December 15, 2025

Vietnam Issues Amended Law on Construction

On December 10, 2025, the National Assembly of Vietnam officially passed the amended Law on Construction, marking the culmination of a multiyear reform process aimed at modernizing Vietnam’s construction legal framework, streamlining administrative procedures, and aligning with digital transformation and sustainability goals.

The amended law, which replaces the current Law on Construction No. 50/2014/QH13, will take effect on July 1, 2026. The Ministry of Construction (MOC) is also preparing several guiding decrees covering project classification, digital submissions and database management, and technical standards for design documentation.

Key Changes in the Amended Law

While the executed version of the amended Law on Construction has yet to be released to the public, reports have confirmed that it includes the following key changes introduced under the latest draft submitted by the MOC in September:

  • Project classification: The amended Law on Construction classifies construction projects by investment form (public, PPP, business investment, and others), which aligns with the Law on Public Investment, the Law on Investment, and the Law on PPP Investment. This reduces regulatory overlap and clarifies responsibilities.
  • Project preparation and appraisal: The requirement for prefeasibility reports for business investment projects is abolished, as this requirement is now governed by the Law on Investment and the Law on Public Investment. This change shortens the preparation timeline and reduces duplication of procedures. In addition, the authority’s appraisal is streamlined to a single feasibility stage. Also eliminated is the appraisal process conducted following basic design approval, shifting more responsibility to investors and consultants, with targeted post-audit mechanisms for high-risk projects.
  • Construction permits: One of the most significant new changes of the amended Law on Construction is the expansion of exemptions from construction permit requirements to the following eight distinct groups of construction works:
    1. State-secret works, emergency or urgent constructions, works under special public investment projects or projects following special procedures, temporary works, and works located on national defense or security land.
    2. Works under public investment projects approved by competent authorities such as the prime minister, heads of central agencies, leaders of supreme judicial bodies, the State Audit Office, the Office of the President, the Office of the National Assembly, ministries, political-social organizations, and chairpersons of People’s Committees at all levels.
    3. Works constructed along routes spanning two or more provinces, or those outside designated urban development areas as per approved plans or accepted route proposals.
    4. Offshore works under investment projects with authorized sea area allocation, airports, airport-related works, and works ensuring flight operations outside airports.
    5. Advertising structures exempt under the Law on Advertising—such as small, compact signs and billboards (under 20 m² per side), signs and billboards with simple structures (not metal frames), and freestanding billboards under 40 m² in area—and passive telecommunications infrastructure.
    6. Works under investment projects whose feasibility study reports or adjustments have been appraised and approved by competent authorities according to regulations.
    7. Grade 4 constructions and individual residential buildings under seven stories with a total floor area under 500 m2, provided they are not located in areas with specific architectural management regulations—such as functional zones, urban areas, rural residential zones, provincial/city urban development areas, national economic or tourism zones, or areas with established architectural management rules.
    8. Works involving internal repairs or external renovations that do not adjoin urban roads subject to architectural management, as long as such repairs do not alter the building’s purpose or function, affect structural safety, or compromise fire safety, environmental protection, or technical infrastructure.

According to the MOC, forthcoming government decrees will further simplify construction permit procedures. The entire permitting process is expected to be conducted online, with a maximum processing time of 7 to 10 days—reducing both time and costs by at least 30% as mandated by the government. The new regulations will also increase the responsibility of design consultants to ensure construction safety.

Other Notable Reforms

The amended law also reforms requirements and procedures in several other areas, as detailed below.

Cost Management and Contractual Principles

The amended law introduces clearer and more practical provisions on construction cost management and contractual arrangements, with a particular focus on risk allocation and contract adjustment. Accordingly, it distinguishes between force majeure events and fundamental changes of circumstances, following the Civil Code 2015, aiming to provide a fair and transparent legal basis for contract adjustment in exceptional situations.

Force majeure in this context refers to events that are entirely beyond the parties’ control and directly disrupt construction activities, such as natural disasters, environmental catastrophes, fires, epidemics, wars, national emergencies, strikes, blockades, or other situations determined by the prime minister for public investment and PPP projects. By contrast, a fundamental change of circumstances arises when external conditions make contract performance excessively difficult or economically imbalanced—for instance, changes in state policies or laws, unforeseeable geological conditions, or abnormal fluctuations in construction material prices.

Digital Transformation, Innovation, and Smart Construction Governance

For the first time, the amended Law on Construction establishes a legal basis for a National Construction Information and Database System, creating a digital foundation for state management of construction activities. This system will collect, store, and update data throughout the project lifecycle, serving as an official source to support functions such as project appraisal, permit issuance, and quality supervision. It will also connect with other national databases on land, planning, investment, and infrastructure, enabling data sharing and consistency across sectors.

In parallel, the law promotes the use of science, technology, and innovation in construction, including the adoption of green technologies and building information modeling (BIM).

Green and Sustainable Construction Policy

The amended law incorporates sustainability principles, requiring construction activities to comply with environmental protection standards and encouraging the use of local, recyclable, and energy-efficient materials. It promotes research and application of advanced technologies and green building solutions to reduce resource consumption and environmental impact. These provisions aim to align construction practices with Vietnam’s broader green growth strategy and support the transition toward sustainable development.

