December 7, 2020

Impact of COVID-19 on Commercial Contracts in Thailand: Force Majeure

Informed Counsel

COVID-19 has had an economic impact across a wide range of industries, including hospitality, airlines, automotive, construction, logistics, and more, and many performance obligations on contractual parties have been rendered impossible. However, many others—while certainly more difficult, complicated, or expensive—remain literally or legally possible.

While COVID-19 will continue to have a devastating impact on health and economies globally, governments—including Thailand’s—have implemented preventive and responsive measures in an attempt to mitigate that impact. On May 24, 2020, for example, the Committee for Government Procurement and Supplies Management circulated guidelines for the administration of contracts between private parties during the COVID-19 pandemic, announcing that the COVID-19 pandemic qualifies as a force majeure event. The specific period of force majeure in Thailand began with the government’s announcement of a state of emergency on March 26, 2020. See the previous article for more details on this measure.

As market circumstances continue to evolve along with the impact of COVID-19, companies in Thailand are paying special attention to the role force majeure plays in navigating the various legal implications of commercial contracts during the outbreak.

Force Majeure Clauses under Thai Law   

In the midst of the COVID-19 pandemic many are wondering whether parties will be excused from performance under the doctrine of force majeure, by which parties can be excused from contractual performance that becomes impossible due to an extraordinary or exogenous event.

For contracts that have no force majeure clause, the definition of force majeure under section 8 of the Civil and Commercial Code will automatically be applied. However, parties may negotiate a force majeure clause and establish a course of action to follow in such events of force majeure. This clause can also pertain to things like excuse of liability, right to terminate or revise the contract, and distribution of damages due to force majeure.

Every force majeure clause should be considered and interpreted separately and in light of the contract as a  whole, as the precise terms of that clause will control the outcome. It may be easier to argue COVID-19 has triggered a force majeure clause if the clause expressly includes a pandemic, epidemics, or quarantines as examples of events giving rise to the clause. For example, the WHO categorizing  COVID-19 as a pandemic should lend support to parties seeking to enforce force majeure clauses in contracts that contain the term. In the absence of these examples, a party claiming the benefit of a force majeure clause would first have to demonstrate that COVID-19 is a circumstance that falls within the language of the provision.

Application of Force Majeure

When a company invokes a force majeure clause to excuse its contractual nonperformance, it must show that the contractual obligation in question cannot be performed due to unforeseeable, extraordinary circumstances beyond the company’s control. However, Thai law does not explicitly state that force majeure excuses a contractual party from liability when they cannot perform an obligation.

The party who invokes force majeure will need to establish the following facts:

  • The event that prevents the party from performing the contractual obligation is force majeure and is not caused by the non-performing party;
  • It is not possible to perform the obligation during the force majeure; and
  • After the force majeure event concludes, performance is not possible.

Fulfilling these three factors would make a non-performing party likely to be excused from liability under force majeure. However, force majeure clauses are strictly and narrowly construed, and even if the COVID-19 pandemic or a government order under the state of emergency qualifies as a force majeure event, a party would only be excused if the pandemic or a subsequent order actually delayed or prevented the party from performing.

For example, in Supreme Court Case No. 5353/2552, the defendant purchased chicks and food for chicks from the plaintiff, and agreed to sell the grown chickens back to the plaintiff. The court considered that there were two contracts—one for the sale of chicks and food (with the defendant obligated to pay the price for these items), and the second for the sale of grown chickens from the defendant to the plaintiff. However, the outbreak of avian flu caused the government to order the culling of all chickens in the defendant’s possession. The court considered the avian flu to be a force majeure event, and the culling of the chickens made the defendant’s contractual performance impossible. Thus, the defendant was excused from the contractual obligation to sell the chickens to the plaintiff. However, the defendant’s obligation to pay the price of the chicks and food for chicks (or the monetary obligation) had not been made impossible, so the defendant was held liable for the outstanding price for chicks and their food.

Where performance would likely not be prevented, but merely rendered more difficult or expensive, it would not be excused. Often, the relevant question is whether the additional expense or difficulty would be so great as to make it effectively impossible for the party to perform. From the Thai court’s perspective, having insufficient funds to carry out an obligation is likely not reasonable grounds for releasing a party from a contractual obligation, and raising the issue of force majeure would not help. The court has ruled in many cases that shortage of funds cannot be considered force majeure because the funds should be prepared in the normal course of business.

The Importance of Timing

If force majeure can be demonstrated, the question of when it began will then need to be addressed, but that may not be as simple as one might expect, thanks to the dynamic evolution of COVID-19 and the differences in restrictions across the globe. For example, if performance was to take place in Wuhan, China, the force majeure would commence January 23, 2020, when the central government imposed a lockdown in Wuhan and other cities in Hubei in an effort to quarantine the center of an outbreak. However, if performance was based in Thailand on the same date, it may not be considered impossible because, at that time, the WHO had not yet declared the coronavirus disease a pandemic.

In summary, it is not enough to simply establish force majeure in order to excuse the non-performing party’s liability, as force majeure does not automatically release parties from their contractual liability unless they can establish that the contractual obligation is impossible—something that can have a high burden of proof, and be subject to variation depending on a range of factors.

