A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

December 12, 2025
Cross-border disputes often end with a judgment or arbitral award issued outside Thailand. When a party has assets or operations in Thailand, the key question becomes simple: will a Thai court enforce it? Thai law treats foreign court judgments and foreign arbitral awards very differently. Foreign court judgments cannot be recognized or enforced directly and must effectively be re-litigated. Foreign arbitral awards, however, benefit from a clear recognition and enforcement process under the New York Convention and Thailand’s Arbitration Act. Thailand’s Overall Approach Thailand does not have a general law or treaty that allows automatic enforcement of foreign court judgments. To rely on a foreign judgment, a party must initiate a new lawsuit in a Thai court, plead the claim under Thai law, and prove the case again. The foreign judgment can be used as evidence, but it is not binding, and the Thai court retains full discretion to reassess both the facts and the law. Foreign arbitral awards are treated more favorably. Thailand is a longstanding member of the New York Convention and has implemented it through the Arbitration Act. The act provides a straightforward process for asking a Thai court to recognize and enforce a qualifying award, without retrying the dispute, and subject only to limited refusal grounds. Foreign Court Judgments: Persuasive but Not Binding Although Thai courts do not recognize or enforce foreign court judgments, they may rely on them as persuasive evidence under certain conditions. Courts generally give more weight to judgments that are final on the merits, issued by a court with proper jurisdiction, and reached after proper notice and an opportunity for the defendant to be heard. Default judgments or rulings based primarily on procedural grounds carry less weight, and the ultimate relevance and weight are left to the court’s discretion. In practical
December 5, 2025
One morning, a California-based company mapping its Southeast Asia rollout opened an unexpected cease-and-desist letter from a Vietnamese IP firm. To the company’s surprise, the letter asserted that a local client already owned the company’s brand in Vietnam and threatened legal action. This is not an isolated incident. In another recent matter in the sports industry, a squatter demanded at least USD 48,000 from our client to “resolve” a similar conflict. For brands entering Vietnam or expanding distribution there, these tactics can create acute risk at precisely the point at which market momentum is building. Vietnam’s rapid economic growth and deepening integration into global trade have made it an increasingly attractive destination for multinational brands. Those same dynamics have intensified a longstanding issue: trademark squatting. Vietnam has modernized its IP framework over the past decade, but its strict first-to-file trademark system continues to incentivize opportunistic filings by parties with no legitimate interest in a mark. As more foreign brands build their reputation abroad before turning to Vietnam, squatters remain alert to timing gaps and enforcement frictions. The First-to-File System: Advantages and Vulnerabilities Vietnam adheres closely to the first-to-file principle under its Law on Intellectual Property. In practice, exclusive trademark rights belong to whoever submits the earliest valid application to the Vietnam Intellectual Property Office, regardless of prior use in Vietnam. This approach offers administrative clarity and reduces evidentiary burdens compared to use-based jurisdictions. Yet it also creates fertile conditions for squatting. Bad-faith actors regularly monitor foreign markets, identify brands gaining traction, and move quickly to register those marks domestically, often long before the genuine owner enters the market or prioritizes local filings. By the time the true brand seeks protection, the squatter’s application (or registration) stands as a legal obstacle, pushing businesses toward costly oppositions, cancellations, or uncomfortable negotiations
December 3, 2025
Attorneys from Tilleke & Gibbins’ Bangkok office have contributed the Thailand chapter to Litigation 2026, published by Chambers and Partners. Litigation 2026 provides an overview of litigation procedures and practices across numerous jurisdictions. The guide is a key reference for businesses, in-house counsel, and legal professionals seeking to understand and compare litigation frameworks around the world. The Thailand chapter delivers analysis of 14 core areas of litigation, including: General characteristics of the legal system and court structure Litigation funding options and requirements Procedures for initiating lawsuits and pre-trial steps Discovery processes and injunctive relief Trial procedures and rules on evidence Settlement mechanisms and enforcement Damages and judgment considerations Appeal processes and cost issues Alternative dispute resolution and arbitration Developments and future outlook for dispute resolution in Thailand Each section offers practical guidance on navigating Thailand’s litigation landscape, providing useful context for international businesses and legal practitioners involved in dispute resolution matters. Chambers and Partners’ Global Practice Guides deliver expert commentary on key practice areas across jurisdictions, allowing readers to compare legislation, procedures, and practical considerations relevant to business operations. The Thailand chapter can be downloaded through the button below, and the full Litigation 2026 guide is available free of charge on the Chambers and Partners website.
December 3, 2025
Thailand’s Civil Court has issued a regulation targeting the use of artificial intelligence (AI) in the preparation of pleadings and other documents submitted to the court. Effective November 17, 2025, the regulation aligns with September 2025 guidance from the president of the Supreme Court, and aims to safeguard accuracy, transparency, and public confidence in civil adjudication. The regulation applies to all parties submitting pleadings or any documents to the Civil Court that are prepared using AI tools or contain AI-generated content. It subjects AI used for these purposes to strict requirements on verification, disclosure, and accountability. Core Obligations The regulation imposes four principal obligations: Lawyers who use AI remain subject to duties of honesty, responsibility to the court, professional standards, and legal ethics, including the duty to assess the appropriateness of the AI tool for the work. Parties and lawyers must verify the accuracy and completeness of all facts, legal provisions, and citations in AI-generated content before submission. Parties and lawyers must disclose to the court any AI-generated content by clearly marking the beginning and end of the AI-generated portion with prescribed statements (see below). Additionally, a certification confirming the use of AI must be provided at the end of the pleading or document, stating that AI was used for certain portions and that the party has reviewed and certifies the accuracy of factual and legal content. Parties and lawyers bear the same full legal and ethical responsibility for AI-generated content as they do for personally authored documents; they cannot evade responsibility or avoid liability by citing AI-related errors. Likewise, parties must ensure that any AI-generated content is truthful, accurate, and unbiased. Prescribed Disclosure Language Each instance of AI-generated content must be preceded by the statement “[The following content was prepared using artificial intelligence]” and must end with “[End