When the Thai government enacted the Private Investments in State Undertakings Act B.E. 2556 (2013) (PISUA)—a new law regulating public-private partnerships (PPPs) that was designed to streamline and clarify the PPP process and thereby boost private investment, especially in the infrastructure sector—measures were introduced to increase the effectiveness and transparency of the PPP process, something previously unseen in PISUA’s predecessor, the Private Participation in State Undertakings Act B.E. 2535 (1992) (PPSUA).

The provisions of the old PPSUA, which were in effect from 1992 until 2013, were written in a way that allowed for a variety of legal interpretations, thus providing for uncertainty as to which projects were captured within the scope of the law. Although regulations had been issued under the old law which addressed the selection process, many investors still perceived difficulties, which ultimately discouraged them from pursuing participation in PPPs in Thailand. Additionally, the old PPSUA lacked any provisions that would specifically guide the development of PPPs in Thailand, as it did not determine which sectors PPPs would benefit the public and should therefore be promoted.

While the new PISUA—which applies to all projects (except petroleum and mining concessions) with a value of THB one billion (approximately USD 30.5 million) or more—made only incremental changes relative to the older PPSUA in terms of approval procedures, it did set out a much stronger framework for comprehensive planning and quality of public-private ventures. This was evident in the stipulation of regulations on the use of qualified experts and consultants for preparing an independent project appraisal report, as well as sections calling for a PPP Policy Committee, a PPP Fund, and, as a main driver and guideline of PPP policy, a PPP Strategic Plan.

The new law has also established a PPP Development Fund, which is to be used for developing the PPP Strategic Plan, hiring consultants, and helping agencies develop PPPs that are consistent with the plan. Among other matters, the Strategic Plan identifies sectors and specific projects in which PPPs would be of benefit to Thailand, the priority of each, a target for private investment, and a timeframe for implementation. Five-year Strategic Plans are, from now on, to be prepared on a roll-on basis to provide for continual guidance.

The PPP Committee, which is chaired by the Prime Minister and vice-chaired by the Minister of Finance, is now required to work with the State Enterprise Policy Office (SEPO) to prepare a five-year Strategic Plan for PPPs for the Cabinet’s consideration. The SEPO, acting as the secretariat, has the duty to prepare a framework setting out the draft Strategic Plan, goals, target audience, and other details for approval of the PPP Committee. To ensure the plan reflects public needs, the PPP Policy Committee must also hold hearings to obtain input from state agencies and members of the public.

Once the hearings have been held and the Committee has then approved the draft Strategic Plan under consideration of the input from these hearings, it will submit the plan to the Cabinet for approval and promulgation.

In addition, once the Strategic Plan has been published in the Government Gazette, it is binding on state agencies regarding the preparation and approval of projects that fall under the Strategic Plan. Even the Cabinet and the PPP Committee are required to principally adhere to the Strategic Plan when they are making their decision regarding the approval of a project. However, if the Cabinet finds it expedient to revise a Strategic Plan that is already in effect, it does have the right to approve revisions suggested by the PPP Committee, and in such a case, the newly revised Strategic Plan would again have to be published in the Government Gazette to replace the previous one.

The current draft of the Strategic Plan for 2015-2019, which marks the first time such a Strategic Plan for PPPs in Thailand has ever been submitted, completed the public hearing stage in March 2015 and is currently awaiting approval by the Committee to be submitted to the Cabinet. In this draft, it has been stipulated that projects have to be conducted as PPPs in the following six fields: urban mass rail systems, urban toll roads, commercial ports, high-speed rail systems, telecommunication networks, and high-speed Internet systems.

For 15 other fields, the current draft Strategic Plan recommends that the government encourage the participation of private investors, but in these fields, private participation is not mandatory and the relevant state agencies have the right to decide whether they want to use a PPP or whether they would prefer to fund the project entirely by the use of the state budget or the state agency’s budget. In this group are fields such as inter-urban toll roads, solid waste disposal systems, airport management, terminals for transportation, packing, sorting, and distribution of goods, as well as administration, management, and maintenance of common ticketing systems. (For the full list of these 15 fields under group 2, please see “Table 1: PPP Implementation Timeframe” in the attached PDF.)

