December 7, 2020

Impact of COVID-19 on Commercial Contracts in Thailand: Force Majeure

Informed Counsel

COVID-19 has had an economic impact across a wide range of industries, including hospitality, airlines, automotive, construction, logistics, and more, and many performance obligations on contractual parties have been rendered impossible. However, many others—while certainly more difficult, complicated, or expensive—remain literally or legally possible.

While COVID-19 will continue to have a devastating impact on health and economies globally, governments—including Thailand’s—have implemented preventive and responsive measures in an attempt to mitigate that impact. On May 24, 2020, for example, the Committee for Government Procurement and Supplies Management circulated guidelines for the administration of contracts between private parties during the COVID-19 pandemic, announcing that the COVID-19 pandemic qualifies as a force majeure event. The specific period of force majeure in Thailand began with the government’s announcement of a state of emergency on March 26, 2020. See the previous article for more details on this measure.

As market circumstances continue to evolve along with the impact of COVID-19, companies in Thailand are paying special attention to the role force majeure plays in navigating the various legal implications of commercial contracts during the outbreak.

Force Majeure Clauses under Thai Law   

In the midst of the COVID-19 pandemic many are wondering whether parties will be excused from performance under the doctrine of force majeure, by which parties can be excused from contractual performance that becomes impossible due to an extraordinary or exogenous event.

For contracts that have no force majeure clause, the definition of force majeure under section 8 of the Civil and Commercial Code will automatically be applied. However, parties may negotiate a force majeure clause and establish a course of action to follow in such events of force majeure. This clause can also pertain to things like excuse of liability, right to terminate or revise the contract, and distribution of damages due to force majeure.

Every force majeure clause should be considered and interpreted separately and in light of the contract as a  whole, as the precise terms of that clause will control the outcome. It may be easier to argue COVID-19 has triggered a force majeure clause if the clause expressly includes a pandemic, epidemics, or quarantines as examples of events giving rise to the clause. For example, the WHO categorizing  COVID-19 as a pandemic should lend support to parties seeking to enforce force majeure clauses in contracts that contain the term. In the absence of these examples, a party claiming the benefit of a force majeure clause would first have to demonstrate that COVID-19 is a circumstance that falls within the language of the provision.

Application of Force Majeure

When a company invokes a force majeure clause to excuse its contractual nonperformance, it must show that the contractual obligation in question cannot be performed due to unforeseeable, extraordinary circumstances beyond the company’s control. However, Thai law does not explicitly state that force majeure excuses a contractual party from liability when they cannot perform an obligation.

The party who invokes force majeure will need to establish the following facts:

  • The event that prevents the party from performing the contractual obligation is force majeure and is not caused by the non-performing party;
  • It is not possible to perform the obligation during the force majeure; and
  • After the force majeure event concludes, performance is not possible.

Fulfilling these three factors would make a non-performing party likely to be excused from liability under force majeure. However, force majeure clauses are strictly and narrowly construed, and even if the COVID-19 pandemic or a government order under the state of emergency qualifies as a force majeure event, a party would only be excused if the pandemic or a subsequent order actually delayed or prevented the party from performing.

For example, in Supreme Court Case No. 5353/2552, the defendant purchased chicks and food for chicks from the plaintiff, and agreed to sell the grown chickens back to the plaintiff. The court considered that there were two contracts—one for the sale of chicks and food (with the defendant obligated to pay the price for these items), and the second for the sale of grown chickens from the defendant to the plaintiff. However, the outbreak of avian flu caused the government to order the culling of all chickens in the defendant’s possession. The court considered the avian flu to be a force majeure event, and the culling of the chickens made the defendant’s contractual performance impossible. Thus, the defendant was excused from the contractual obligation to sell the chickens to the plaintiff. However, the defendant’s obligation to pay the price of the chicks and food for chicks (or the monetary obligation) had not been made impossible, so the defendant was held liable for the outstanding price for chicks and their food.

Where performance would likely not be prevented, but merely rendered more difficult or expensive, it would not be excused. Often, the relevant question is whether the additional expense or difficulty would be so great as to make it effectively impossible for the party to perform. From the Thai court’s perspective, having insufficient funds to carry out an obligation is likely not reasonable grounds for releasing a party from a contractual obligation, and raising the issue of force majeure would not help. The court has ruled in many cases that shortage of funds cannot be considered force majeure because the funds should be prepared in the normal course of business.

The Importance of Timing

If force majeure can be demonstrated, the question of when it began will then need to be addressed, but that may not be as simple as one might expect, thanks to the dynamic evolution of COVID-19 and the differences in restrictions across the globe. For example, if performance was to take place in Wuhan, China, the force majeure would commence January 23, 2020, when the central government imposed a lockdown in Wuhan and other cities in Hubei in an effort to quarantine the center of an outbreak. However, if performance was based in Thailand on the same date, it may not be considered impossible because, at that time, the WHO had not yet declared the coronavirus disease a pandemic.

In summary, it is not enough to simply establish force majeure in order to excuse the non-performing party’s liability, as force majeure does not automatically release parties from their contractual liability unless they can establish that the contractual obligation is impossible—something that can have a high burden of proof, and be subject to variation depending on a range of factors.