RELATED INSIGHTS​ 

November 19, 2025
Litigation has its place in resolving business disputes, but it is often time-consuming and costly. In Thailand, a straightforward civil case can take a year or more to reach judgment at first instance, and appeals can extend that timeline further. Court filing fees are tied to the value of the claim, typically amounting to around two percent for claims up to THB 50 million, before accounting for attorney fees, translation costs, expert work, and the internal time that management must devote to the case. Against this backdrop, Thai law provides an alternative pathway for parties to attempt resolution before filing suit, and Thai courts commonly encourage mediation as part of the dispute-resolution process. Specifically, prelitigation mediation is a court-supervised process designed to facilitate confidential settlement discussions at an early stage. Participation is voluntary and requires the consent of both parties. The process does not replace litigation but is available in parallel as an initial step for interested parties. If the parties reach an agreement, the settlement can be recorded as a consent judgment that is directly enforceable in Thailand. If no settlement is reached, the parties retain their full right to proceed with a court claim. Reasons to Consider Prelitigation Mediation Prelitigation mediation can offer several advantages. It may shorten timelines from months or years to just weeks, reduce legal costs, and keep discussions confidential. It also allows parties to pursue practical, business-driven solutions or tailored remedies that address their specific needs—outcomes that may not be available through traditional litigation. To facilitate this process, under Thailand’s Civil Procedure Code, parties may petition the court to initiate prelitigation mediation before filing a suit. If the opposing party agrees, the court appoints a mediator to work with the parties under established mediation rules. In such a scenario, there are no court
November 13, 2025
The Land Department in Thailand’s Ministry of the Interior (MOI) plays a central role in ensuring the stability and legality of real estate transactions in the country. Its core responsibilities include issuing land title deeds, registering transactions (e.g., sales, mortgages, leases), conducting surveys for subdivision or consolidation of land, and providing information and guidance on land and property development laws. These administrative functions secure investor confidence and support transparency in the Thai property market, so any delay can have a significant impact. This is especially true for investors who depend on timely registration to secure or transfer property rights. Delays can create liquidity risks, postpone project timelines, and even reduce Thailand’s attractiveness as a real estate investment destination. This article explores the nature of these challenges, the legal framework governing the timelines for administrative actions, and remedies available under Thai law. Sources of Delay Procedural delays at land offices can arise for a variety of structural and operational reasons. These include approval processes that require several levels of internal review, heavy staff workloads, and occasional communication gaps within the bureaucratic chain. Many processes still rely upon manual documentation, which can prolong administrative steps and increase the likelihood of bottlenecks. Some delays stem from ongoing investigations into the legality of land titles. For example, a land title deed may have an annotation indicating that the title deed is under investigation to verify its legality. Even though this annotation does not legally prohibit the sale or transfer of the land, in practice, most prospective purchasers are reluctant to proceed with a transaction until the annotation is removed. As a result, the land can become effectively illiquid during the investigation period, leading to significant investment delays. While such investigations are essential to maintaining the integrity of Thailand’s land registration system, prolonged inquiries
October 30, 2025
Thailand has introduced a comprehensive overhaul of its tax litigation procedures that will significantly impact how tax disputes are handled. The Regulations for Tax Cases B.E. 2568 (2025) take effect on November 24, 2025, and repeal the prior B.E. 2544 (2001) regulations in full. These regulations support the implementation of the Act on the Establishment of the Tax Court and Tax Case Procedure (No. 3) B.E. 2568 (2025), which expands the Tax Court’s jurisdiction to certain criminal tax matters. Published in the Government Gazette on October 14, 2025, the regulations have been reorganized into three parts covering civil cases, criminal cases, and forms, and are designed to accelerate proceedings, tighten evidentiary discipline, and modernize court operations. Structural Reform and Scope The prior regime governed only civil tax disputes. Under the new framework, the regulations introduce a dedicated chapter for criminal cases alongside updated civil procedures, as the Tax Court now has express authority to adjudicate specified criminal tax offenses. Select mechanisms applied in civil case proceedings, such as electronic communication, recording testimony, and appointing experts, also apply to criminal proceedings mutatis mutandis where they do not conflict with criminal procedure. Civil Cases: Evidence Submission, Deadlines, and Scheduling Parties must submit, together with the witness list, originals of all documentary evidence, media, or electronic data (such as files, USB drives, or CDs), and all physical evidence in the party’s possession. Failure to submit any original within the deadline (see below) results in a loss of the right to adduce that item at trial, subject only to narrow exceptions where submission is impossible due to force majeure or where receipt of the evidence is indispensable to the interests of justice. The practical impact is that parties are now obligated to assemble and verify all original documents and data at the very
October 24, 2025
The Thai Arbitration Institute (TAI), a division of Thailand’s Office of the Judiciary, has taken a step toward harmonizing the tools available for dispute resolution. On August 8, 2025, the institute formally launched the TAI Mediation Center (TAI-MC). Although the amendments to TAI’s Arbitration Rules that will govern the TAI-MC have not yet been finalized, the framework now under consideration suggests that TAI is positioning itself to become a more attractive venue for commercial dispute resolution. In the regime contemplated under the current version of the amendments, TAI proceedings will adopt an “arbitration-annexed mediation” mechanism—commonly termed the “Med-Arb” model—while preserving the procedural safeguards indispensable to arbitral neutrality. Mediation will be entrusted to a separate, dedicated mediator appointed under the TAI-MC who is precluded from serving on the arbitral tribunal in the same matter. By clearly separating the functions of mediator and arbitrator, the institute eliminates any risk that confidential information disclosed during mediation could influence the adjudicatory outcome if the parties do not settle. Only when all parties subsequently make a request may that same mediator assume arbitral duties in the case. The parties will retain substantial autonomy in selecting the mediator. They may either designate a mediator by mutual consent or invite the TAI-MC to appoint one from its authorized panel. TAI has announced its intention to curate that panel with particular emphasis on commercial expertise and cross-cultural negotiation skills, supplemented by ongoing professional training. Where the parties cannot agree on remuneration, the mediator’s fee will default to a tariff comparable to the TAI-MC’s cost schedule, which under the current version of the amendments will be approximately THB 45,000 for disputes in which the aggregate claims do not exceed THB 10 million, with incremental increases tied to higher claim values. This predictable cost matrix is aimed at enhancing