May 30, 2024

Bank Guarantee Disputes in Thai Construction and Procurement Agreements

A bank guarantee or bond is a powerful tool that provides contractual parties with security and assurance. Bank guarantees are commitments made by a bank (as a guarantor) on behalf of a customer (as an obligor) to a beneficiary to ensure that certain contractual obligations will be fulfilled. If the customer fails to comply with these obligations, the bank can compensate the beneficiary up to the amount specified in the bank guarantee.

Bank guarantees are widely used in Thailand as a form of security and are common in construction agreements and government procurement contracts, among others. If the beneficiary (e.g., a project owner) concludes that the counterparty in the agreement (e.g., a contractor) has breached the underlying contract in some way, the beneficiary will demand payment from the bank pursuant to the guarantee.

Collecting on a Guarantee and Preventing Payment

In the context of construction and procurement agreements, there are two types of bank guarantees—conditional and unconditional. A conditional bank guarantee means that the project owner must satisfy certain agreed-upon conditions (e.g., provision of proof of the breach, proof of damages, or even consent from the contractor) to demand payment. An unconditional bank guarantee means that the bank must compensate the project owner for the demanded amount (up to the limit specified in the bank guarantee) without any conditions.

When a project owner concludes that a contractor has breached the underlying contract (often for nonperformance or failure to comply with a representation or warranty), the project owner will demand payment from the bank holding the guarantee. Upon receiving such a demand, Thai banks will usually inform the contractor and ask if it has any objections.

Even if the bank guarantee is unconditional, in practice, a bank may be reluctant to make payment if the contractor, as the bank’s customer, strongly objects. This means that if the contractor disagrees with any insinuation by the project owner that a breach has occurred, and there is a risk that the project owner will demand payment under a bank guarantee, the contractor should clearly voice its objection.

To make an effective objection, the contractor should be aware of the various conditions that are attached to the guarantee. Common conditions in Thailand include requirements that the project owner make a demand through a specific channel or method, or within a specific time-period (e.g., 15 days from the date that the project owner became aware of the breach entitling the project owner to make a demand). The Thai Supreme Court has ruled that this is an essential condition to make a demand, and failing to do so would cost the project owner the entire payment under the bank guarantee.

Furthermore, the breach or other event entitling the project owner to make a demand must occur before the expiry date specified on the bank guarantee. In other words, the bank guarantee must be valid when the breach event occurs. If the guarantee is no longer valid at the date of the breach, the bank should deny any payment request. As such, parties should know the expiry date of the guarantee and plan accordingly.

Lastly, the contractor may carefully and selectively provide an argument, together with necessary and sufficient supporting documents, to claim that the project owner’s payment demand has no merit. A common example is to show that the contractor is actually not in breach and that any payment demand by the project owner is misguided and premature. An effective argument by the contractor can help persuade the bank to hold off on making any payment under the guarantee.

If a contractor’s objection to a bank regarding payment is not effective, then the contractor will usually have to resort to court action. An injunction can potentially stop the project owner from demanding payment from the bank or prevent the bank from making payment to the project owner. A court order is required, and in certain limited circumstances, an injunction may be granted on an emergency basis. This is applicable to both litigation and arbitration proceedings. However, Thai courts are generally reluctant to grant emergency injunctions, and the evidentiary standards are high.

Conclusion

Bank guarantees are often an integral part of Thai legal transactions, such as construction and procurement agreements. When disputes arise, and ideally before they do, the contractor and project owner should be fully aware of any conditions attached to guarantees. Swift action is usually required when a party wants to call a bond. It is generally in the best interest of both contractors and project owners to know their respective legal positions and have a ready-made plan to handle any dispute that may arise involving a bank guarantee.

