Vietnam’s Draft Amended Land Law Introduces Notable Reforms

On August 12, 2025, Vietnam’s Ministry of Agriculture and Environment submitted a draft law amending several provisions of the Land Law 2024 (“Draft Amended Land Law” or “Draft”) for government consultation and public comment. The Draft primarily aims to address three controversial issues in Vietnam’s land regime concerning (i) land pricing, (ii) land clearance, and (iii) the allocation of land outside auctions, following policy set out by Resolution 18-NQ/TW and the newly adopted Resolution 69-NQ/TW on land governance modernization. Land pricing is potentially one of the most important areas among the proposed reforms.

The Draft, however, has notably not addressed a major concern recently raised by the public: When a project has been allocated or leased land, but the relevant authority has not yet issued the land-price decision, a “supplemental charge” continues to accrue for the entire waiting period. Under current rules, this charge is calculated at 5.4% per year on the ultimately determined land-use fee or land rent, materially shifting project economics and pricing risks to developers or end-buyers.

Core Reforms on Land Pricing

The Draft Amended Land Law sets out a number of reforms on land pricing, including the following:

  • Land price tables: The Draft maintains provincial land price tables but clarifies the scope of application: They are used to determine land-related financial obligations of land users and compensation when the state recovers land; the government will detail the adjustment coefficient regime, ratios for land-use fee calculation by land type/user/form, and deductible infrastructure costs. Provincial people’s committees will continue to issue land price tables every five years, effective from January 1 of the first year in the cycle, with authority to supplement within the cycle as necessary. In provinces with cadastral maps and digital land price databases, the tables may be established down to the land-parcel level, aiming to enhance accuracy and market alignment.
  • Annual adjustment coefficient: To enhance responsiveness, the Draft requires provincial people’s committees to promulgate a land price adjustment coefficient annually, effective from January 1 of each year. The committees may also adjust the coefficient within the year or apply it differently for specific areas when required. The Draft aligns cases where coefficients apply with those for the land price tables.
  • Valuation inputs and deductions: Valuation inputs used for preparing land price tables and adjustment coefficients must be based on market data formed within 24 months prior to the approval of the land price table or coefficient project. The Draft also allows deduction of infrastructure construction costs when calculating land use fees or rents, aiming to reduce distortions and more accurately reflect project economics.
  • Appraisal councils: The Draft establishes provincial appraisal councils for land price tables and adjustment coefficients, chaired by the chairperson or a vice chairperson of the provincial people’s committee; the head of the provincial finance authority is vice chair; members include heads of relevant provincial departments and the chairs of commune-level people’s committees where relevant. Councils may set up working groups and hire valuation organizations to advise on appraisals.
  • High-Consensus Mechanism (“75% Rule”): Two options are under consideration for projects assembling land by private agreement where negotiations stall, with the drafting agency proposing the selection of Option 2:
    • Option 1: If either more than 75% by land area, or more than 75% of affected land users by headcount, have agreed, the state may acquire the balance and allocate/lease it to the investor.
    • Option 2: If either more than 75% by land area, or more than 75% of affected land users by headcount, have agreed, and those agreeing account for more than 50% of the project land area, the state may acquire the balance and allocate/lease it to the investor.

Other Notable Reforms

  • Choice of rent-payment modality (transitional clarity): The Draft permits flexibility for projects leasing land to choose between one-off upfront rent or annual rent, with safeguards for public entities managing land used for public interests to lease land with the annual-rent option only. This safeguard aims to prevent leakage of the state’s land budget.
  • Issuance of Land Use Rights Certificates (“LURCs”): The Draft streamlines procedures by allowing simultaneous LURC issuance when the underlying state decision (e.g., conversion or extension) is made, reducing processing time. It also clarifies who has the authority to issue LURCs: in most cases, provincial land-administration offices will handle the process, while commune-level chairs can issue certificates in straightforward cases or in cases serving the public interest.
  • Commercial housing projects: The Draft removes the restriction under Article 127.1(b) of the Land Law 2024, which had confined developers to negotiating only for residential land when conducting site assembly for commercial housing projects. This amendment permits negotiations for other land types in line with planning and subject to land-use conversion procedures where required. Nevertheless, related provisions in Articles 127.3(b) and 127.6 remain unchanged, still referring to “residential land” as the eligible category, which may result in internal inconsistencies and practical uncertainty during implementation.
  • Commune-level planning: Two options are presented; Option 1 replaces district-level planning with commune-level planning and introduces five-year commune plans; Option 2 abolishes commune-level land-use planning altogether (retaining commune five-year plans). The drafting body has expressed a preference for Option 2, aiming to simplify planning layers.
  • Expanded cases of state land recovery: The Draft adds several socio‑economic development cases (e.g., urban renewal; mixed‑use/urban/tourism/service projects; logistics; free‑trade/commercial‑finance centers; “cultural industry” projects) where land may be recovered for the public interest, aiming to unlock stalled large‑scale projects. This sits alongside the 75% mechanism as a complementary path.
  • Early land revocation in special situations: By default, revocation of land follows approval of compensation/resettlement plans. However, for urgent public projects or where the majority has agreed (or on‑site resettlement is feasible), the Draft permits revocation before full completion of such compensation/resettlement plans, while requiring local policies on temporary accommodation.

