Decommissioning Offshore Oil and Gas Installations in Thailand

Informed Counsel

Thailand’s Ministry of Energy promulgated the Ministerial Regulation Prescribing Plan and Estimated Cost and Security for Decommissioning of Installations Used in the Petroleum Industry B.E. 2559 (2016) earlier this year. As the specific rules and procedures governing the end of the life cycle for upstream petroleum projects had been somewhat uncertain, the decommissioning regulation adds a great deal of clarity on legal obligations for concessionaires.

Unlike businesses with perpetual growth potential, upstream petroleum production has a limited project life cycle—since oil and gas are not renewable resources, every project will have a finite timetable. The tail end of the production cycle is also generally when fewer barrels of oil are being produced, which, to the detriment of petroleum producers, coincides with the capital-intensive task of decommissioning various installations.

A common misconception about offshore drilling rigs is that at the end of the production cycle they will retain some monetary value. This seems intuitive, since it can be assumed that, at the very least, the metal which has been used to construct the installations could be melted down for scrap. But these materials have endured the corrosive effects of seawater over several decades, and the logistical expenses of retrieving the salvageable material are extraordinary. The reality is that the decommissioning of offshore rigs is extremely costly and does not generally enable the petroleum producer to realize any return on the physical assets.

Since the costly endeavor of decommissioning will occur precisely at the moment in the production cycle when revenues will be decreasing, petroleum producers and governments must design appropriate procedures to ensure that decommissioning work is properly carried out. Policy issues of major concern for host governments include protecting the environment, minimizing the impact on fisheries, and ensuring that shipping lanes remain clear of any obstacles. Although offshore petroleum production has been occurring around the world for decades, decommissioning is increasing in importance globally as more projects near the end of their life cycles. Accordingly, lawmakers everywhere are still in the process of learning what processes are best employed to achieve the desired policy objectives.

In Thailand, the Petroleum Act was amended in 2007, introducing two sections which provide the Director General of the Department of Mineral Fuels with the authority to prescribe regulations concerning decommissioning activities. Section 80/1 of the Petroleum Act outlines the general rule that the concessionaire will be responsible for decommissioning works, while Section 80/2 is concerned with the requirement of the concessionaire to make a security deposit to ensure that it will be financially responsible for those decommissioning works. The specific procedures, rules, and timelines outlined under Sections 80/1 and 80/2 of the Petroleum Act are to be in accordance with Ministerial Regulations.

The decommissioning regulation requires the concessionaire to submit a Decommissioning Plan (divided into an Initial Decommissioning Plan and a Final Decommissioning Plan), an Estimate of Decommissioning Costs, a Decommissioning Environmental Assessment Report, and a Best Practical Environmental Option Report to the Director General within prescribed timelines.

The obligation of the concessionaire to begin the decommissioning process will be triggered by any of the following:

  1. when the concessionaire does not use the installations continuously for more than one year;
  2. when petroleum reserves of the concession are less than 40 percent of the sum of the accumulated petroleum production and the petroleum reserves;
  3. when the remaining time for petroleum production as specified in the concession is five years; or
  4. if the concessionaire wishes to commence decommissioning activities.

The Estimated Decommissioning Costs and Decommissioning Plan must be audited by authorized third parties based on qualifications prescribed by the Director General and published in the Government Gazette. The Director General has the authority to accept the decommissioning reports or request clarifications and/or amendments if the reports are not in compliance with the prescribed rules.

The concessionaire will be obligated to make a security deposit to the Director General, which may be in the form of cash or a cashier check payable by a bank, Thai government bonds, a letter of guarantee issued by a bank, an irrevocable standby letter of credit, or any other security prescribed by the Director General and announced in the Government Gazette. The security deposit will be for an amount approved by the Director General which must not be less than the Estimated Decommissioning Cost. Failure to make a complete security deposit will result in a written warning from the Director General, and exposure to a surcharge of 2 percent per month of the unpaid amount.

The decommissioning regulation leaves a few rules and procedures open, to be determined later by the Director General. In addition, depending on how the decommissioning regulation is implemented in practice, there may still be room for further minor amendments. In general, the decommissioning regulation provides a great deal of clarity and certainty for petroleum producers working on concessions which are nearing the end of their production lifespan.

