the concessionaire. By contrast, when the PPP agreement takes the form of an operating and maintenance agreement, the demand risk remains with the public sector while the private entity acts mainly as a service contractor.

In comparison to these more extreme types of PPP arrangements, a “Design-Build” or “Design-Build-Operate” (DBO) model allows the public sector to maintain ownership over the project while allocating the design and construction tasks to a private entity. If the private sector entity is operating the project, it often does so in exchange for fixed fees while the public sector recoups its costs through pay-as-you-go fees from the public. The DBO is a common structure—though not the only structure available—in toll-road projects.

A “Build-Operate-Transfer” (BOT), “Build-Transfer-Operate” (BTO), or “Build-Operate-Own” (BOO) structure shifts ownership, either temporarily or indefinitely, to the private party. Along with the shift in ownership comes greater risk and the potential for greater rewards. The private partners in BOT or BOO contracts are generally responsible for financing the project development. Such structures are commonly used in greenfield power generation projects, particularly when the government or a state-owned entity acts as the off-taker.

According to a report released earlier this year by the ASEAN Secretariat, the Thai Department of Highways (DOH) has been considering the trade-offs between alternative PPP structures with respect to highway toll projects. The DOH is conscious that tolls collected by private investors under a BTO model may be insufficient to cover the costs of the project, and may therefore not be sufficiently attractive to the private sector. On the other hand, a DBO model, or a modification thereof, requires the government to assume a greater degree of risk in the event the highway is underused by the public.

Other Risks

There are other risks which a private investor must consider when bidding on a PPP contract. Political risk and regulatory risk often refer to the possibility of expropriation to the detriment of the private investor, or a change in regulations which would adversely affect the profitability of the private participant. It is difficult to completely mitigate this in the PPP agreement, since these risks are more fundamental to the host state’s capacity and willingness to promote private investment, particularly with regard to public infrastructure works. Thailand has been a model for a number of developing economies, as successive Thai governments have actively encouraged both private investment and PPP projects in general.

Additional risks include environmental risk, insurance risk, social risk, and exchange rate risk. These are only some of the factors which both public and private parties must consider when entering into PPP agreements. Since the public sector generally develops the contractual framework for a particular project prior to offering the tender, it will need to carefully consider which contractual form will best promote the public policy objective while attracting sufficient interest for private investment. Terms which allocate most risks to the private party may be unattractive in some situations, particularly where the rewards of successful project implementation cannot justify the assumption of such risks.

The use of PPPs by states to promote infrastructure development is increasing in popularity not only in Southeast Asia, but across the world. When properly executed, PPPs can be an efficient means to allocate state resources in order to promote economic growth and benefit the public at large. For private investors, the increased use of PPPs in Thailand represents an economic opportunity. Understanding the allocation of risk in PPP agreements and developing strategies to mitigate is a key component to a successful project.

RELATED INSIGHTS​ 

August 12, 2024
With the growing prominence of ESG (Environmental, Social, and Governance) factors, businesses in Vietnam are increasingly recognizing their importance in driving global demand, societal impact, and economic value. A comprehensive acknowledgment of ESG-related legal requirements is critical for investors and companies operating in Vietnam to meet stakeholder expectations and ensure compliance. Our guide provides a basic overview of the rapidly evolving ESG landscape in Vietnam, covering a range of key issues for companies doing business in the country: What is ESG, and what does the ESG legal framework look like in Vietnam? Who needs to follow ESG regulations in Vietnam? What are the benefits of ESG compliance? How can enterprises enhance ESG best practices in Vietnam? Please click on the link below to view the full article.
June 6, 2024
On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly. One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector. Annual payment of land rental Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment. As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning. Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged. Obtaining land Under the Land Law 2024,
June 4, 2024
Thailand’s Department of Mineral Fuels (DMF) is in the process of preparing a notification that will open the application period for onshore petroleum exploration and production rights in the country’s 25th bidding round. The 25th round of bidding will cover nine petroleum blocks, including the northeastern areas (blocks L1/66, L2/66, L3/66, L4/66, L5/66, L7/66, and L9/66) and central areas (blocks L6/66 and L8/66). The DMF estimates that application submissions will commence around the middle of 2024, and the successful bidder will be announced at the end of the same year. Based on previous rounds of bidding, applicants must meet the following key criteria: The applicant is a company with the purpose of carrying out petroleum exploration and production; The applicant commands the necessary assets, machinery, equipment, tools, and specialists to explore for, produce, sell, and dispose of petroleum; The applicant has not abandoned its operations under a concession or been subject to revocation of a concession in Thailand; and None of its personnel, shareholders, directors, or authorized directors is listed as a person who has abandoned its operations under a concession, or has been subject to revocation of a concession in Thailand. If the applicant does not itself possess all the qualifications under (2) above, it must have another government-approved company that possesses all the qualifications under (2) and has a capital or management relationship with the applicant, and the applicant must supply guarantees that the company will make available to the applicant all necessary assets, machinery, equipment, tools, and specialists for the applicant to explore for, produce, sell, and dispose of petroleum. Companies with a vested interest in petroleum exploration and production in Thailand must remain vigilant for updates. The DMF is expected to provide an update and more details on the bidding very soon. For more details
June 4, 2024
As Vietnam continues its rapid economic development, the demand for sustainable and reliable energy sources has never been more critical. Solar power has emerged as a key component of Vietnam’s strategy to diversify its energy portfolio and reduce its carbon footprint. Recent developments of the regulatory framework governing solar power projects in Vietnam, as discussed below, highlight the country’s commitment to renewable energy and its efforts to create a conducive environment for solar power investments. Objectives for the Development of Solar Power Projects On May 15, 2023, the Prime Minister issued Decision No. 500/QD-TTg, approving the National Power Development Plan for 2021-2030 with a vision to 2050 (“PDP VIII”). Following this, on April 1, 2024, the Prime Minister promulgated the Implementation Plan for PDP VIII (“Implementation Plan”). These documents underscore Vietnam’s commitment to promoting renewable energy, particularly solar. They emphasize self-production and self-consumption of solar power, the development of rooftop solar systems, and the promulgation of the direct power purchase mechanism. The integration of solar power with battery storage is also encouraged, contingent upon economic viability. PDP VIII sets ambitious capacity targets for solar power. By 2030, the capacity is projected to reach approximately 12,836 MW, accounting for 8.5% of the total power capacity. This includes 10,236 MW from concentrated solar power and 2,600 MW from self-production and self-consumption solar power. By 2050, the capacity is expected to rise to between 168,594 MW and 189,294 MW, representing 33.0-34.4% of the total power capacity. Additionally, PDP VIII and the Implementation Plan list 27 solar power projects, totaling 4,136.25 MW, slated for implementation after 2030. However, these projects may be advanced under self-production and self-consumption arrangements. Draft Decree on Direct Power Purchase Agreements On April 15, 2024, the Ministry of Industry and Trade (“MOIT”) released a draft decree on direct power