Positively Private: Thailand’s Infrastructure Strategic Plan for 2015–2019

Southeast Asia Infrastructure

When the Thai government enacted the Private Investments in State Undertakings Act B.E. 2556 (2013) (PISUA)—a new law regulating public-private partnerships (PPPs) that was designed to streamline and clarify the PPP process and thereby boost private investment, especially in the infrastructure sector—measures were introduced to increase the effectiveness and transparency of the PPP process, something previously unseen in PISUA’s predecessor, the Private Participation in State Undertakings Act B.E. 2535 (1992) (PPSUA).

The provisions of the old PPSUA, which were in effect from 1992 until 2013, were written in a way that allowed for a variety of legal interpretations, thus providing for uncertainty as to which projects were captured within the scope of the law. Although regulations had been issued under the old law which addressed the selection process, many investors still perceived difficulties, which ultimately discouraged them from pursuing participation in PPPs in Thailand. Additionally, the old PPSUA lacked any provisions that would specifically guide the development of PPPs in Thailand, as it did not determine which sectors PPPs would benefit the public and should therefore be promoted.

While the new PISUA—which applies to all projects (except petroleum and mining concessions) with a value of THB one billion (approximately USD 30.5 million) or more—made only incremental changes relative to the older PPSUA in terms of approval procedures, it did set out a much stronger framework for comprehensive planning and quality of public-private ventures. This was evident in the stipulation of regulations on the use of qualified experts and consultants for preparing an independent project appraisal report, as well as sections calling for a PPP Policy Committee, a PPP Fund, and, as a main driver and guideline of PPP policy, a PPP Strategic Plan.

The new law has also established a PPP Development Fund, which is to be used for developing the PPP Strategic Plan, hiring consultants, and helping agencies develop PPPs that are consistent with the plan. Among other matters, the Strategic Plan identifies sectors and specific projects in which PPPs would be of benefit to Thailand, the priority of each, a target for private investment, and a timeframe for implementation. Five-year Strategic Plans are, from now on, to be prepared on a roll-on basis to provide for continual guidance.

The PPP Committee, which is chaired by the Prime Minister and vice-chaired by the Minister of Finance, is now required to work with the State Enterprise Policy Office (SEPO) to prepare a five-year Strategic Plan for PPPs for the Cabinet’s consideration. The SEPO, acting as the secretariat, has the duty to prepare a framework setting out the draft Strategic Plan, goals, target audience, and other details for approval of the PPP Committee. To ensure the plan reflects public needs, the PPP Policy Committee must also hold hearings to obtain input from state agencies and members of the public.

Once the hearings have been held and the Committee has then approved the draft Strategic Plan under consideration of the input from these hearings, it will submit the plan to the Cabinet for approval and promulgation.

In addition, once the Strategic Plan has been published in the Government Gazette, it is binding on state agencies regarding the preparation and approval of projects that fall under the Strategic Plan. Even the Cabinet and the PPP Committee are required to principally adhere to the Strategic Plan when they are making their decision regarding the approval of a project. However, if the Cabinet finds it expedient to revise a Strategic Plan that is already in effect, it does have the right to approve revisions suggested by the PPP Committee, and in such a case, the newly revised Strategic Plan would again have to be published in the Government Gazette to replace the previous one.

The current draft of the Strategic Plan for 2015-2019, which marks the first time such a Strategic Plan for PPPs in Thailand has ever been submitted, completed the public hearing stage in March 2015 and is currently awaiting approval by the Committee to be submitted to the Cabinet. In this draft, it has been stipulated that projects have to be conducted as PPPs in the following six fields: urban mass rail systems, urban toll roads, commercial ports, high-speed rail systems, telecommunication networks, and high-speed Internet systems.

For 15 other fields, the current draft Strategic Plan recommends that the government encourage the participation of private investors, but in these fields, private participation is not mandatory and the relevant state agencies have the right to decide whether they want to use a PPP or whether they would prefer to fund the project entirely by the use of the state budget or the state agency’s budget. In this group are fields such as inter-urban toll roads, solid waste disposal systems, airport management, terminals for transportation, packing, sorting, and distribution of goods, as well as administration, management, and maintenance of common ticketing systems. (For the full list of these 15 fields under group 2, please see “Table 1: PPP Implementation Timeframe” in the attached PDF.)

The current draft Strategic Plan also sets out the timeframes of implementation for most of the PPP fields (for details, please see “Table 1: PPP Implementation Timeframe” in the attached PDF), as well as the estimated investment amount for each field (for details, please see “Table 2: Estimated investment amounts under the Strategic Plan for 2015-2019” in the attached PDF). It now remains to be seen whether this Strategic Plan, once enacted, will indeed become a driving force for increased private investment in Thailand’s state undertakings.