Opportunities for Investors and Developers

If implemented as drafted, the reforms would be able to improve project timelines and overall predictability for financiers and investors. The availability of five-year tables of land prices, which can possibly be detailed to land-parcel level in provinces with digitalized cadastral systems, would provide better clarity for real estate valuation in Vietnam. The requirement for an annual adjustment factor, operative from January 1 each year and with intra-year revision, is intended to better align the state’s land prices with true market movements, reducing the disparity which traditionally makes the viability of land pricing in Vietnam problematic for many new investors.

In the housing real estate sector, removal of the “residential-only” negotiation constraint enables developers to assemble sites from a wider variety of land types, converting where required and within the law, thereby lessening structuring frictions that previously caused projects to be held up. The proposed “75%” mechanism for preemptive land recovery in high-pressure or high-consensus scenarios could also shake loose the site assembly logjams, shortening timelines on major projects. Finally, more open delegation of LURC-granting authority and more accommodating rent-payment terms (one-time or recurring) should streamline administrative procedures and improve financing possibilities, particularly where more predictable land-fee timetables are important to underwriting.

Challenges for Investors and Developers

Even with these reforms, there is one significant shortfall; The Draft does not address the regime under which projects that have been awarded or leased land, but are still pending a land-price determination, fall under a 5.4% per annum of overdue charges based on the ultimate fee payable for utilizing the land or rent. This overcharge, having built up over decades of administrative delay, remains one of the most important hot topics for both current and near-term transactions.

Moreover, the Draft retains broad provincial discretion over annual adjustment coefficients with the potential to further exacerbate interprovincial divergence in pricing. The functioning of appraisal councils, coupled with the application of market data for the past 24 months, will play a crucial role in informing valuation outcomes, but these tools may struggle to quickly accommodate evolving market conditions. Further, while new land-revocation techniques can accelerate project implementation, they raise risks of execution in compensation and resettlement sequencing and involve proper management of stakeholders.

Finally, transitional projects that lie between the 2024 regime and the new regime will require meticulous refinancing of financing covenants, price-adjustment terms, and land-fee accrual assumptions to cut legal and financial risks down to their barest minimum.

Outlook

The Draft Amended Land Law is scheduled to be submitted to the National Assembly for consideration in late 2025, with a proposed effective date of January 1, 2026. Investors and developers need to stay tuned on how the Draft is finalized in some essential areas. One such area is the scope of cases where land price tables and annual coefficients are to be used. Another is how the annual coefficient should be computed and to what extent its disclosure is transparent. The ultimate form of the “75%” land assembly mechanism also warrants close scrutiny since it may have a material impact on project timetables. The government’s procedures for LURC issuance and planning reform direction will determine whether or not administrative processes are simplified or compounded. Finally, transitional rules will affect current projects, which will need to make provisions for how they move from the current structure to the new regime. Overall, these factors will shape compliance requirements and investment outcome certainty in Vietnam’s land market in the future.

