October 13, 2020

Circular 21 Updates Procedures for Electricity Operating Licenses in Vietnam

On September 9, 2020, Vietnam’s Ministry of Industry and Trade (MOIT) issued Circular No. 21/2020/TT-BCT on the order and procedures for issuance of electricity operating licenses (Circular 21). Circular 21 will take effect on October 26, 2020, replacing Circular No. 36/2018/TT-BCT as amended by Circular No. 15/2019/TT-BCT (together, Circular 36).

The primary purpose of Circular 21 is to promulgate updated forms and templates for the power generation sector, including templates for the electricity operating licenses themselves, requests for granting or amending such licenses, and reports on the status of various electricity activities. One new template is introduced, for the licensing authorities of provinces and municipalities to report on the granting of electricity operating licenses in their locality for the previous year.

Generally speaking, the changes introduced by Circular 21 are minor, and serve mainly to clarify aspects of Circular 36. One notable change is that the regulations on revocation of electricity operating licenses have been removed. Circular 21 also provides a more generous timeline for responding to a request to amend or supplement an application file. In particular, after an applicant receives a request from the licensing agency to amend its application file, it will have 60 business days to make such amendment, whereas such timeline under Circular 36 was not specified for applications submitted to the MOIT and Electricity Regulatory Authority of Vietnam (ERAV) via the public online portal, and was only five business days for applications for which the licensing agency was the provincial people’s committee.

For more information on Circular 21, please contact us at [email protected].

RELATED INSIGHTS​ 

September 1, 2020
With interest in renewable and sustainable energy sources rapidly increasing worldwide, the nations of the Mekong region are beginning to incorporate innovative power generation options into their electrical grids and, more significantly, into their growth plans for the future. As a result, wind energy, formerly one of the least-utilized options in the hydro and solar dominated region, is beginning to see a considerable uptick in interest from investors and governments in the region alike.
August 19, 2020
In order to qualify as a VSPP, a power producer must generate no more than 10 MW per project, and must comply with the requirements and restrictions set by the Executive Committee of Power Purchase from Community Power Plant Projects. Furthermore, prospective VSPPs may only use one of the following:BiomassBiogas from wastewater or wasteBiogas from biofuelA hybrid of biomass or biogas  with solar power
August 19, 2020
On March 2, 2020, the Department of Mineral Fuels (DMF) issued its Notification Re: the Determination of Exploration Blocks for the Bidding for Petroleum Exploration and Production B.E. 2563 (2020). This notification, which repeals the Notification of the Department of Mineral Fuels Re: the Determination of Exploration Blocks for the Bidding for Petroleum Exploration and Production B.E. 2561 (2018), allocates the areas to be used as exploration blocks for the 23rd round of bidding for petroleum and exploration production.