RELATED INSIGHTS​ 

May 19, 2023
On May 15, 2023, Vietnam’s Deputy Prime Minister Tran Hong Ha signed Decision No. 500 of the Prime Minister approving the National Power Development Plan for the period 2021-2030, with a vision to 2050 (“PDP VIII”), following extensive public consultations and multiple rounds of review since the first draft version was circulated in 2021. The plan was approved in the context that in the past few years, a number of large power projects have been behind schedule for operation, while new projects have not been able to be implemented due to waiting for additional planning. PDP VIII is the master plan for the development of the power source and transmission grid at 220kV or higher; services in renewable energy and new energy in Vietnam; and works connecting the power grids of Vietnam and neighboring countries. We set out below some quick updates regarding PDP VIII. 1. Development Targets Key development targets are summarized in the table below: Investors in coal, domestic gas, and LNG projects may need to have a conversion plan ready given the 2050 targets to convert to other sources of energy. 2. Solar Projects A list of 27 solar power projects that were planned for the period of 2021-2030 but which have not been assigned to investors are not allowed to be deployed but can be considered after 2030, except in the case of deployment in the form of self-production and self-consumption (Appendix IV). These projects represent 4,136.25 MW of capacity that will be left on the sidelines until 2030. 3. Hydropower Projects A list of 14 potential hydropower projects can be considered if economic and technical conditions allow for more hydropower development (Appendix III). These projects represent 1,244 MW of capacity that can be added to the hydropower targets for 2030. 4. Projects Prioritized for
March 22, 2023
Attorneys from Tilleke & Gibbins have contributed the Cambodia, Laos, Myanmar, and Vietnam sections to DLA Piper’s Global Government Contracting Country by Country guide, which provides essential information for businesses in 75 jurisdictions on how to source and enter into government contracting opportunities. The guide provides procurement information for jurisdictions in Africa, the Americas, Asia-Pacific, Europe, and the Middle East, and includes information on how to find procurement opportunities, the structure of procurement laws, and in-country resources and relevant publications. Each jurisdictional section includes valuable information on procedures for government tenders, bidding, and contract execution, as well as an overview of the legal and regulatory framework governing government procurement. Businesses can refer to the guide to gain a better understanding of procurement processes and regulations in each jurisdiction, which can help them identify potential opportunities and make informed decisions when pursuing government contracts. The guide’s procurement information for Cambodia, Laos, Myanmar, and Vietnam, combined with the online platform’s comprehensive resources, provides businesses and governments with a valuable tool to navigate the complex regulatory landscape of government contracting in the region. The full Global Contracting Country-by-Country guide is available on the DLA Piper website.
February 20, 2023
On December 20, 2022, the Notification re: Rules, Procedures, and Conditions on Transfer of Energy Licenses of the Thailand Energy Regulatory Commission (ERC) became effective. The notification sets out the new standard and procedure for transferring licenses for energy industry operation. The notable changes in the notification are provided below. Anti-Competition Consideration and Impact Assessment Report In considering the transfer of a license, in addition to ensuring the transferee meets all the qualifications for an applicant for the license, the ERC will consider if the transfer would (1) create a monopoly, reduce or restrict competition, or result in market dominance; (2) affect the contracting parties of the transferors or energy users; or (3) affect energy security or the public interest. In this respect, the vetting process for an application for license transfer would be separated into two different approaches. If the ERC believes that the transfer of the energy license would affect competition, energy users, energy security, or the public interest, the transferor will need to submit an impact assessment report on the license transfer to the ERC. In this regard, the ERC may establish a sub-committee or an independent consultant to contemplate the transfer at the transferor’s expense. However, if the ERC believes that the transfer of license would not lead to any impact, the transferor will not be required to submit the impact assessment. Also, if the license transfer is related to any transactions specified under the ERC’s Regulation re: Rules and Procedures on Merger and Cross-Shareholding in Energy Businesses, B.E. 2565, the ERC can combine the license transfer application with the M&A application. After approval, the ERC might require the transferee to periodically report to the ERC and comply with measures stipulated by the ERC. Therefore, an energy license holder which plans to carry out M&A
February 3, 2023
The Federation of Thai Industries (FTI) announced on January 16, 2023, the opening of registration for carbon credit trading on its Renewable Energy and Carbon Credit Exchange Platform. This new online platform supports the domestic carbon market and provides Thai exporters with the ability to purchase carbon credits, allowing them to address demands from importing nations to conform to carbon emission reduction regulations. This is expected to be a positive step forward for the current practice in Thailand, in which the carbon market operates as a voluntary and unregulated buy-sell platform, free from government regulation. Developed in partnership with the Thailand Greenhouse Gas Management Organization (TGO), the FTI: CC/RE/REC X Platform, or FTIX, is intended to increase the promotion of national carbon credits, renewable energy, and renewable energy certificates, thus improving the country’s efforts to mitigate climate change. Entrepreneurs interested in registering for carbon credit trading on the FTIX can do so through the FTIX website at fti-cc.com. The platform initially supports carbon credit trading through over-the-counter methods. In the near future, the FTIX will be developed to support 100% renewable energy (i.e., RE100 energy) and renewable energy certificate trading. However, the related tax and carbon pricing policies have not yet been issued. The TGO is currently in discussions with the Fiscal Policy Office and the Ministry of Finance regarding fiscal policy for the FTIX. For more information on the FTIX, or on any aspect of renewable energy activities in Thailand, please contact Charuwan Charoonchitsathian at [email protected], Napassorn Lertussavavivat at [email protected], or Ratchapat Triteeyaputranonta at [email protected].