As Thailand, and the world, face the growing COVID-19 crisis, the impact has begun to spread beyond people’s health and into the economy as a whole. While some businesses may be able to move to remote working practices to minimize economic distress, others may require a physical presence that becomes difficult or impossible to maintain, or may face substantial changes to their operations, resulting in hardship or emergency measures.

In this rapidly developing situation, employers may thus find themselves faced with unforeseeable events that require them to take drastic actions related to their workforce. In such instances, it is important that employers know their options. This article identifies some of the more common scenarios that are arising, and what employers in Thailand can do under Thai labor laws when faced with them.

1.  An employee is quarantined by authorities for being in a risk group

The employer does not need to pay wages to the employee during the quarantine period, under the principle of “no work no pay.”

2.  An employee falls ill with COVID-19 and needs to take sick leave

The employer is required by law to pay wages to the employee, but not exceeding 30 days in a year. 

3.  Authorities issue an order requiring the employer’s business to temporarily close down

The employer is not required to pay wages during the closure period ordered by the authorities—again under the principle of “no work no pay.”

4.  The employer decides to temporarily cease operations

If the COVID-19 outbreak critically impacts the employer’s business, for example by causing a greatly reduced number of customers or a greatly decreased amount of purchase orders, and the employer needs to close down the business temporarily or stop production, the employer may apply for a temporary cessation of operations. An example of this would be where an employer has to reduce production by 50 percent and needs to ask employees to work for only three days a week, rather than the normal five. Another example would be where the employer separates employees into groups and assigns each group to work for a certain time and then take time off on a rotating basis.

Under section 75 of the Labor Protection Act (LPA), an employer is entitled to temporarily cease operations, during which time they must pay employees at least 75% of their regular working-day wages, subject to the following conditions:

  • There is a necessity and a significant cause for the employer to take this step, such as the employer’s business being unable to operate as usual.
  • The necessity is not considered to be force majeure  under Thai law. If an event is deemed to have arisen due to a force majeure  event, the employer is entitled to forgo paying wages to employees—this is discussed in more detail below.
  • The employer has to elect whether to seek a temporary cessation of operations on a whole or partial basis.
  • The employer has to inform a labor inspection officer, and the employees, three business days in advance of the intended cessation of operations.
  • The employer has to pay employees throughout the entire period of cessation.
  • The cessation period depends on the situation on a case-by-case basis. Once the previously cited reason for cessation of operations has subsided, making the measure no longer necessary, the employer has to cancel the cessation measure.

The LPA does not indicate what qualifies as a “necessity” for employers to invoke the measure. Thai Supreme Court precedent, however, does offer some guidance, indicating that both (1) a reduction in customer purchase orders and (2) financial difficulties faced by the employer are viewed as situations of necessity. Furthermore, the situation has to be significant and must seriously impact the employer’s business. It cannot be a result of the employer’s own failure to conduct business efficiently.

5.  The employer decides to lay off employees

Under Thai labor law, if the COVID-19 virus impacts the employer’s business to the point that the business cannot operate, the employer may terminate or lay off employees, taking care to observe the following conditions:

  • Employees must be informed of the planned layoffs at least one pay period in advance, in accordance with the LPA. Otherwise, the employer is required to pay remuneration in lieu of advance notice. If relevant employment contracts, collective bargaining agreements (CBA), or work rules state a longer period for informing the employee of layoffs, the employer must comply with the contract or CBA.
  • Statutory severance depends on each employee’s length of service, from 30 days’ pay at the employee’s most recent wage rate for those who have worked with the employer for at least 120 days consecutively, but less than one year; up to 400 days’ pay for employees who have worked with the employer for at least 20 consecutive years.
  • Employers must make necessary remuneration for other benefits under the employment contract, work rules, and laws, such as unused annual leave and so on.

In addition, if the employer has a CBA with a labor union or the employees regarding temporary cessation of operations or layoffs, the employer must abide by the procedures stated in the CBA. Failure to do so could result in the employees claiming violation of the CBA.

6.  Force majeure prevents the employer from paying wages

At present, the court has not taken a clear position on whether the COVID-19 situation is or can result in a force majeure  event, and it is likely to be addressed by the court on a case-by-case basis. Situations arising from events deemed as force majeure , resulting in the employer not being able to operate, enable the employer to withhold all wages from employees.

Force majeure  is described under Thai law as referring to events that a person is not able to protect against, despite taking the appropriate care that should be reasonably expected from him or her in such a situation. Earthquakes and tsunamis are examples of force majeure —for example, the collapse of a factory due to an earthquake, resulting in the employer being unable to operate, would justify withholding of wages.

Interestingly, the Supreme Court has ruled that the following events do not qualify as force majeure :

  • A seasonal wildfire where the party does not undertake any preventive action;
  • A violent storm that usually occurs every season;
  • Flooding of a factory’s premises; and,
  • A factory fire.

However, if the above incidents result in the shutdown of a factory, the employer would still be entitled to apply for temporary cessation of operations under LPA section 75.

While it remains unclear what situations, if any, will constitute force majeure  during the COVID-19 crisis, this is sure to be a topic of dispute between employers and employees in the coming months.

Business Survival Strategies

Although the measures described in this article, such as temporary cessation of business operations and layoffs, may not be the answer to all of an employer’s problems in this current economic crisis, for some it may be a question of survival. Acting prudently to handle these challenges is of utmost importance, which in this case means being fully informed of each potential action before implementing one course or another.