RELATED INSIGHTS​ 

March 9, 2026
Over the past several years, numerous automobile manufacturers have brought electric vehicles (EVs) to the market and received positive feedback from consumers in Thailand and around the world. EVs have gained popularity due to their lower maintenance costs, reduced energy expenses, and environmental benefits. However, reports have emerged of EVs causing problems such as battery fires, autopilot malfunctions leading to accidents, and safety systems such as brakes engaging automatically under inappropriate conditions. Even when these situations do not cause injury to drivers or passengers, they raise significant concerns for EV manufacturers, importers, and sellers operating in Thailand. These problems may seriously impact businesses if the products are identified as unsafe under Thailand’s Product Liability Act (PLA), officially known as the Liability for Damages Arising from Unsafe Products Act. Under this law, authorities or courts can order business operators to recall products from the market or prohibit their export, import, or sale. To manage and mitigate the risk of being found liable for damages due to an unsafe product under the PLA, EV business operators should be aware of the scope of the law. Potentially Liable Parties The PLA identifies several types of entrepreneurs and business operators—both individuals and entities—as “potentially liable parties” (PLPs) who may be held liable under the law. In the EV context, this could include vehicle manufacturers, battery suppliers, software developers whose systems are integrated into the vehicle, and local importers or distributors. Specifically, the PLA covers: Manufacturers or hirers Importers Sellers of goods for which the manufacturer, hirer, or importer cannot be identified Any other party who uses the name, trade name, trademark, or statements associated with the alleged unsafe products, or acts in a manner that causes them to be perceived as a manufacturer, hirer, or importer Definition of “Product” and “Unsafe Product” The
March 5, 2026
Amid increasing financial globalization, Vietnam’s establishment of an International Financial Center (IFC) represents a strategic initiative to attract high-quality foreign investment and enhance the country’s position in the global financial system. In support of this objective, a Specialized Court was introduced under Resolution No. 222/2025/QH15 as a dedicated dispute resolution mechanism within the IFC framework. The Specialized Court at the IFC was subsequently operationalized by Law on the Specialized Court No. 150/2025/QH15, effective from January 1, 2026. Organizational Structure of the Specialized Court The Specialized Court at the IFC is a court within the system of the People’s Courts, organized and operating in accordance with the Law on the Specialized Court, and vested with jurisdiction to adjudicate and resolve cases at the IFC. The Specialized Court is located in Ho Chi Minh City and comprises (i) a Court of First Instance; (ii) a Court of Appeal, and (iii) a supporting apparatus. Jurisdiction of the Specialized Court The jurisdiction of the Specialized Court at the IFC is strictly defined based on both (i) the subject matter of the cases and (ii) the membership status of the parties involved. Specifically, the Specialized Court has jurisdiction over (except for cases involving public interests or the interests of the state) the following: Disputes arising from investment and business activities. Requests for recognition and enforcement in Vietnam of judgments and decisions of foreign courts and foreign arbitral awards. Requests related to dispute resolution by arbitration. Other disputes directly related to investment and business activities (to be specified by the Supreme People’s Court). Additionally, at least one party in the case must be a member of the IFC. The IFC’s membership status is established through registration, recognition as a member, or the grant of a license for establishment and operation within the IFC. In the
February 25, 2026
In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions. Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam. While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam. What’s New? Article 86.2 of the 2025 Law on Construction provides (emphasis added): “Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.” This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2. Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the
February 20, 2026
Thailand’s Supreme Administrative Court has issued a decisive ruling annulling the Ministry of Labor’s notification that had granted an exemption for foreign pilots to fly domestic routes under wet‑lease arrangements. A wet lease is a leasing arrangement in which the aircraft is provided together with its foreign flight crew, including pilots, and related operational support, rather than the airline supplying its own pilots. The judgment, delivered on November 17, 2025, and published in the Government Gazette on January 30, 2026, follows a legal challenge brought by the Thai Pilots Association, which argued that the exemption unlawfully enabled foreign workers to assume a role traditionally reserved for Thai nationals. The notification in question, dated December 13, 2024, authorized foreign pilots who came as part of wet‑leased aircraft to fly domestic routes. The Thai Pilots Association disputed the legality of this rationale, asserting that the exemption was triggered by a private airline’s request rather than by any statutory necessity. The Ministry of Labor justified this measure by relying on aircraft‑specific approvals issued by the Ministry of Transport and by enabling the Department of Employment to issue corresponding work permits. Arguments Presented in the Case The Thai Pilots Association argued that the exemption undermined the interests of domestic pilots and conflicted with the policy intent of Thailand’s foreign‑worker regulatory framework. The lawsuit emphasized that the notification arose directly from a private airline company’s request to operate two A320 aircraft under a wet lease and that the measure had the practical effect of displacing Thai pilots who remained unemployed. Meanwhile, the Ministry of Labor defended the exemption as a temporary and necessary response to industry shortages and part of national efforts to support tourism and restore aviation capacity. Legal Framework Thai law establishes a general prohibition against foreign nationals piloting domestic aircraft. Section