Positively Private: Thailand’s Infrastructure Strategic Plan for 2015–2019

Southeast Asia Infrastructure

When the Thai government enacted the Private Investments in State Undertakings Act B.E. 2556 (2013) (PISUA)—a new law regulating public-private partnerships (PPPs) that was designed to streamline and clarify the PPP process and thereby boost private investment, especially in the infrastructure sector—measures were introduced to increase the effectiveness and transparency of the PPP process, something previously unseen in PISUA’s predecessor, the Private Participation in State Undertakings Act B.E. 2535 (1992) (PPSUA).

The provisions of the old PPSUA, which were in effect from 1992 until 2013, were written in a way that allowed for a variety of legal interpretations, thus providing for uncertainty as to which projects were captured within the scope of the law. Although regulations had been issued under the old law which addressed the selection process, many investors still perceived difficulties, which ultimately discouraged them from pursuing participation in PPPs in Thailand. Additionally, the old PPSUA lacked any provisions that would specifically guide the development of PPPs in Thailand, as it did not determine which sectors PPPs would benefit the public and should therefore be promoted.

While the new PISUA—which applies to all projects (except petroleum and mining concessions) with a value of THB one billion (approximately USD 30.5 million) or more—made only incremental changes relative to the older PPSUA in terms of approval procedures, it did set out a much stronger framework for comprehensive planning and quality of public-private ventures. This was evident in the stipulation of regulations on the use of qualified experts and consultants for preparing an independent project appraisal report, as well as sections calling for a PPP Policy Committee, a PPP Fund, and, as a main driver and guideline of PPP policy, a PPP Strategic Plan.

The new law has also established a PPP Development Fund, which is to be used for developing the PPP Strategic Plan, hiring consultants, and helping agencies develop PPPs that are consistent with the plan. Among other matters, the Strategic Plan identifies sectors and specific projects in which PPPs would be of benefit to Thailand, the priority of each, a target for private investment, and a timeframe for implementation. Five-year Strategic Plans are, from now on, to be prepared on a roll-on basis to provide for continual guidance.

The PPP Committee, which is chaired by the Prime Minister and vice-chaired by the Minister of Finance, is now required to work with the State Enterprise Policy Office (SEPO) to prepare a five-year Strategic Plan for PPPs for the Cabinet’s consideration. The SEPO, acting as the secretariat, has the duty to prepare a framework setting out the draft Strategic Plan, goals, target audience, and other details for approval of the PPP Committee. To ensure the plan reflects public needs, the PPP Policy Committee must also hold hearings to obtain input from state agencies and members of the public.

Once the hearings have been held and the Committee has then approved the draft Strategic Plan under consideration of the input from these hearings, it will submit the plan to the Cabinet for approval and promulgation.

In addition, once the Strategic Plan has been published in the Government Gazette, it is binding on state agencies regarding the preparation and approval of projects that fall under the Strategic Plan. Even the Cabinet and the PPP Committee are required to principally adhere to the Strategic Plan when they are making their decision regarding the approval of a project. However, if the Cabinet finds it expedient to revise a Strategic Plan that is already in effect, it does have the right to approve revisions suggested by the PPP Committee, and in such a case, the newly revised Strategic Plan would again have to be published in the Government Gazette to replace the previous one.

The current draft of the Strategic Plan for 2015-2019, which marks the first time such a Strategic Plan for PPPs in Thailand has ever been submitted, completed the public hearing stage in March 2015 and is currently awaiting approval by the Committee to be submitted to the Cabinet. In this draft, it has been stipulated that projects have to be conducted as PPPs in the following six fields: urban mass rail systems, urban toll roads, commercial ports, high-speed rail systems, telecommunication networks, and high-speed Internet systems.

For 15 other fields, the current draft Strategic Plan recommends that the government encourage the participation of private investors, but in these fields, private participation is not mandatory and the relevant state agencies have the right to decide whether they want to use a PPP or whether they would prefer to fund the project entirely by the use of the state budget or the state agency’s budget. In this group are fields such as inter-urban toll roads, solid waste disposal systems, airport management, terminals for transportation, packing, sorting, and distribution of goods, as well as administration, management, and maintenance of common ticketing systems. (For the full list of these 15 fields under group 2, please see “Table 1: PPP Implementation Timeframe” in the attached PDF.)

The current draft Strategic Plan also sets out the timeframes of implementation for most of the PPP fields (for details, please see “Table 1: PPP Implementation Timeframe” in the attached PDF), as well as the estimated investment amount for each field (for details, please see “Table 2: Estimated investment amounts under the Strategic Plan for 2015-2019” in the attached PDF). It now remains to be seen whether this Strategic Plan, once enacted, will indeed become a driving force for increased private investment in Thailand’s state undertakings.

