Positively Private: Thailand’s Infrastructure Strategic Plan for 2015–2019

Southeast Asia Infrastructure

When the Thai government enacted the Private Investments in State Undertakings Act B.E. 2556 (2013) (PISUA)—a new law regulating public-private partnerships (PPPs) that was designed to streamline and clarify the PPP process and thereby boost private investment, especially in the infrastructure sector—measures were introduced to increase the effectiveness and transparency of the PPP process, something previously unseen in PISUA’s predecessor, the Private Participation in State Undertakings Act B.E. 2535 (1992) (PPSUA).

The provisions of the old PPSUA, which were in effect from 1992 until 2013, were written in a way that allowed for a variety of legal interpretations, thus providing for uncertainty as to which projects were captured within the scope of the law. Although regulations had been issued under the old law which addressed the selection process, many investors still perceived difficulties, which ultimately discouraged them from pursuing participation in PPPs in Thailand. Additionally, the old PPSUA lacked any provisions that would specifically guide the development of PPPs in Thailand, as it did not determine which sectors PPPs would benefit the public and should therefore be promoted.

While the new PISUA—which applies to all projects (except petroleum and mining concessions) with a value of THB one billion (approximately USD 30.5 million) or more—made only incremental changes relative to the older PPSUA in terms of approval procedures, it did set out a much stronger framework for comprehensive planning and quality of public-private ventures. This was evident in the stipulation of regulations on the use of qualified experts and consultants for preparing an independent project appraisal report, as well as sections calling for a PPP Policy Committee, a PPP Fund, and, as a main driver and guideline of PPP policy, a PPP Strategic Plan.

The new law has also established a PPP Development Fund, which is to be used for developing the PPP Strategic Plan, hiring consultants, and helping agencies develop PPPs that are consistent with the plan. Among other matters, the Strategic Plan identifies sectors and specific projects in which PPPs would be of benefit to Thailand, the priority of each, a target for private investment, and a timeframe for implementation. Five-year Strategic Plans are, from now on, to be prepared on a roll-on basis to provide for continual guidance.

The PPP Committee, which is chaired by the Prime Minister and vice-chaired by the Minister of Finance, is now required to work with the State Enterprise Policy Office (SEPO) to prepare a five-year Strategic Plan for PPPs for the Cabinet’s consideration. The SEPO, acting as the secretariat, has the duty to prepare a framework setting out the draft Strategic Plan, goals, target audience, and other details for approval of the PPP Committee. To ensure the plan reflects public needs, the PPP Policy Committee must also hold hearings to obtain input from state agencies and members of the public.

Once the hearings have been held and the Committee has then approved the draft Strategic Plan under consideration of the input from these hearings, it will submit the plan to the Cabinet for approval and promulgation.

In addition, once the Strategic Plan has been published in the Government Gazette, it is binding on state agencies regarding the preparation and approval of projects that fall under the Strategic Plan. Even the Cabinet and the PPP Committee are required to principally adhere to the Strategic Plan when they are making their decision regarding the approval of a project. However, if the Cabinet finds it expedient to revise a Strategic Plan that is already in effect, it does have the right to approve revisions suggested by the PPP Committee, and in such a case, the newly revised Strategic Plan would again have to be published in the Government Gazette to replace the previous one.

The current draft of the Strategic Plan for 2015-2019, which marks the first time such a Strategic Plan for PPPs in Thailand has ever been submitted, completed the public hearing stage in March 2015 and is currently awaiting approval by the Committee to be submitted to the Cabinet. In this draft, it has been stipulated that projects have to be conducted as PPPs in the following six fields: urban mass rail systems, urban toll roads, commercial ports, high-speed rail systems, telecommunication networks, and high-speed Internet systems.

For 15 other fields, the current draft Strategic Plan recommends that the government encourage the participation of private investors, but in these fields, private participation is not mandatory and the relevant state agencies have the right to decide whether they want to use a PPP or whether they would prefer to fund the project entirely by the use of the state budget or the state agency’s budget. In this group are fields such as inter-urban toll roads, solid waste disposal systems, airport management, terminals for transportation, packing, sorting, and distribution of goods, as well as administration, management, and maintenance of common ticketing systems. (For the full list of these 15 fields under group 2, please see “Table 1: PPP Implementation Timeframe” in the attached PDF.)