RELATED INSIGHTS​ 

June 3, 2024
Nearly a year after Vietnam’s issuance of its National Power Development Plan for 2021-2030, with a vision to 2050 (“PDP VIII”), the Prime Minister issued Decision No. 262/QD-TTg dated April 1, 2024, approving the Implementation Plan for PDP VIII (“Implementation Plan”). Among other contents, the Implementation Plan sets forth the list of prioritized power source projects through 2030, and the capacity of renewable energy sources through 2030, as detailed below. Prioritized Power Source Projects through 2030 The Implementation Plan lists out six types of power source projects prioritized for development through 2023 according to the capacity approved under PDP VIII. They include: Domestic gas-fired power (14,930 MW) LNG-fired power (22,400 MW) Coal-fired power (30,127 MW) Cogeneration power using residual heat, blast furnace gas, and by-products of technological lines in industrial facilities (2,700 MW) Hydropower (29,346 MW) Pumped storage hydropower (2,400 MW) With respect to each type, the Implementation Plan provides details of projects by location and their operational progress. Such information is set out in Schedule III of the Implementation Plan. For power source projects not included in this list, the provincial People’s Committees will consult with the Ministry of Industry and Trade (“MOIT”) and relevant agencies on compliance with the planning prior to appraisal and issuance of in-principle investment approval. Renewable Energy Projects through 2030 The Implementation Plan allocates the capacity of the following renewable energy sources by locality/region: Offshore wind power (6,000 MW) Onshore wind power (21,880 MW) Hydroelectric power (29,346 MW) Biomass electricity (1,088 MW) Electricity produced from waste (1,182 MW) Rooftop solar power for self-production and self-consumption (2,600 MW) Battery storage (300 MW) With respect to each renewable energy source, the Implementation Plan provides a list of certain renewable energy projects through 2030, including the expected life cycle of the projects, and the allocated capacity
April 29, 2024
On November 4, 2021, Cambodia’s Ministry of Mines and Energy (MME) issued a Prakas No. 0305 on Management of the Steam Energy Subsector within the Energy Sector. The prakas aims to regulate steam energy operations, and requires companies wishing to develop, build, install, or operate steam energy to apply for a steam energy license. As this is the first prakas regulating steam energy operations in Cambodia, all relevant companies operating in steam energy must apply for a steam energy license with the MME. Prakas 0305 discusses permits for three types of activities: Development, Construction, Installation, and Operation of Steam Energy. Companies wishing to develop, build, install, and operate steam energy production facilities must first apply for a permit from the MME. Steam Energy Service Provision. Companies wishing to develop, build, install, and operate steam energy for the purpose of supplying steam energy to consumers must apply for a permit for steam energy service provider in addition to a permit for development, construction, installation, and operation of steam energy. Two-in-One Steam Energy and Electricity Production. Companies wishing to develop and operate both steam energy and electricity production activities must also apply for a permit for two-in-one steam energy and electricity production. Companies operating without the necessary permits are subject to a daily fine of KHR 400,000–4,000,000 (approx. USD 100–1,000). In addition, they may face other penalties, including: An order to halt business activities; Permit suspension; Permit revocation; Judicial action; and Other legal measures as the MME deems fit. For more information on regulations and requirements for steam energy licenses in Cambodia, please contact Tilleke & Gibbins at [email protected].
January 25, 2024
Thailand’s Department of Mineral Fuels (DMF) has developed a framework to regulate carbon capture and storage (CCS) and related activities by introducing “carbon business” to the draft amendment to the Petroleum Act B.E. 2514 (1971). CCS involves the capture, treatment, transport, and underground storage of carbon dioxide produced from industrial power generation. The captured carbon can be used to enhance oil recovery, converted into fuel such as methane or DME (dimethyl ether), or converted to higher-value products. In Thailand, various companies have carried out CCS feasibility studies. Carbon Business and Licensing Under the draft amendment to the Petroleum Act, “carbon business” is defined as exploration for purposes of carbon storage or compression of carbon into carbon storage, while “carbon” is defined as carbon dioxide in the state of gas or supercritical fluid generated as a byproduct or captured from other sources and transported for storage. Any concessionaire, product-sharing contractor, or service contract holder that has been granted permission to explore for or produce petroleum under the Petroleum Act can apply for a carbon business license from the director-general of the DMF with the approval of the Petroleum Committee. Licenses are also available to any other parties who meet the eligibility criteria to be prescribed later by a ministerial regulation. Licenses for these parties will be allocated through competitive bidding according to procedures to be announced by the minister of the Ministry of Energy (MOE). In granting a license, the minister of the MOE and the director-general of the DMF will consider the geological suitability of carbon storage, storage systems, surrounding areas of carbon storage, risk of carbon leakage and movement, environmental impacts, and the applicant’s financial potential and ability in environmental management. Responsibilities of Carbon Business Operators Carbon business operators are required to monitor and inspect their installations, structures,
January 10, 2024
On December 15, 2023, the Electricity Authority of Cambodia (EAC) issued a notification requiring all owners of solar power systems to report their systems to their local electricity supplier by January 31, 2024. Systems that have already been reported under existing regulations are exempt from this requirement. Systems that remain unreported after the deadline will be deemed illegal and subject to penalties, including possible disconnection from the national grid. The rationale for the reporting requirement is that the EAC expects to adopt a new solar power regulation soon. Electricite du Cambodge (the main state-owned utility provider in Cambodia) and EAC-licensed private electricity providers are now gathering data on the current use of solar power systems in order to prepare for, adopt, and execute the upcoming regulation. The reporting requirement is to facilitate this gathering of data. The upcoming regulation, planned for early 2024 according to the notification, follows last year’s Prakas No. 159, which contained the Ministry of Mines and Energy’s guidelines and principles for rooftop solar systems. The EAC now needs to issue implementing regulations that are in line with the ministry’s guidelines and principles. Although stand-alone solar power systems that did not have a connection to the national grid were previously not regulated and did not require any authorizations, the EAC is now stating that all types of solar power systems need to adhere to the reporting requirement under the notification. According to the EAC, the upcoming regulation will address all types of systems, and the December 15 notification clearly announces that all types of solar power systems will need to obtain EAC approval under the upcoming regulation. Solar power system operators in Cambodia should report their systems to their local electricity providers by January 31, 2024, to avoid any penalties, while remaining vigilant for the upcoming