The current draft Strategic Plan also sets out the timeframes of implementation for most of the PPP fields (for details, please see “Table 1: PPP Implementation Timeframe” in the attached PDF), as well as the estimated investment amount for each field (for details, please see “Table 2: Estimated investment amounts under the Strategic Plan for 2015-2019” in the attached PDF). It now remains to be seen whether this Strategic Plan, once enacted, will indeed become a driving force for increased private investment in Thailand’s state undertakings.

RELATED INSIGHTS​ 

January 27, 2025
Thailand’s Ministry of Energy (MOE) has announced the launch of the 25th bidding round for petroleum exploration and production. This round offers nine greenfield onshore blocks—seven in northeastern Thailand and two in central Thailand—encompassing over 33,000 km². The bids can be submitted from July 1 to July 16, 2025. The sizes and locations of these blocks are: Northeast Thailand Block L1/66: 3,223.51 km² (Khon Kaen, Nong Bua Lam Phu, Udon Thani) Block L2/66: 3,917.03 km² (Kalasin, Sakon Nakhon, Udon Thani) Block L3/66: 3,918.22 km² (Kalasin, Khon Kaen, Maha Sarakham, Udon Thani) Block L4/66: 3,656.65 km² (Amnat Charoen, Mukdahan, Nakhon Phanom, Yasothon) Block L5/66: 3,436.01 km² (Chaiyaphum, Khon Kaen, Nakhon Ratchasima) Block L7/66: 3,438.51 km² (Buri Ram, Maha Sarakham, Nakhon Ratchasima, Roi Et, Surin, Khon Kaen) Block L9/66: 3,885.44 km² (Nakhon Ratchasima) Central Thailand Block L6/66: 3,966.86 km² (Chaiyaphum, Lop Buri, Phetchabun) Block L8/66: 3,957.41 km² (Kanchanaburi, Nakhon Pathom, Ratchaburi, Suphan Buri) Bidding Process Interested companies must submit their bids to the Department of Mineral Fuels (DMF) between July 1 and July 16, 2025. Bids should include: Application form (ChorThor/Por1) Proof of eligibility: Corporate documentation, audited financial statements, and proof of resources Technical and commercial proposals: Exploration plans, geological surveys, financial and work commitments, and special benefits such as signing bonuses of at least USD 100,000. There is a nonrefundable THB 50,000 application fee per block, and applicants must provide a bid bond of THB 3 million per block via an unconditional bank guarantee from a commercial bank with branches in Thailand, valid for at least one year from the bidding submission date. The guarantee will be returned to unsuccessful bidders upon request and to successful bidders upon the signing of the concession agreement. Eligibility Bidders must meet the following main eligibility criteria: Bidders must be limited companies with the following qualifications: The company must have the objective of
January 23, 2025
In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges. In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports. The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models. Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include: Allowing additional planning where projects do not violate national security. Allowing rectification of projects’ violations in land and construction process as per law. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered. For items (iv) and (v), the authority will issue regulations
January 14, 2025
Thailand’s Department of Industrial Works (DIW) has issued a new regulation (Ministerial Regulation Re: Designation of Type, Kind, and Size of Factories (No. 3) B.E. 2567 (2024)), which removes the factory license requirement for electricity generation from solar energy installations on rooftops, roof decks, or any part of a building used for residential or other purposes, regardless of capacity. The new rules took effect on December 28, 2024. Under the previous regulations, solar rooftop installations had to seek approval from the DIW if their capacity exceeded 1,000 kW (1 MW), which added time and administrative costs when adopting renewable energy solutions. Benefits and Further Compliance The updated regulation benefits industrial operators by facilitating faster installation times and lower costs, as solar rooftops can now be installed without the need for prior approval of a factory license from the DIW. Operators can now more easily contribute to environmental sustainability and carbon reduction efforts. Despite the lifting of the factory licensing requirement, other compliance obligations, such as an energy business license (or exemption from an energy business license), a controlled energy production license, and a construction permit, may still apply. Reason for the Change Removing the classification of rooftop or building-installed solar power plants as factories aligns with Thailand’s renewable energy goals and reduces regulatory burdens for industrial operators. Additionally, it supports the achievement of energy policies aligned with the UN’s Sustainable Development Goals and Thailand’s international commitments to reduce greenhouse gas emissions through the participation of all sectors. For further details on how this change affects business operations or to explore strategies for renewable energy implementation, please contact Supasit Boonsanong at [email protected], Charuwan Charoonchitsathian at [email protected], or Phareeya Yongpanich at [email protected].
December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.