A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

October 15, 2024
The Contract Committee of Thailand’s Office of the Consumer Protection Board (OCPB) has issued the Notification Prescribing the Business of Selling Condominium Units Through Reservations as a Contract-Controlled Business B.E. 2567 (2024). The notification was published in the Government Gazette on October 3, 2024, and is expected to come into effect 120 days after the publication date (i.e., January 31, 2025). This notification aims to prevent condominium project business operators/developers from exploiting consumers. Under the notification, the business of selling condominium units through reservations refers to a business in which a consumer enters into a reservation contract with a business operator to reserve a condominium unit in a condominium building, by paying a reservation fee (or other benefit similar to a reservation fee) that is not a security deposit or down payment, and committing the consumer to enter into a subsequent sales contract to buy the unit. This also extends to the sale of condominium units reserved through electronic channels. The reservation contract must be written in Thai and must include material terms and conditions as specified in the prescribed reservation contract form attached to the Notification (“Standard Reservation Contract”). In addition, the reservation contract must not contain any of the following terms and conditions: Exemption or limitation of the business operator’s liability arising from its breach of contract. The business operator’s right to change the contract or various conditions imposing an additional burden on the consumer, exceeding what was agreed upon at the time the contract was made. The business operator’s right to terminate the contract with the consumer without written notice, or without the material breach of contract by the consumer. The business operator’s right to confiscate all or part of the payment unless the consumer is in breach of the contract. The business operator’s right to
October 2, 2024
As Thailand is a contracting state of the UN Convention on the Recognition and Enforcement of Foreign Arbitral Awards, international arbitral awards can, in principle, be enforced in Thailand. However, not all awards will necessarily be enforceable. The Arbitration Act BE 2545 (2002) gives courts the discretion to deny the enforcement of an award if the court determines that enforcing it would be contrary to “public order or the good morals of the people” (often referred to as “public policy”). Similarly, the Arbitration Act allows a court to set aside a domestic award if its recognition would violate public policy. This discretionary power of the court is prescribed by the law and does not require any party to make an argument on public policy grounds to trigger such power. A recent Supreme Court judgment demonstrates that a court considering an award will review the legality of the arbitral proceedings as well as the content of the award. In this case, the Supreme Court set aside an award on the grounds that it violated public policy because it was the result of arbitration that did not proceed in accordance with the relevant law. Under Thai bankruptcy law, after the Bankruptcy Court accepts a request for rehabilitation of a debtor, all civil proceedings against that debtor, including arbitration proceedings, must be stayed until the court orders otherwise or until the rehabilitation case ceases. In this matter before the Supreme Court, however, the arbitrator continued with the arbitration and went on to render an award even after the court had accepted the request for rehabilitation. The award was later challenged to be set aside on the grounds that continuing with the arbitration was against public policy. While setting aside the award was arguably unnecessary, in this case (as the relevant bankruptcy law
October 1, 2024
Three of Tilleke & Gibbins’ labor and employment specialists in Vietnam have contributed the Vietnam chapter to the newly issued Labor and Employment Disputes 2024, a comprehensive guide from Lexology Panoramic to labor and employment dispute resolution in various jurisdictions around the world. The Vietnam chapter covers the following topics: Pre-action considerations: Key requirements, third-party funding, contingency fee arrangements Issuing a claim: Forum, territorial jurisdiction, standing, commencing claims, fees, service Defendants and legal personality: Types of claims, time limits, counterclaims Case management: Procedure, rules, amendments to claims, adding parties to proceedings, consolidating proceedings Class and collective actions: Special considerations Evidence: Witnesses, tactical considerations Interim relief: Availability, requirements Trial: Hearings conduct and typical time frames, confidentiality and public access, media reporting Elements of successful claims and burden of proof Alternative dispute resolution: Available types, requirements and expectations Enforcement: Collective employment and labor rights, enforcement of collective rights, standing Remedies and enforcement: Available remedies, assessing compensation, enforcement mechanisms Appeals: Appeal procedure and time frames, other means of challenge Update and trends: Recent cases and developments, technology developments, other issues The Vietnam chapter was authored by Truc Thi Thanh, Linh Ngoc Nguyen, and Kien Trung Trinh. Tilleke & Gibbins also contributed the Cambodia and Thailand chapters to Labor and Employment Disputes 2024.
October 1, 2024
Four of Tilleke & Gibbins’ labor and employment specialists in Bangkok have contributed the Thailand chapter to the newly issued Labor and Employment Disputes 2024, a comprehensive guide from Lexology Panoramic to labor and employment dispute resolution in various jurisdictions around the world. The Thailand chapter covers the following topics: Pre-action considerations: Key requirements, third-party funding, contingency fee arrangements Issuing a claim: Forum, territorial jurisdiction, standing, commencing claims, fees, service Defendants and legal personality: Types of claims, time limits, counterclaims Case management: Procedure, rules, amendments to claims, adding parties to proceedings, consolidating proceedings Class and collective actions: Special considerations Evidence: Witnesses, tactical considerations Interim relief: Availability, requirements Trial: Hearings conduct and typical time frames, confidentiality and public access, media reporting Elements of successful claims and burden of proof Alternative dispute resolution: Available types, requirements and expectations Enforcement: Collective employment and labor rights, enforcement of collective rights, standing Remedies and enforcement: Available remedies, assessing compensation, enforcement mechanisms Appeals: Appeal procedure and time frames, other means of challenge Update and trends: Recent cases and developments, technology developments, other issues The Thailand chapter was authored by Eric M. Meyer, Chusert Supasitthumrong, Pathanin Sornchangwat, and Chayathorn Kruatao, all in the Thailand dispute resolution and litigation team. Tilleke & Gibbins also contributed the Cambodia and Vietnam chapters to Labor and Employment Disputes 2024. The full Thailand chapter is available below as a PDF.