A bank guarantee or bond is a powerful tool that provides contractual parties with security and assurance. Bank guarantees are commitments made by a bank (as a guarantor) on behalf of a customer (as an obligor) to a beneficiary to ensure that certain contractual obligations will be fulfilled. If the customer fails to comply with these obligations, the bank can compensate the beneficiary up to the amount specified in the bank guarantee.

Bank guarantees are widely used in Thailand as a form of security and are common in construction agreements and government procurement contracts, among others. If the beneficiary (e.g., a project owner) concludes that the counterparty in the agreement (e.g., a contractor) has breached the underlying contract in some way, the beneficiary will demand payment from the bank pursuant to the guarantee.

Collecting on a Guarantee and Preventing Payment

In the context of construction and procurement agreements, there are two types of bank guarantees—conditional and unconditional. A conditional bank guarantee means that the project owner must satisfy certain agreed-upon conditions (e.g., provision of proof of the breach, proof of damages, or even consent from the contractor) to demand payment. An unconditional bank guarantee means that the bank must compensate the project owner for the demanded amount (up to the limit specified in the bank guarantee) without any conditions.

When a project owner concludes that a contractor has breached the underlying contract (often for nonperformance or failure to comply with a representation or warranty), the project owner will demand payment from the bank holding the guarantee. Upon receiving such a demand, Thai banks will usually inform the contractor and ask if it has any objections.

Even if the bank guarantee is unconditional, in practice, a bank may be reluctant to make payment if the contractor, as the bank’s customer, strongly objects. This means that if the contractor disagrees with any insinuation by the project owner that a breach has occurred, and there is a risk that the project owner will demand payment under a bank guarantee, the contractor should clearly voice its objection.

To make an effective objection, the contractor should be aware of the various conditions that are attached to the guarantee. Common conditions in Thailand include requirements that the project owner make a demand through a specific channel or method, or within a specific time-period (e.g., 15 days from the date that the project owner became aware of the breach entitling the project owner to make a demand). The Thai Supreme Court has ruled that this is an essential condition to make a demand, and failing to do so would cost the project owner the entire payment under the bank guarantee.

Furthermore, the breach or other event entitling the project owner to make a demand must occur before the expiry date specified on the bank guarantee. In other words, the bank guarantee must be valid when the breach event occurs. If the guarantee is no longer valid at the date of the breach, the bank should deny any payment request. As such, parties should know the expiry date of the guarantee and plan accordingly.

Lastly, the contractor may carefully and selectively provide an argument, together with necessary and sufficient supporting documents, to claim that the project owner’s payment demand has no merit. A common example is to show that the contractor is actually not in breach and that any payment demand by the project owner is misguided and premature. An effective argument by the contractor can help persuade the bank to hold off on making any payment under the guarantee.

If a contractor’s objection to a bank regarding payment is not effective, then the contractor will usually have to resort to court action. An injunction can potentially stop the project owner from demanding payment from the bank or prevent the bank from making payment to the project owner. A court order is required, and in certain limited circumstances, an injunction may be granted on an emergency basis. This is applicable to both litigation and arbitration proceedings. However, Thai courts are generally reluctant to grant emergency injunctions, and the evidentiary standards are high.

Conclusion

Bank guarantees are often an integral part of Thai legal transactions, such as construction and procurement agreements. When disputes arise, and ideally before they do, the contractor and project owner should be fully aware of any conditions attached to guarantees. Swift action is usually required when a party wants to call a bond. It is generally in the best interest of both contractors and project owners to know their respective legal positions and have a ready-made plan to handle any dispute that may arise involving a bank guarantee.