RELATED INSIGHTS​ 

November 13, 2025
The Land Department in Thailand’s Ministry of the Interior (MOI) plays a central role in ensuring the stability and legality of real estate transactions in the country. Its core responsibilities include issuing land title deeds, registering transactions (e.g., sales, mortgages, leases), conducting surveys for subdivision or consolidation of land, and providing information and guidance on land and property development laws. These administrative functions secure investor confidence and support transparency in the Thai property market, so any delay can have a significant impact. This is especially true for investors who depend on timely registration to secure or transfer property rights. Delays can create liquidity risks, postpone project timelines, and even reduce Thailand’s attractiveness as a real estate investment destination. This article explores the nature of these challenges, the legal framework governing the timelines for administrative actions, and remedies available under Thai law. Sources of Delay Procedural delays at land offices can arise for a variety of structural and operational reasons. These include approval processes that require several levels of internal review, heavy staff workloads, and occasional communication gaps within the bureaucratic chain. Many processes still rely upon manual documentation, which can prolong administrative steps and increase the likelihood of bottlenecks. Some delays stem from ongoing investigations into the legality of land titles. For example, a land title deed may have an annotation indicating that the title deed is under investigation to verify its legality. Even though this annotation does not legally prohibit the sale or transfer of the land, in practice, most prospective purchasers are reluctant to proceed with a transaction until the annotation is removed. As a result, the land can become effectively illiquid during the investigation period, leading to significant investment delays. While such investigations are essential to maintaining the integrity of Thailand’s land registration system, prolonged inquiries
October 30, 2025
Thailand has introduced a comprehensive overhaul of its tax litigation procedures that will significantly impact how tax disputes are handled. The Regulations for Tax Cases B.E. 2568 (2025) take effect on November 24, 2025, and repeal the prior B.E. 2544 (2001) regulations in full. These regulations support the implementation of the Act on the Establishment of the Tax Court and Tax Case Procedure (No. 3) B.E. 2568 (2025), which expands the Tax Court’s jurisdiction to certain criminal tax matters. Published in the Government Gazette on October 14, 2025, the regulations have been reorganized into three parts covering civil cases, criminal cases, and forms, and are designed to accelerate proceedings, tighten evidentiary discipline, and modernize court operations. Structural Reform and Scope The prior regime governed only civil tax disputes. Under the new framework, the regulations introduce a dedicated chapter for criminal cases alongside updated civil procedures, as the Tax Court now has express authority to adjudicate specified criminal tax offenses. Select mechanisms applied in civil case proceedings, such as electronic communication, recording testimony, and appointing experts, also apply to criminal proceedings mutatis mutandis where they do not conflict with criminal procedure. Civil Cases: Evidence Submission, Deadlines, and Scheduling Parties must submit, together with the witness list, originals of all documentary evidence, media, or electronic data (such as files, USB drives, or CDs), and all physical evidence in the party’s possession. Failure to submit any original within the deadline (see below) results in a loss of the right to adduce that item at trial, subject only to narrow exceptions where submission is impossible due to force majeure or where receipt of the evidence is indispensable to the interests of justice. The practical impact is that parties are now obligated to assemble and verify all original documents and data at the very
October 24, 2025
The Thai Arbitration Institute (TAI), a division of Thailand’s Office of the Judiciary, has taken a step toward harmonizing the tools available for dispute resolution. On August 8, 2025, the institute formally launched the TAI Mediation Center (TAI-MC). Although the amendments to TAI’s Arbitration Rules that will govern the TAI-MC have not yet been finalized, the framework now under consideration suggests that TAI is positioning itself to become a more attractive venue for commercial dispute resolution. In the regime contemplated under the current version of the amendments, TAI proceedings will adopt an “arbitration-annexed mediation” mechanism—commonly termed the “Med-Arb” model—while preserving the procedural safeguards indispensable to arbitral neutrality. Mediation will be entrusted to a separate, dedicated mediator appointed under the TAI-MC who is precluded from serving on the arbitral tribunal in the same matter. By clearly separating the functions of mediator and arbitrator, the institute eliminates any risk that confidential information disclosed during mediation could influence the adjudicatory outcome if the parties do not settle. Only when all parties subsequently make a request may that same mediator assume arbitral duties in the case. The parties will retain substantial autonomy in selecting the mediator. They may either designate a mediator by mutual consent or invite the TAI-MC to appoint one from its authorized panel. TAI has announced its intention to curate that panel with particular emphasis on commercial expertise and cross-cultural negotiation skills, supplemented by ongoing professional training. Where the parties cannot agree on remuneration, the mediator’s fee will default to a tariff comparable to the TAI-MC’s cost schedule, which under the current version of the amendments will be approximately THB 45,000 for disputes in which the aggregate claims do not exceed THB 10 million, with incremental increases tied to higher claim values. This predictable cost matrix is aimed at enhancing
October 24, 2025
In Vietnam, litigation is generally treated as a last resort in dispute resolution. Businesses often strive to avoid court proceedings, given the potential for disrupted relationships, higher costs, and lengthy timelines. Yet, litigation is sometimes unavoidable, whether to secure a remedy or respond to a claim. Familiarity with Vietnam’s court system and procedures is therefore crucial for any party involved in such matters. Civil Litigation in Vietnam offers a concise overview of the country’s civil court system and litigation process. The guide a highlights essential points for navigating legal disputes in Vietnam, whether as a plaintiff or a defendant. Tilleke & Gibbins also publishes a similar guide for Thailand. The full Civil Litigation in Vietnam guide is available as a PDF through the button below.