The current draft Strategic Plan also sets out the timeframes of implementation for most of the PPP fields (for details, please see “Table 1: PPP Implementation Timeframe” in the attached PDF), as well as the estimated investment amount for each field (for details, please see “Table 2: Estimated investment amounts under the Strategic Plan for 2015-2019” in the attached PDF). It now remains to be seen whether this Strategic Plan, once enacted, will indeed become a driving force for increased private investment in Thailand’s state undertakings.

RELATED INSIGHTS​ 

August 12, 2024
With the growing prominence of ESG (Environmental, Social, and Governance) factors, businesses in Vietnam are increasingly recognizing their importance in driving global demand, societal impact, and economic value. A comprehensive acknowledgment of ESG-related legal requirements is critical for investors and companies operating in Vietnam to meet stakeholder expectations and ensure compliance. Our guide provides a basic overview of the rapidly evolving ESG landscape in Vietnam, covering a range of key issues for companies doing business in the country: What is ESG, and what does the ESG legal framework look like in Vietnam? Who needs to follow ESG regulations in Vietnam? What are the benefits of ESG compliance? How can enterprises enhance ESG best practices in Vietnam? Please click on the link below to view the full article.
June 6, 2024
On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly. One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector. Annual payment of land rental Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment. As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning. Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged. Obtaining land Under the Land Law 2024,
June 4, 2024
Thailand’s Department of Mineral Fuels (DMF) is in the process of preparing a notification that will open the application period for onshore petroleum exploration and production rights in the country’s 25th bidding round. The 25th round of bidding will cover nine petroleum blocks, including the northeastern areas (blocks L1/66, L2/66, L3/66, L4/66, L5/66, L7/66, and L9/66) and central areas (blocks L6/66 and L8/66). The DMF estimates that application submissions will commence around the middle of 2024, and the successful bidder will be announced at the end of the same year. Based on previous rounds of bidding, applicants must meet the following key criteria: The applicant is a company with the purpose of carrying out petroleum exploration and production; The applicant commands the necessary assets, machinery, equipment, tools, and specialists to explore for, produce, sell, and dispose of petroleum; The applicant has not abandoned its operations under a concession or been subject to revocation of a concession in Thailand; and None of its personnel, shareholders, directors, or authorized directors is listed as a person who has abandoned its operations under a concession, or has been subject to revocation of a concession in Thailand. If the applicant does not itself possess all the qualifications under (2) above, it must have another government-approved company that possesses all the qualifications under (2) and has a capital or management relationship with the applicant, and the applicant must supply guarantees that the company will make available to the applicant all necessary assets, machinery, equipment, tools, and specialists for the applicant to explore for, produce, sell, and dispose of petroleum. Companies with a vested interest in petroleum exploration and production in Thailand must remain vigilant for updates. The DMF is expected to provide an update and more details on the bidding very soon. For more details
June 4, 2024
As Vietnam continues its rapid economic development, the demand for sustainable and reliable energy sources has never been more critical. Solar power has emerged as a key component of Vietnam’s strategy to diversify its energy portfolio and reduce its carbon footprint. Recent developments of the regulatory framework governing solar power projects in Vietnam, as discussed below, highlight the country’s commitment to renewable energy and its efforts to create a conducive environment for solar power investments. Objectives for the Development of Solar Power Projects On May 15, 2023, the Prime Minister issued Decision No. 500/QD-TTg, approving the National Power Development Plan for 2021-2030 with a vision to 2050 (“PDP VIII”). Following this, on April 1, 2024, the Prime Minister promulgated the Implementation Plan for PDP VIII (“Implementation Plan”). These documents underscore Vietnam’s commitment to promoting renewable energy, particularly solar. They emphasize self-production and self-consumption of solar power, the development of rooftop solar systems, and the promulgation of the direct power purchase mechanism. The integration of solar power with battery storage is also encouraged, contingent upon economic viability. PDP VIII sets ambitious capacity targets for solar power. By 2030, the capacity is projected to reach approximately 12,836 MW, accounting for 8.5% of the total power capacity. This includes 10,236 MW from concentrated solar power and 2,600 MW from self-production and self-consumption solar power. By 2050, the capacity is expected to rise to between 168,594 MW and 189,294 MW, representing 33.0-34.4% of the total power capacity. Additionally, PDP VIII and the Implementation Plan list 27 solar power projects, totaling 4,136.25 MW, slated for implementation after 2030. However, these projects may be advanced under self-production and self-consumption arrangements. Draft Decree on Direct Power Purchase Agreements On April 15, 2024, the Ministry of Industry and Trade (“MOIT”) released a draft decree on direct power