RELATED INSIGHTS​ 

September 25, 2025
In the Thailand contribution to Labor and Employment Disputes 2026, four members of Tilleke & Gibbins’ Bangkok labor and employment team outline key aspects of dispute resolution in Thailand. Their analysis, part of Lexology Panoramic’s comparative guide covering jurisdictions worldwide, addresses the following areas: Pre-action considerations: key requirements, third-party funding, contingency fee arrangements Issuing a claim: forum, territorial jurisdiction, standing, commencing claims, fees, service, defendants and legal personality, types of claims, time limits, counterclaims Case management: procedure, rules, amendments to claims, adding parties, consolidating proceedings, class and collective actions, evidence, witnesses, tactical considerations Interim relief: availability, requirements Trial: hearings conduct and time frames, confidentiality and public access, media reporting, elements of successful claims and burden of proof Alternative dispute resolution: available types, requirements and expectations, enforcement Collective employment and labor rights: enforcement and standing Remedies and enforcement: available remedies, assessing compensation, enforcement mechanisms Appeals: procedure, time frames, other means of challenge Updates and trends: recent cases and developments, technology developments, other issues The complete Thailand chapter can be downloaded below. Tilleke & Gibbins also contributed the Cambodia and Vietnam chapters to Labor and Employment Disputes 2026. Readers can also gain 30 days of complementary access to the full Labor and Employment Disputes 2026 guide and the rest of Lexology Panoramic’s varied offerings through this link.
September 25, 2025
Four of Tilleke & Gibbins’ labor and employment specialists in Phnom Penh have authored the Cambodia chapter of Labor and Employment Disputes 2026, the latest edition of Lexology Panoramic’s global guide to handling labor and employment disputes. The chapter provides practical insights on a wide range of dispute resolution issues, including: Pre-action considerations: key requirements, third-party funding, contingency fee arrangements Issuing a claim: forum, territorial jurisdiction, standing, commencing claims, fees, service, defendants and legal personality, types of claims, time limits, counterclaims Case management: procedure, rules, amendments to claims, adding parties, consolidating proceedings, class and collective actions, evidence, witnesses, tactical considerations Interim relief: availability, requirements Trial: hearings conduct and time frames, confidentiality and public access, media reporting, elements of successful claims and burden of proof Alternative dispute resolution: available types, requirements and expectations, enforcement Collective employment and labor rights: enforcement and standing Remedies and enforcement: available remedies, assessing compensation, enforcement mechanisms Appeals: procedure, time frames, other means of challenge Updates and trends: recent cases and developments, technology developments, other issues The full Cambodia chapter is available for download below. Tilleke & Gibbins also contributed the Thailand and Vietnam chapters to Labor and Employment Disputes 2026. Readers can also gain 30 days of complementary access to the full Labor and Employment Disputes 2026 guide and the rest of Lexology Panoramic’s varied offerings through this link.
September 24, 2025
On September 12, 2025, the Bank of Thailand (BOT) officially released its AI Risk Management Guidelines for Financial Service Providers, building upon the draft guidelines issued in June 2025. The guidelines reflect a balanced approach, encouraging innovation while safeguarding financial stability and consumer protection. The guidelines are targeted at all financial service providers, including financial institutions and special financial institutions under the Financial Institution Business Act, as well as payment providers under the Payment Systems Act. The guidelines apply to both AI systems developed in-house and those developed by third parties that are adopted for use by financial service providers. AI Risk Management Guidelines The two main pillars in managing AI risk are (1) governance of AI system implementation and (2) AI system development and security controls, consisting of the following key elements: 1. Governance Stakeholder roles and responsibilities. Boards and senior management assume accountability for decisions and operations involving AI systems, and are responsible for defining roles and responsibilities for AI oversight. This includes establishing an AI system usage policy, designating personnel responsible for AI risk management, and building awareness of AI-related risk within the organization. Organizations are expected to foster internal capabilities to use AI securely and avoid overreliance that could compromise business continuity or customer service. AI system usage policy. Policies governing AI usage should align with organizational goals, regulatory obligations, and recognized responsible AI frameworks—such as the FEAT principles (fairness, ethics, accountability, and transparency). These policies should be reviewed regularly to respond to technological advancements and evolving risk profiles. Risk management throughout the AI lifecycle. Risk management should encompass the entire AI lifecycle, from establishing risk appetite to implementing continuous risk assessment and control measures tailored to specific use cases. Financial service providers should assess risks and impacts of AI usage on operations and customer services.
September 12, 2025
On September 10, 2025, Vietnam’s National Credit Information Center (CIC) reported to the Vietnam Cybersecurity Emergency Response Team (VNCERT) a suspected significant cybersecurity incident involving unauthorized access to the CIC’s credit information database. A hacker group has claimed responsibility and allegedly posted over 160 million records for sale, including sensitive personal and financial data. Implications for Banks and Financial Institutions Companies that share customers’ or potential customers’ personal data with the CIC for credit scoring or other purposes—and continue to act as a data controller for such data—may be obligated under Vietnam’s Personal Data Protection Decree (PDPD) and related regulations to: Notify A05 (Department of Cybersecurity and High-Tech Crime Prevention) and the State Bank of Vietnam without delay. Inform affected individuals if their personal data is at risk. Recommended Actions Companies that could be impacted by this data breach should take the following actions: Conduct an internal review of CIC-related data in their systems, and identify whether and how the systems have been affected by this incident. Assess whether to notify regulators and customers/potential customers. Enhance cybersecurity controls, monitor for suspicious activity, and implement additional safeguards to prevent secondary breaches.