RELATED INSIGHTS​ 

August 11, 2026
Cambodia’s Ministry of Justice has launched a new platform on its official website to publish notices of forced sales issued by each municipal and provincial court of first instance. The platform’s stated purpose is to inform the public and facilitate greater participation in forced-sale auctions conducted in connection with court-ordered enforcement proceedings. How the Platform Works The platform publishes forced-sale notices from courts of first instance across Cambodia’s municipalities and provinces and includes a link where the public can view properties currently subject to forced sale. To participate in a forced-sale auction, individuals can download Khmer-language bidding application forms through links provided on the platform. The form typically requires the applicant’s name, sex, year of birth, identity card number and issue date, and address, together with details identifying the immovable property (including its ownership certificate number), the relevant enforcement case number and date, and the reference to the public auction or tender announcement issued by the court. Completed application forms must be submitted directly to the specific municipal or provincial court that issued the forced sale. For further inquiries about a particular forced sale, interested parties should likewise contact the relevant municipal or provincial court. Forced Sale of Immovable Property in Cambodia The publication of these notices relates to the forced sale procedure for immovable property under Cambodia’s Code of Civil Procedure (CPC). Unlike property seizure by a court, a forced sale is a compulsory execution proceeding—a subsequent enforcement step that arises only after an underlying dispute has been adjudicated and a debtor fails to pay the debt or outstanding amount due under a final and binding judgment or other enforceable title of execution. For the purposes of this procedure, the term “immovable property” under the CPC refers to land, registered buildings, jointly held shares of such property, registered
August 6, 2026
Every month, VAT-registered businesses in Thailand calculate their output and input VAT and file a return to pay the net amount due or claim a refund. Yet a common and costly dispute arises when a business that has paid input VAT to its supplier—and done everything asked of it—later finds that input VAT rejected on the grounds that the tax invoice was issued by “a person not entitled to issue tax invoices.” In these cases, a buyer may have confirmed the supplier’s VAT registration on the Revenue Department’s website, paid through the banking system, received a complete tax invoice, and kept full payment and inventory records. Even so, if the Revenue Department later determines that the supplier did not genuinely make the sale or collected the VAT without remitting it, the department can disallow the input VAT and assess additional tax, surcharge, and penalty—often more than a year after the transaction. A new article from tax and dispute resolution specialists at Tilleke & Gibbins in Bangkok examines how the Revenue Department and the courts approach these disputes, including two recent Supreme Court (Tax Division) decisions confirming that the taxpayer bears the burden of proving a supplier genuinely sold and delivered the goods and received payment. It considers why the VAT registration system offers no legal safe harbor, why the evidentiary burden falls hardest on online and cross-border transactions where buyers and sellers never meet, and how the Revenue Department’s own digital infrastructure could detect non-remitting suppliers at the source rather than shifting the loss to good-faith buyers. The article also sets out practical guidance: how to build a comprehensive “know-your-supplier” file at the time of a transaction, the procedural steps and strict deadlines for challenging a VAT assessment, and why dispute readiness belongs alongside tax planning at the center
July 30, 2026
Thailand’s cabinet has approved a draft ministerial regulation introducing significant changes to the calculation of old-age pension and old-age gratuity benefits under the Social Security Fund. The reform would replace the current pension calculation method with a career average revalued earnings (CARE) model designed to better reflect an individual’s lifetime contributions while supporting the long-term financial sustainability of the Social Security Fund. The changes are also intended to improve fairness and align Thailand’s pension framework with international practices. Key proposed changes under the draft ministerial regulation are outlined below. CARE-Based Formula for Old-Age Pension Calculations Currently, old-age pensions are calculated based on the insured person’s average salary over the preceding 60 months. The proposed regulation would replace this approach with the CARE model, under which pension benefits will be calculated based on earnings throughout an individual’s entire working life. Historical earnings will be revalued to reflect their present value before the pension benefit is calculated. According to the Ministry of Labor, this change is intended to better align pension benefits with an individual’s lifetime contribution history and provide a fairer basis for calculating benefits. Pension Accrual Rate for Contributions Exceeding 180 Months Under the current rules, insured persons who contribute for more than 180 months receive an additional pension accrual of 1.5% for each completed 12-month contribution period, with any remaining months disregarded. The proposed regulation would instead calculate the additional accrual on a monthly basis at a rate of 0.125% of actual monthly contributions; this aims to make pension benefits more accurately reflect the actual duration of each individual’s contribution history. Transitional Protections for Insured Persons The draft regulation includes transitional protections for both existing pension recipients and those who will become eligible within five years of the CARE model taking effect. For existing recipients, the following protections
June 29, 2026
Thailand’s cabinet has approved the draft Act on Liability for Defective Goods, commonly called Thailand’s “Lemon Law.” The Draft Act is currently pending consideration by Parliament. The draft law aims to strengthen buyers’ position in pursuing cases against sellers. While the Civil and Commercial Code offers provisions governing liability for defective goods, it is difficult in practice for buyers to successfully make a claim against sellers, particularly where defects are latent and not discoverable at the time of sale or delivery. By introducing product-specific rules and clearer remedies, the new law is intended to modernize Thailand’s consumer protection framework and align it more closely with international standards, and to help relieve the buyer’s burden of proof against the seller in product liability cases. If enacted, the draft act will take effect 180 days after publication in the Government Gazette, giving businesses a transition period to assess their compliance obligations. This article provides an overview of the key provisions of the draft act and highlights some practical considerations for businesses operating in Thailand. Scope and Key Definitions The draft act applies to sellers—defined as persons who sell goods in the ordinary course of business—and protects buyers, a term defined broadly to include not just the original purchaser but also transferees and successors in title. This expands the class of people who can bring claims. The law does not apply to used goods, live animals, or goods exempted by future ministerial regulation. It also leaves intact any separate warranties, promises, advertisements, or other guarantees a seller has given; those remain enforceable alongside the new statutory rights. General Liability for Defective Goods Sellers are liable for defects that exist at the time of delivery, regardless of whether the seller knew about them. Liability arises where a defect reduces: The benefit intended under