Decommissioning Offshore Oil and Gas Installations in Thailand

Informed Counsel

Thailand’s Ministry of Energy promulgated the Ministerial Regulation Prescribing Plan and Estimated Cost and Security for Decommissioning of Installations Used in the Petroleum Industry B.E. 2559 (2016) earlier this year. As the specific rules and procedures governing the end of the life cycle for upstream petroleum projects had been somewhat uncertain, the decommissioning regulation adds a great deal of clarity on legal obligations for concessionaires.

Unlike businesses with perpetual growth potential, upstream petroleum production has a limited project life cycle—since oil and gas are not renewable resources, every project will have a finite timetable. The tail end of the production cycle is also generally when fewer barrels of oil are being produced, which, to the detriment of petroleum producers, coincides with the capital-intensive task of decommissioning various installations.

A common misconception about offshore drilling rigs is that at the end of the production cycle they will retain some monetary value. This seems intuitive, since it can be assumed that, at the very least, the metal which has been used to construct the installations could be melted down for scrap. But these materials have endured the corrosive effects of seawater over several decades, and the logistical expenses of retrieving the salvageable material are extraordinary. The reality is that the decommissioning of offshore rigs is extremely costly and does not generally enable the petroleum producer to realize any return on the physical assets.

Since the costly endeavor of decommissioning will occur precisely at the moment in the production cycle when revenues will be decreasing, petroleum producers and governments must design appropriate procedures to ensure that decommissioning work is properly carried out. Policy issues of major concern for host governments include protecting the environment, minimizing the impact on fisheries, and ensuring that shipping lanes remain clear of any obstacles. Although offshore petroleum production has been occurring around the world for decades, decommissioning is increasing in importance globally as more projects near the end of their life cycles. Accordingly, lawmakers everywhere are still in the process of learning what processes are best employed to achieve the desired policy objectives.

In Thailand, the Petroleum Act was amended in 2007, introducing two sections which provide the Director General of the Department of Mineral Fuels with the authority to prescribe regulations concerning decommissioning activities. Section 80/1 of the Petroleum Act outlines the general rule that the concessionaire will be responsible for decommissioning works, while Section 80/2 is concerned with the requirement of the concessionaire to make a security deposit to ensure that it will be financially responsible for those decommissioning works. The specific procedures, rules, and timelines outlined under Sections 80/1 and 80/2 of the Petroleum Act are to be in accordance with Ministerial Regulations.

The decommissioning regulation requires the concessionaire to submit a Decommissioning Plan (divided into an Initial Decommissioning Plan and a Final Decommissioning Plan), an Estimate of Decommissioning Costs, a Decommissioning Environmental Assessment Report, and a Best Practical Environmental Option Report to the Director General within prescribed timelines.

The obligation of the concessionaire to begin the decommissioning process will be triggered by any of the following:

  1. when the concessionaire does not use the installations continuously for more than one year;
  2. when petroleum reserves of the concession are less than 40 percent of the sum of the accumulated petroleum production and the petroleum reserves;
  3. when the remaining time for petroleum production as specified in the concession is five years; or
  4. if the concessionaire wishes to commence decommissioning activities.

The Estimated Decommissioning Costs and Decommissioning Plan must be audited by authorized third parties based on qualifications prescribed by the Director General and published in the Government Gazette. The Director General has the authority to accept the decommissioning reports or request clarifications and/or amendments if the reports are not in compliance with the prescribed rules.

The concessionaire will be obligated to make a security deposit to the Director General, which may be in the form of cash or a cashier check payable by a bank, Thai government bonds, a letter of guarantee issued by a bank, an irrevocable standby letter of credit, or any other security prescribed by the Director General and announced in the Government Gazette. The security deposit will be for an amount approved by the Director General which must not be less than the Estimated Decommissioning Cost. Failure to make a complete security deposit will result in a written warning from the Director General, and exposure to a surcharge of 2 percent per month of the unpaid amount.

The decommissioning regulation leaves a few rules and procedures open, to be determined later by the Director General. In addition, depending on how the decommissioning regulation is implemented in practice, there may still be room for further minor amendments. In general, the decommissioning regulation provides a great deal of clarity and certainty for petroleum producers working on concessions which are nearing the end of their production lifespan.