RELATED INSIGHTS​ 

January 25, 2023
Thailand’s Energy Regulatory Commission (ERC) has issued four new regulations under the Energy Business Act B.E. 2550 (2007) setting forth competition regimes to control both anticompetitive conduct and market structure in the energy business sector. The regulations were published in the Government Gazette on December 19, 2022, and took effect the following day. The key provisions of these ERC competition regulations largely mirror those articulated in the Trade Competition Act B.E. 2560 (2017) and its subordinate legislation. The most significant features of these competition regulations are summarized below. Market Definition Regulation The ERC’s market definition regulation (officially the ERC Regulation re: Market Definition and Relevant Market of Related Energy Services B.E. 2565) outlines the general framework for defining relevant markets in the energy sector. The factors to be taken into consideration include types of energy licenses, geographical areas, competition conditions, and interchangeability of energy services. In the annex to this regulation, the ERC has classified the relevant energy service markets as follows: Power business activities include power generation, power transmission system services, power distribution system services, power distribution services, and power system control services. Natural gas business activities include natural gas transmission through pipelines via natural gas transmission systems, natural gas procurement and wholesale via natural gas distribution systems, natural gas retail via natural gas distribution systems, and storage and regasification of liquefied natural gas. The ERC will review its market definitions and relevant energy service markets from time to time, taking into account changes in technology and competition conditions as well as feedback from public hearings. Market Dominance Regulation Under the ERC’s market dominance regulation (officially the ERC Regulation re: Criteria on Business Operator having a Market Dominance B.E. 2565), the ERC is empowered to proactively determine and declare which license-holding energy business operators have a dominant position
August 31, 2022
Thailand’s Draft Climate Change Act Countries around the world have given significant attention to climate change legislation, with many national, regional, and global attempts to slow the momentum of climate change. The most notable of these multilateral efforts is the Paris Agreement, a legally binding international treaty on climate change currently adopted by 193 parties. Its goal is to limit the global average temperature to well below 2°C (preferably below 1.5°C) above preindustrial levels, and the treaty’s coordinated efforts to combat climate change are much more ambitious than previous global agreements and discussions. Article 4 of the Paris Agreement requires countries to provide “nationally determined contributions” (NDCs), consisting of their action plans for climate action. Thailand, as a party to the Paris Agreement, has put forth an NDC that pledges to achieve an unconditional greenhouse gas (GHG) emission reduction target of 20% from the business-as-usual projection for 2030, with the possibility of increasing that target to 25% subject to adequate and enhanced access to technology development and transfer, financial resources, and other support. To enable the accomplishment of this pledge, Thailand is looking to enact climate change legislation that functions as a key mechanism for domestic climate action. In 2018, the Office of Natural Resources and Environmental Policy and Planning (ONEP) under the Ministry of Natural Resources and Environment was assigned to prepare a draft Climate Change Act. The draft is now complete, and according to news reports it is set to be submitted to the cabinet for further consideration. The draft Climate Change Act lays out Thailand’s action plan for climate change mitigation and adaptation, including emissions reductions. Some of the key sections in the draft law involve citizen rights, the National Climate Change Policy Committee, and a national GHG database. Rights of Citizens The draft establishes the
August 26, 2022
Thailand’s Board of Investment (BOI) has extended its previously announced period for reduction of import duty on imported raw and essential materials for battery manufacturing for electric vehicles and other applications. The BOI’s announcement No. 5/2565 dated August 8, 2022, extended the reduction period to a maximum of five years. The BOI’s promoted activities list includes two battery-manufacturing business activities: Activity 4.8.3.1 – Battery manufacturing Activity 5.2.6.1 – High energy density battery manufacturing Qualifying battery manufacturers who have cell or module manufacturing processes are eligible for 90% import duty reductions on raw and essential materials that cannot be produced in Thailand. These reductions will be available on an annual basis, and are renewable for five years in total—up from the original two years. Existing projects (i.e., those which have the original two-year duration in their BOI certificate) can also benefit from the extension by preparing a project amendment form, along with a clarification letter and supporting documents, for submission to the BOI office. For more details on these customs duty reductions, or on any aspect of investment promotion in Thailand, please contact Charuwan Charoonchitsathian at [email protected] or +66 2056 5657, or Napassorn Lertussavavivat at [email protected] or +66 2056 5662.
August 16, 2022
On July 21, 2022, Vietnam’s Ministry of Industry and Trade (MOIT) submitted Report No. 126/BC-BCT to the Prime Minister regarding the mechanism for transitional wind and solar power projects. In this report, the MOIT proposed some recommendations to explicitly address difficulties for outstanding wind and solar power projects (“Transitional Projects”) which have been developed under the Prime Minister’s Decision No. 13/2020/QD-TTg dated April 6, 2020, on the development of solar power projects (Decision 13) and Decision No. 37/2011/QD-TTg dated June 29, 2011, on the development of wind power projects (Decision 37), as amended by Decision No. 39/2018/QD-TTg dated September 10, 2018 (Decision 39). The Transitional Projects primarily include those which have completed construction but have not yet been put into operation, and those which have been put into operation but for which the power price has not yet been decided, due to missing the deadline set forth under the aforementioned decisions to be eligible for the feed-in-tariff (FIT). In particular, the MOIT has proposed the following key recommendations to the Prime Minister: Mechanism for Transitional Projects The MOIT proposes two options: Option 1: Developers of the Transitional Projects negotiate and sign power purchase agreements (PPA) with Vietnam Electricity (EVN) within the price framework issued by the MOIT in accordance with the Law on Electricity, the Law on Prices, and their subordinate guiding legislation; or Option 2: The Prime Minister formulates a new decision specifying the mechanism for bidding on the purchase of power produced by the Transitional Projects, estimated to be implemented for the time limit of three years and within the price framework issued by the MOIT. Mechanism for future wind and solar power projects The MOIT proposes to apply the mechanism that developers of future wind and solar projects negotiate the power price and sign the PPA