RELATED INSIGHTS​ 

December 15, 2025
On December 10, 2025, the National Assembly of Vietnam officially passed the amended Law on Construction, marking the culmination of a multiyear reform process aimed at modernizing Vietnam’s construction legal framework, streamlining administrative procedures, and aligning with digital transformation and sustainability goals. The amended law, which replaces the current Law on Construction No. 50/2014/QH13, will take effect on July 1, 2026. The Ministry of Construction (MOC) is also preparing several guiding decrees covering project classification, digital submissions and database management, and technical standards for design documentation. Key Changes in the Amended Law While the executed version of the amended Law on Construction has yet to be released to the public, reports have confirmed that it includes the following key changes introduced under the latest draft submitted by the MOC in September: Project classification: The amended Law on Construction classifies construction projects by investment form (public, PPP, business investment, and others), which aligns with the Law on Public Investment, the Law on Investment, and the Law on PPP Investment. This reduces regulatory overlap and clarifies responsibilities. Project preparation and appraisal: The requirement for prefeasibility reports for business investment projects is abolished, as this requirement is now governed by the Law on Investment and the Law on Public Investment. This change shortens the preparation timeline and reduces duplication of procedures. In addition, the authority’s appraisal is streamlined to a single feasibility stage. Also eliminated is the appraisal process conducted following basic design approval, shifting more responsibility to investors and consultants, with targeted post-audit mechanisms for high-risk projects. Construction permits: One of the most significant new changes of the amended Law on Construction is the expansion of exemptions from construction permit requirements to the following eight distinct groups of construction works: State-secret works, emergency or urgent constructions, works under special public investment
November 28, 2025
On November 26, 2025, the government of Vietnam issued Resolution No. 8/2025/NQ-CP to extend and expand the pilot program allowing Vietnamese citizens who meet certain conditions to gamble at three integrated casino resorts in Vietnam: Corona Resorts & Casino Phu Quoc (An Giang Province) – Effective immediately, and continuing an ongoing pilot program that started in 2019. The Grand Casino Ho Tram (Ho Chi Minh City) – New pilot program for five years starting November 26, 2025. Van Don Integrated Casino & Tourism Complex (Quang Ninh Province) – New pilot program for five years from the date the casino receives its license. The pilot program was originally established under Decree No. 03/2017/ND-CP on casino business, which also sets out the specific eligibility conditions for Vietnamese citizens. After the pilot period, these projects must stop allowing Vietnamese players until the government issues further decisions. This expansion of the pilot program comes after Vietnam’s Ministry of Finance (MOF) released a draft decree earlier this year proposing significant changes to the regulatory framework governing casino operations. These revisions, which focus on increasing fiscal contributions from local players and strengthening compliance obligations for casino operators nationwide, are detailed below. Proposed Increase in Casino Entry Fees for Vietnamese Players The draft decree increases the entry fees applicable to Vietnamese citizens permitted to play at casinos. Under the current regulations, Vietnamese players are required to pay an entry fee of VND 1 million (approx. USD 38) for 24 consecutive hours or VND 25 million (approx. USD 950) per month. The draft decree proposes increasing these fees to VND 2.5 million (approx. USD 95) for 24 consecutive hours and VND 50 million (approx. USD 1,900) per month, effectively doubling the existing amounts and marking the first major fee revision since the pilot program allowing Vietnamese players
November 21, 2025
On November 17, 2025, Thailand’s Ministry of Interior introduced significant regulatory changes to make rooftop solar adoption easier and more cost-effective for property owners. Ministerial Regulation No. 72 B.E. 2568 (2025), issued under the Building Control Act B.E. 2522 (1979), was published in the Government Gazette on November 19, 2025, with immediate effect. Background Under the Building Control Act (BCA), any alteration made to a building requires either notification of the relevant authority or application for a building alteration permit—unless the alteration falls under a separate list of exceptions specified in the ministerial regulations issued under the BCA. In 2015, installation of solar rooftops on any residential building under 160 square meters was added to this list of exceptions, subject to inspection and notification requirements. The newly enacted regulation now eliminates many of these requirements and introduces a broader and more permissive framework to promote solar adoption nationwide. Key Changes Specifically, the regulation introduces three major changes: Expanded exemption from the definition of “building alteration”: The installation of solar panels on any building roof—regardless of the type of building or the total area of the installation—is no longer considered a building alteration under the BCA, provided that the total weight of the installation does not exceed 20 kg/m2. Removal of structural integrity certification requirement: The new regulation eliminates the obligation to obtain a structural stability certificate from a licensed civil engineer. Removal of notification requirement: Property owners or possessors are no longer required to notify the local authority before installation of a solar rooftop. Impact This significant streamlining of requirements for solar rooftop installation is expected to accelerate the adoption of renewable energy in the country, particularly for residential and commercial properties—similar to the way Thailand’s December 2024 removal of licensing requirements for factory solar rooftop installations encouraged such
November 14, 2025
Interest in data center land acquisition has increased significantly over the past year, with a notable rise in inquiries from investors seeking to establish digital infrastructure in Thailand. Although the sector is still in its early stages, this emerging wave of development represents a significant shift in Thailand’s technology infrastructure landscape, driven primarily by multinational technology companies and operators looking to expand their regional presence. Project Development The data center sector in Thailand is attracting a diverse range of international investors, though with clear geographic patterns. Most investors are from China, Singapore, and Japan, with some additional interest from countries outside Asia, including the United States and Europe. This investor base consists primarily of multinational tech companies and operators seeking to establish new facilities rather than acquire existing assets. Data center business activities are also a sector promoted by Thailand’s Board of Investment (BOI), which offers investors both tax and nontax privileges as well as exemptions to foreign investment and land-ownership restrictions. Projects currently underway are still largely in the land acquisition and construction phase. Unlike more mature markets where many facilities are operational and generating revenue, the predominant focus in Thailand remains on securing suitable land and beginning the building process. This means that while interest is high and land assembly is accelerating, the sector as a whole has not yet reached the operational phase that will ultimately drive licensing applications and full regulatory compliance. The licensing process itself remains at an early stage, as most projects must first complete their facilities before applying for the specific licenses required from the telecommunications authority. Once the facilities are built, the next critical step will be obtaining these telecommunications licenses, which are mandatory for data center operations. Legal and Regulatory Considerations The complexity of data center development in Thailand requires