RELATED INSIGHTS​ 

January 3, 2024
Thailand’s Energy Regulatory Commission (ERC) has issued the Notification on the Criteria for Regulating the Licensed Pool Manager B.E. 2566 (2023), which took effect on November 30, 2023. It followed an earlier notification, which took effect on October 13, 2023, that added the new license for the country’s pool gas manager. The new notification aims to regulate natural gas sale agreements and promote competition among players in the regulated natural gas market—that is, those who utilize natural gas for electricity generation under the Electricity Generating Authority of Thailand (EGAT) scheme, including industrial and NGV (natural gas for vehicles) consumers who rely on natural pool gas. The establishment of the pool gas scheme is aimed at encouraging new shippers to enter the market and providing new natural gas shippers with fair opportunities to compete with existing shippers, as all licensed shippers in the regulated market are subject to the same natural gas costs under this new scheme. Under this pool gas scheme, the pool manager plays a critical part in reselling natural gas in the country. Some of its responsibilities include the following: Purchasing natural gas or liquid natural gas (LNG) from licensed shippers in the regulated market at the rate at which the shippers procured the natural gas, including incidental expenses such as pipeline transportation and LNG station fees; Collecting data on the quantity and price of the gas purchased from the licensed shippers and calculating the pool gas price as specified in the ERC-approved manual, which is basically the average price of the natural gas procurement cost of all shippers in the pool; and Reselling natural gas or LNG to licensed shippers at the pool gas pricing rate in the quantity distributed to the pool by each shipper. Apart from its function in facilitating the primary procedures of
December 15, 2023
As part of its membership in Lex Mundi, Tilleke & Gibbins has published an updated edition of its Guide to Doing Business in Thailand for 2023. This guide outlines the key factors for starting and operating a business in the Thai market. Issues covered include: Investment incentives Financial facilities Exchange controls Import and export regulations Structures for doing business Requirements for the Establishment of a Business Operation of the Business Cessation or Termination of the Business Labor legislation, relations, and supply Tax Immigration requirements This publication is part of Lex Mundi’s Country Guides series prepared by member firms in more than 100 jurisdictions worldwide. The guides serve as a useful resource for planning international business strategy and researching new markets. The full Guide to Doing Business in Thailand is available through the button below.
July 25, 2023
Thailand’s Energy Regulatory Commission (ERC) is in the process of reviewing a draft regulation that updates the nationality qualifications for the ultimate shareholders and directors of applicants for an energy business license. The draft ERC Regulation Re: Qualifications, Documents and Application for Electricity Business—which is intended to replace the ERC Regulation Re: Application and Permission for Electricity Business B.E. 2551 and its amendments—is likely to be adopted soon and will affect licensed companies that are foreign majority owned when they apply for or renew their energy business licenses. The draft regulation requires partnerships, limited companies, and public limited companies to have the following qualifications unless there is an international agreement granting national treatment for a specific commitment (mode 3 or mode 4) or exemption by other laws: Juristic persons must be established under Thai law or registered in Thailand with the objective of carrying out electricity business; For private limited companies, foreign ultimate shareholders must not hold more than 49% of the total shares, and the number of the foreign shareholders must not exceed half of all shareholders; At least half of all directors must have Thai nationality; and Any authorized directors must have Thai nationality. When the draft regulation is adopted, it will not take retroactive effect on previously granted energy business licenses, which will continue to be valid until they expire if there is no material change to the license as defined by the draft regulation. Once the license is up for renewal (energy business licenses are normally issued for a specific period of time), it will be subject to the draft regulation. All license applications submitted prior to the effective date of the draft regulation and under consideration will be deemed applications for a license under the draft regulation. As noted above, the new qualification requirements
July 7, 2023
Cambodia has the potential to be one of the top countries in the world for generating renewable energy through solar, based on the average amount of sunlight hours available per day and the consistent sunshine throughout the year. The Cambodian government has recognized this potential and has made major updates to its energy policies in recent years. Solar power is now taking over a much larger portion of the total energy mix in Cambodia, especially as a number of utility-scale solar power plants have come online in recent years. The long-term Power Development Master Plan 2022–2040 sets out the long-term energy policy for Cambodia and requires a bigger role for renewables. The use of solar power will play a key role in this aim to increase the role of renewables, with the plan foreseeing almost 30% of all national power generated through solar technologies by 2040. Two of the latest legislative and regulatory steps by the government are the Ministry of Mines and Energy’s guidelines for rooftop solar systems, and most recently the long-awaited Environment and Natural Resources Code, which was enacted on June 29, 2023. Rooftop Solar Projects Many companies, from small startups to multinationals, are exploring the potential for rooftop solar in Cambodia. However, despite the favorable natural factors, the regulatory framework was not always clear or friendly to rooftop solar, hampering investment. This started slowly changing with the adoption of the first solar energy regulation in 2018, which provided the country’s first official guidance on both solar power plants and rooftop solar. It provided some much-needed clarity, but the 2018 solar energy regulation—and especially the subsequent electricity tariff schemes—often kept rooftop projects from being financially viable. Many players in the industry voiced their doubts about the regulations and tariffs, focusing especially on the capacity charge—a monthly