A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

January 14, 2026
Employers operating in Thailand can enforce post-employment noncompete covenants, but success depends on precise drafting and strong evidentiary support. Thai courts will uphold restraints that protect legitimate employer interests and are fair and reasonable in duration, geographic reach, and substantive scope. Overbroad covenants, however, draw judicial skepticism and may fail unless they are drafted in severable, defensible components tied to the employee’s actual role. This article synthesizes recent trends in Thai case practice, explains how Thai courts assess reasonableness in employment restraints, and provides a practical litigation-focused framework for drafting enforceable covenants, preparing evidence, and pursuing relief through the Labor Court. The Legal Framework and Its Practical Implications Thai courts evaluate noncompete covenants under general principles of contract enforceability and public policy, with particular focus on whether a restraint is necessary to protect a legitimate employer interest and proportionate to that objective. In employment matters, this analysis is shaped by the employee-protective tenor of Thai labor law and by the Labor Court’s equitable discretion in determining appropriate remedies. The practical takeaway is that standardized or broadly drafted covenants rarely survive scrutiny. Courts look for a demonstrable nexus between the employee’s actual exposure to confidential information, trade secrets, or customer relationships and the scope of the restraint. Where that nexus is weak or the restraint operates as a blanket prohibition, courts are inclined to decline enforcement or limit relief to a narrowly tailored prohibition. The employer interests most commonly recognized as legitimate in Thai practice include the protection of trade secrets, confidential business information, and goodwill tied to identifiable customer segments or territories. Courts are more likely to enforce restraints where employers can clearly document what information is at risk, why particular customer relationships matter, and how the employee was involved with those assets. Judges also look closely at the
January 8, 2026
Thailand’s Board of Investment (BOI) has tightened criteria for BOI-promoted companies to own land for residential use and introduced new procedures for land ownership applications under a new notification. Officially titled Notification of the Office of the Board of Investment No. Por. 9/2568 Re: Amended Criteria and Conditions for Permitting Foreign Juristic Persons Receiving Investment Promotion to Own Land for Office and Residence for Operational-Level Workers to Operate Business Granted Investment Promotion, dated July 18, 2025, the new notification was published in the Government Gazette on January 6, 2026, and is applicable to all applications submitted since the date of the notification (July 18, 2025). The new notification introduces an online application process for BOI-promoted companies seeking to own land for office use or residential purposes via the e-Land system, the BOI’s electronic system for land rights and benefits. Applications are reviewed virtually, and any requested amendments or additional documents must be submitted within seven business days. Failure to amend the application or submit any additional requested documents within this period will result in automatic rejection and removal of the application from the system. The new notification builds on the requirements specified in the previous notification on land ownership allowances for foreign companies, issued in 2024, by introducing additional qualification requirements for residences for operational-level workers (i.e., unskilled laborers). In this regard, such a residence must not be: Part of a land development project (housing estate), A condominium unit, or Classified as a house or commercial building.
January 8, 2026
Doing business in Thailand means operating under a strict regulatory framework. From time to time, companies may receive unexpected administrative orders from government authorities that restrict their operations, impose new compliance obligations, or levy fines and penalties. When this happens, a business may challenge the order under Thailand’s administrative law system. The primary concern in pursuing administrative litigation is timing, as strict statutory deadlines apply and missing them can permanently affect a company’s rights. First Step: Administrative Appeal Many companies assume the first step is to immediately bring the matter before the Administrative Court to seek revocation or suspension of the order. Some even attempt to request an interim injunction to stop the order from taking effect. However, Thai law generally requires that the company first challenge the order through an administrative appeal with the same agency that issued it. Only after this process is complete can the matter be taken to court. Seeking an interim injunction at this stage is also not possible. This is because Thai law does not allow a standalone application for an interim injunction; an injunction can only be requested together with the underlying complaint filed with the Administrative Court. Since a court complaint cannot be filed until the administrative appeal process has been exhausted, an injunction is usually not available at the early stage. What Are the Timeframes for Administrative Appeal? Thailand applies a two-stage administrative appeal process. The appeal must first be submitted to the same authority that issued the order, which will review its own decision. If that authority affirms its decision, the appeal is then escalated to the relevant higher authority for further review. In most cases, both stages must be completed before a company is allowed to proceed to court. The timeframe for filing an administrative appeal is very
December 25, 2025
On December 11, 2025, Vietnam’s National Assembly issued Resolution No. 254/2025/QH15 (Resolution No. 254) to address practical difficulties encountered in implementing the Law on Land 2024. The resolution provides specific mechanisms and policies to resolve issues related to land allocation, land leasing, and conversion of land-use purposes, while also addressing land valuation principles, timing of information collection, and land valuation methods. The resolution takes effect on January 1, 2026. Key provisions affecting investors are discussed below. Land Use Terms for Transferred Investment Projects The National Assembly has addressed situations where the remaining term of a transferred investment project is insufficient for the transferee’s business or financial plans. Resolution No. 254, along with the Law on Investment 2025, introduces aligned regulatory solutions. Under the Law on Investment 2025 (4th version submitted to the National Assembly for promulgation), if an investment project implemented prior to March 1, 2026, has been transferred and the transferor holds a Land Use Rights Certificate, has fulfilled all land-related financial obligations, and is not subject to termination, the competent authority may determine a new operating term if the remaining operating term does not meet the transferee investor’s financial or business plan. This adjustment occurs when approving or adjusting the investment policy or issuing or amending the investment registration certificate. The revised operating term is calculated from the date of the approval or issuance and must not exceed the statutory maximum of 70 years for projects in economic zones and 50 years for projects outside economic zones. Resolution No. 254 also permits adjustment of the land use term for transferred investment projects involving land, provided that the transferee investor pays additional land rent in accordance with applicable law, thereby ensuring consistency with the Law on Investment 2025. Land Rent Payment Options Resolution No. 254 generally expands the