A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

August 26, 2024
On July 19, 2024, Cambodia’s Ministry of Land Management, Urban Planning, and Construction (MLMUPC) issued Prakas No. 050 on the Formalities and Procedure for Registration of Private Units in Co-owned Buildings Constructed before December 19, 1997. This new regulation aims to address the lack of clear guidelines for registering units in co-owned buildings constructed prior to 1997 and ensure protection of legal ownership rights for private owners of co-owned buildings constructed before December 19, 1997. Background Cambodia’s real estate market, including co-owned buildings and condominiums, has been experiencing rapid growth. As more individuals acquire separate units in co-owned buildings, the demand for proper registration of each unit has increased. While existing mechanisms like Sub-Decree No. 46 on Systematic Land Registration and Sub-Decree No. 48 on Sporadic Land Registration provide frameworks for registering immovable properties, they do not specifically address the registration procedure for co-owned buildings constructed before 1997. Definition of Co-owned Building A co-owned building contains “private units” exclusively owned by individual co-owners and “common areas” used by all co-owners. This includes various categories such as villas, semi-villas, attached houses, condominiums, and other types of houses with common structures. Application Documents The new prakas introduces a more straightforward documentation process for registering private units in buildings constructed before December 19, 1997, compared to previous regulations (specifically, Sub-Decree No. 126 on the Management and Use of Co-Owned Buildings). The required application documents now include: One copy of application form in Khmer Two copies of certified identification documents for each co-owner Two copies of certified documents of property ownership (if any) Notably, certain documents, such as the internal regulations and detailed architectural plan of the co-owned building, are not required. These more lenient requirements encourage more owners to register their private units, as it makes it easier to secure certificates and
August 20, 2024
Following the enactment of the Tax Administration Law (TAL), Myanmar’s Ministry of Planning and Finance has issued Notification No. 44/2024, which outlines directives and procedures for addressing violations of tax law provisions. These procedures, which came into force on June 13, 2024, primarily focus on three key areas: tax evasion, impeding tax administration, and failure to preserve secrecy. The notification primarily aims to address tax evasion, impeding tax administration, and failure to preserve secrecy, classifying these offenses as either subject to arrest without warrant or not. Notably, tax evasion is classified as an offense subject to arrest without warrant, while impeding tax administration and failure to preserve secrecy are not. The notification also prescribed the forms for notifying taxpayers before taking any action. Tax Evasion Tax evasion refers to a taxpayer who willfully evades the assessment, payment, or collection of tax. Penalties for such offenses include fines of MMK 250,000 (approx. USD 120) or 100% of the evaded tax (whichever is greater), imprisonment for up to seven years, or both. The enforcement process for tax evasion requires the chief officer of the township revenue department or an officer in charge (the tax authority) to assess the relevant documents and information provided by the taxpayer. If a taxpayer is found to be evading tax, the tax authority must send a notice in the prescribed form for verification within 15 days. Taxpayers may apply for a one-time extension of 15 days to submit requested documents and make disclosures. If the taxpayer cannot fulfill the requirements as instructed, the tax authority will seek approval from the director general of the Internal Revenue Department (IRD) for criminal proceedings as cognizable offences. Impeding Tax Administration and Failure to Preserve Secrecy Impeding tax administration refers to obstruction or attempted obstruction of taxation staff or officers
August 15, 2024
Tilleke & Gibbins has contributed the Thailand chapter to the 2024 edition of Litigation & Dispute Resolution from the Global Legal Insights (GLI) series published by Global Legal Group. This comprehensive guide provides detailed analysis of litigation and dispute resolution laws and regulations across multiple jurisdictions worldwide. Each chapter of the guide offers an in-depth examination of key aspects of litigation and dispute resolution, including: Efficiency and integrity of process Privilege and disclosure Evidence Costs and attorney fees Litigation funding Class actions Interim relief Enforcement of judgments/awards Cross-border litigation International arbitration Mediation and ADR Regulatory investigations The complete Thailand chapter, authored by counsel Michael Ramirez and associate Chayathorn Kruatao, is available as a PDF below. The Thailand chapter—and the full Litigation & Dispute Resolution guide—are also freely available on the GLI website.
August 5, 2024
Thailand has continued to face economic challenges since the COVID-19 pandemic, and some businesses have struggled to survive. One of most important measures that indebted businesses in Thailand can take is to file a business rehabilitation petition with the Bankruptcy Court. The Bankruptcy Act B.E. 2483 (1940) provides “automatic stay” measures to protect the debtors that have entered the business rehabilitation process, and during this time creditors have duties and rights under the Bankruptcy Act as well. Once Thailand’s Bankruptcy Court accepts a rehabilitation petition and issues an order for rehabilitation, the debtor is under this automatic stay protection against actions from the creditor to seek debt repayments, and the creditors are only allowed to pursue their debt repayments by submitting a debt repayment application to the official receiver within one month of publication of the plan preparer’s appointment in the Government Gazette. These are general conditions specified in the Bankruptcy Act. However, there are several practical precautions that are not specified in the Bankruptcy Act but that creditors should take during rehabilitation. Below are several steps creditors need to consider taking at various stages of the rehabilitation process. 1. Appointing a local Thai representative to act on behalf of the creditor in the rehabilitation The rehabilitation process requires much more than just submitting the debt repayment application within the fixed one-month period and then waiting for the result. It also involves contacting, meeting, and discussing with the official receiver, plan preparer, other creditors, or debtor representative to investigate or settle any arguments on the debt. Moreover, the language used in all the processes and documents is usually Thai. In practice, creditors—especially foreign creditors—should authorize a Thai attorney or representative through a valid power of attorney (POA) to represent them during all the rehabilitation proceedings. This includes the investigative