Vietnam Issues New Regulations on Building and Operating Golf Courses

In Vietnam, golf is gaining in popularity, and the country is also becoming a popular destination for golfing vacationers. The country has about 35 courses in operation and many more in the pipeline. Most of the courses are found on the outskirts of major cities like Hanoi and Ho Chi Minh City, or near resort areas such as Da Nang, Nha Trang, Vung Tau and Dalat.

New legislation has been passed to help clarify the regime for investment in golf course projects, and to help ensure the prompt completion of projects and efficient use of land. Specifically, On April 27, 2020, the government of Vietnam issued Decree No. 52/2020/ND-CP on investment in construction and commercial operation of golf courses (Decree 52). This decree will come into effect on June 15, 2020.

According to Decree 52, the area of a standard 18-hole golf course must not exceed 90 hectares (not more than 5 hectares per hole, on average), and the area of a newly built golf course project must not exceed 270 hectares (54 holes). The investor must complete the construction of a golf course within a maximum of 36 months for an 18-hole course, or a maximum of 48 months for other types of golf courses, from the date of issuance of the land lease decision.

Moreover, an investor implementing a golf course project must:

  • Satisfy the conditions on financial capacity and the conditions on land lease and/or permission to convert land use purpose for implementing the golf course project in compliance with the laws on land; and pay a deposit for the assurance of project implementation (for cases requiring such deposit) in compliance with the laws on investment;
  • Provide appropriate solutions, plans, and commitments relating to resettlement, training, and employment assistance for the current users of land expected to be used for the golf course project and local laborers; and
  • Ensure the fulfillment of necessary requirements and conditions relating to transport, electricity, and water infrastructure, wastewater treatment, and environmental protection.

Decree 52 also provides a list of types of land which are not permitted to be used for construction of golf courses and auxiliary works, which includes the following:

  • Land used for the purposes of national defense and security;
  • Forest land and rice paddy land (with limited exceptions);
  • Land located in areas containing original constituents of classified cultural and historical sites or classified beauty spots, or relics included in the inventory list of provincial People’s Committees (with limited exceptions);
  • Land for construction of industrial parks, industrial clusters, concentrated IT parks, and high-tech parks;
  • Land located inside the protected areas of dikes and coastal protection corridors in accordance with Law on Dikes and the Law on Natural Resources and Environment of the Sea and Islands.

In addition, investors are prohibited from taking the following actions related to investment in construction and commercial operation of golf courses:

  • Building or operating golf courses without having met the conditions and procedures prescribed by Decree 52 and other related laws;
  • Taking advantage of the operations of golf courses to organize illegal betting or gambling activities;
  • Obstructing or failing to comply with examination and inspection by competent state management agencies in accordance with the law; and
  • Failing to provide information or failing to report as requested by competent state management agencies in accordance with the law.

Golf has been developing quickly in many regions of Vietnam, and it is expected that Decree 52 will help accelerate investment further, while minimizing any negative impacts.

For more details on Decree 52, please contact us at [email protected].

RELATED INSIGHTS​ 

October 28, 2022
The draft regulations referred to below were withdrawn from the legislative process on November 8, 2022.   On October 25, 2022, the Thai cabinet approved in principle a draft version of new ministerial regulations that permit certain types of foreign nationals to acquire land for residential use. These draft ministerial regulations represent an additional scheme that complements the existing ministerial regulations from 2002 prescribing rules, methods, and conditions for foreign nationals’ acquisition of land for residential purposes. These draft ministerial regulations aim to attract to Thailand foreign nationals who invest at least THB 40 million. The targeted foreign nationals consist of four groups: Wealthy individuals; Retirees; Foreign nationals who wish to work from Thailand; and Highly skilled expatriates. These four groups are eligible to acquire up to 1 rai (1,600 square meters) of land for use as their own residence in Bangkok, Pattaya City, a municipal area (khet thetsaban), or a designated residential area under the law governing city planning. The area must be situated outside any designated military safety zone. The THB 40 million minimum investment mentioned above may be any type of investment permitted under the ministerial regulations. Some examples include Thai government bonds, real estate or infrastructure mutual funds, real estate investment trusts (REITs), and share capital of Board of Investment (BOI) promoted entities (or a business eligible for BOI promotion). The investment must have been made before submission of the application for land ownership, and it must be maintained for at least three years. If the qualifications are met, the application for land ownership and the related supporting documents (including a certificate of investment issued by the relevant authorities) must be submitted to the director general of the Land Department for consideration and further submission to the Minister of Interior for approval. If approved, the applicant
August 18, 2022
Practical Law has published an updated online version of Agricultural Law in Thailand, a Q&A-style guide that provides detailed overviews of Thailand’s agriculture laws and regulations. The Thailand overview is one of approximately twenty such guides to jurisdictions worldwide, covering key practical issues related to the legal environment for agricultural operations. The Thailand section, which was written by lawyers at Tilleke & Gibbins, covers the following topics: Agricultural policy Acquisition of agricultural companies Acquisition of agricultural land Crop seed business Plant variety rights Genetically modified crops Animal and animal welfare issues Agricultural safety and product liability Practical Law, produced by Thomson Reuters, is a comprehensive global legal resource for business lawyers. The platform features a wide range of guides covering hundreds of jurisdictions and practice areas. The full Agricultural Law in Thailand chapter can be accessed on the Practical Law website.
August 2, 2022
Thailand has issued separate regulations temporarily exempting hotel operators and factory owners from paying their annual government fee. The special allowances are meant to mitigate the COVID-19-related financial impacts that have hit the hospitality and manufacturing sectors in Thailand. The exemption for hotel business operators came on July 8, 2022, when the Ministry of the Interior promulgated the Ministerial Regulation Re: Exemption from the Government Fee for Hotel Business Operators B.E. 2565 (2022). This regulation exempts hotel business operators from paying the annual government fee, which is at the rate of THB 40 per room, from July 1, 2022, to June 30, 2024. The exemption for factory business operators was laid out in the Ministry of Industry’s July 1, 2022, Ministerial Regulation Re: Exemption from Annual Government Fee for Factory Business Operators B.E. 2565 (2022). Under this regulation, operators of type 2 factories (which must notify the Ministry of Industry before operation) and type 3 factories (which must obtain a factory operation license before operation) as designated under the Factory Act B.E. 2535 and its amendments are relieved from paying the annual government fee from June 10, 2022, to June 9, 2023. This fee varies (ranging from THB 300 to THB 43,500 per year) depending on the horsepower of machinery used in the factory. For more information on these exemptions, please contact Tilleke & Gibbins at [email protected].
June 29, 2022
Thailand’s Ministry of Interior has extended the deadline for payment of the 2022 land and building tax by three months, from April 30, 2022, to July 31, 2022, in order to relieve the burden for taxpayers. The announcement was published in the Government Gazette on June 24, 2022. If payment is to be made in installments, the announcement also extends the deadline for each installment as follows: For more details on these measures, or any aspect of Thailand’s land and building tax, please contact Chaiwat Keratisuthisathorn at [email protected], or Sorawit Partomtanasarn at [email protected].