A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

December 19, 2025
Prior to the dissolution of the House of Representatives, Thailand’s cabinet approved a draft amendment to the Administrative Procedure Act, following review by the Council of State. If enacted, this reform will fundamentally change how state agencies process business applications and appeals by imposing enforceable timelines and legal consequences for inaction. The draft directly targets a longstanding commercial frustration: applications and appeals that vanish into administrative silence, stalling investment and foreclosing judicial review across sectors ranging from real estate and manufacturing to healthcare and finance. The “Silence Means Yes” Rule for Applications At the core of the reform is a new automatic “approval by implication” for applications subject to statutory processing deadlines. If an official fails to notify an applicant of a decision within the legally prescribed period, the application will be deemed approved as a matter of law. This presumption shifts the costs of delay from businesses to the bureaucracy and gives applicants a definitive legal position once time expires. The mechanism applies to routine licensing and registration matters governed by explicit consideration periods in existing statutes or ministerial regulations. Officials may extend the decision period by up to thirty days, but only if they notify the applicant before the original deadline and substantiate that the delay arises from genuinely exceptional circumstances beyond their control. Certain sensitive applications are expressly excluded from automatic approval, including those that may significantly affect national security or defense, public safety and health, the environment or natural resources, or national cultural heritage. Once the deadline passes without a decision, businesses can proceed with deployment of capital and operations—construction, hiring, procurement, and market entry—without waiting for formal permission that may never arrive. For time-sensitive projects, this materially reduces regulatory timing risk. The “Deemed Rejection” Rule for Appeals The draft introduces a parallel “deemed rejection”
December 16, 2025
Tilleke & Gibbins has contributed the Cambodia, Laos, Myanmar, Thailand, and Vietnam chapters to Infrastructure and Construction in Southeast Asia, a comparative guide developed by Drew Network Asia (DNA). The publication brings together insights from leading ASEAN law firms to address common legal and practical issues faced by participants in the construction and engineering sector across the region. Covering nine major Southeast Asian jurisdictions, the guide provides concise answers to frequently encountered questions relating to infrastructure and construction projects. Topics addressed include the regulatory environment, procurement practices, project structuring, risk allocation, contracting terms, dispute resolution mechanisms, and the enforcement of arbitral awards. Each jurisdictional chapter follows a consistent question-and-answer format, enabling readers to compare legal approaches and market practices across countries. This structure highlights both areas of convergence and key differences between jurisdictions, supporting more informed decision-making in cross-border projects and investments. While the guide offers a practical regional overview, it also underscores that legal frameworks and market practices vary significantly between jurisdictions and may be shaped by local principles and industry norms. Readers seeking jurisdiction-specific advice are encouraged to contact the practitioners listed at the end of each chapter. The full guide is available for download through the button below or directly from the DNA website.
December 15, 2025
On December 10, 2025, the National Assembly of Vietnam officially passed the amended Law on Construction, marking the culmination of a multiyear reform process aimed at modernizing Vietnam’s construction legal framework, streamlining administrative procedures, and aligning with digital transformation and sustainability goals. The amended law, which replaces the current Law on Construction No. 50/2014/QH13, will take effect on July 1, 2026. The Ministry of Construction (MOC) is also preparing several guiding decrees covering project classification, digital submissions and database management, and technical standards for design documentation. Key Changes in the Amended Law While the executed version of the amended Law on Construction has yet to be released to the public, reports have confirmed that it includes the following key changes introduced under the latest draft submitted by the MOC in September: Project classification: The amended Law on Construction classifies construction projects by investment form (public, PPP, business investment, and others), which aligns with the Law on Public Investment, the Law on Investment, and the Law on PPP Investment. This reduces regulatory overlap and clarifies responsibilities. Project preparation and appraisal: The requirement for prefeasibility reports for business investment projects is abolished, as this requirement is now governed by the Law on Investment and the Law on Public Investment. This change shortens the preparation timeline and reduces duplication of procedures. In addition, the authority’s appraisal is streamlined to a single feasibility stage. Also eliminated is the appraisal process conducted following basic design approval, shifting more responsibility to investors and consultants, with targeted post-audit mechanisms for high-risk projects. Construction permits: One of the most significant new changes of the amended Law on Construction is the expansion of exemptions from construction permit requirements to the following eight distinct groups of construction works: State-secret works, emergency or urgent constructions, works under special public investment
December 12, 2025
Similar to other types of corporate disputes, tax-related conflicts often begin with an earnest attempt to resolve matters outside the courtroom. The prospect of engaging in tax litigation can be daunting, given the potential strain on commercial relationships, the legal expenses, and the uncertainty surrounding its resolution. However, there are instances when tax litigation becomes the sole avenue for seeking redress. For individuals and entities contemplating the pursuit of tax-related legal remedies, the Thai legal system offers an accessible, impartial, and equitable platform for dispute resolution. Tilleke & Gibbins’ latest update to Tax Litigation in Thailand provides an outline for navigating tax-related disputes within the Thai legal framework. It aims to equip readers with a fundamental understanding of procedures and practices within the Thai tax litigation landscape. The full guide is available through the button below.