Outlook for Investors and Developers

While the amended Law on Construction takes a progressive step forward, it also brings several practical challenges that investors and other stakeholders should be mindful of. Pending the issuance of implementing decrees, the decentralization of appraisal and permitting authority could lead to different interpretations and enforcement practices among provinces, which may affect project timelines and create uncertainty in compliance.

The move from state preapproval to postconstruction accountability, though intended to streamline oversight, also places greater responsibility on investors to manage safety, design, and technical risks. This shift will likely require stronger internal controls and more reliable professional assurance systems.

Another issue lies in the transition period. Projects that start under the currently effective Law on Construction but continue after the new law takes effect may face uncertainty over which procedures, documents, or appraisal standards apply until detailed guidance is issued.

Finally, the success of the National Construction Information and Database System will depend heavily on how well government agencies coordinate, how reliable the shared data proves to be, and how secure the digital infrastructure is. Building strong digital capacity across stakeholders will be essential to ensure the system works as intended in practice.

Investors and developers should keep a close watch on forthcoming regulations that clarify the division of appraisal authority between central and local levels, the technical framework for database integration, and transitional procedures for projects that bridge the old and new legal regimes.

RELATED INSIGHTS​ 

February 9, 2021
On January 26, 2021, the Thai government passed a resolution to reduce the government fees that are generally collected for the registration of a sale and mortgage of immovable property. The details of this were subsequently set out in two notifications issued by the Ministry of Interior and published in the Government Gazette on February 2, 2021, taking effect the following day. The notifications will remain in effect through December 31, 2021. These two notifications, which are part of the government’s relief efforts to soften the economic fallout of the COVID-19 pandemic, specify that government fees for the registration of a sale and mortgage of immovable property are reduced to 0.01% of the official assessed sale price (reduced from 2%) and 0.01% of the mortgage amount (reduced from 1%). In order to qualify for the reduced rates, the sale and mortgage must be registered at the same time, and the sale price and mortgage amount must not exceed THB 3 million (approximately USD 100,000). The reduced rates only apply to the sale and mortgage of detached houses, semi-detached houses, row houses, commercial buildings, and condominium units, and they must be sold by a licensed developer or authorized government authority. For more information on these notifications, or on any aspect of the Thai government’s COVID-19 relief measures, please contact Tilleke & Gibbins at [email protected] or +66 2056 5555.
February 2, 2021
The Royal Decree on Land and Building Tax Reduction (No. 2) B.E. 2564, which we previously noted was under consideration, has been officially promulgated. The royal decree, which was announced and published in Thailand’s Government Gazette on January 31, 2021, and came into effect the following day, will effectively reduce land and building tax payments by 90% in 2021 for the following types of land and buildings: Land or buildings used for agricultural purposes; Land or buildings used for residential purposes; Land or buildings used for other purposes; and Vacant or unused land or buildings. Owners of the above types of land or buildings are therefore only required to pay 10% of the land and building tax normally owed for 2021. The royal decree follows the Ministry of Interior’s recent announcement of an extension for the payment of land and building tax in 2021, which will now be due by June 30, 2021 (extended from April 30, 2021). For more details on these measures, or on any aspect relating to Thailand’s land and building tax, please contact Chaiwat Keratisuthisathorn at [email protected] or +66 2056 5507.
January 22, 2021
The renewed spread of COVID-19 in Thailand since December 2020 has led to additional tax relief measures to lessen the economic impact of the outbreak. Most recently, it has prompted the Ministry of Finance to propose a draft Royal Decree on Land and Building Tax Reduction B.E. 2564 (2021), which is expected to be similar to the 2020 measures that reduced land and building tax payments by 90 percent. In the meantime, on January 21, 2020, the Ministry of Interior announced an extension for the payment of land and building tax in 2021, which is now due by June 30, 2021 (extended from April 30, 2021). In light of the new land and building tax payment deadline for 2021, the Bangkok Metropolitan Administration, or the relevant municipality or local administrative office, will now send land and building tax assessment forms to taxpayers by April 30, 2021 (extended from February 28, 2021). For more details on these measures, or on any aspect of Thailand’s land and building tax, please contact Chaiwat Keratisuthisathorn at [email protected] or +66 2056 5507.
December 1, 2020
Multilaw has launched the 2020 edition of its Real Estate Guide, including updated contributions for Cambodia, Laos, Myanmar, Thailand, and Vietnam provided by real estate specialists at Tilleke & Gibbins. This concise guide, which features contributions from Multilaw member firms in 58 jurisdictions worldwide, is designed to help investors navigate the complex global real estate landscape and overcome the key challenges they may face when managing real estate across borders. The guide outlines key legal requirements in each jurisdiction, focusing especially on the restrictions and taxes applicable in each country, and the legal methods available for registering and identifying real estate and property ownership. Tilleke & Gibbins is a proud member of Multilaw, a leading network of carefully selected, independent law firms consisting of over 8,000 lawyers in more than 150 commercial centers, able to provide expert legal advice in complex environments around the globe. The full Real Estate Guide  is available free on the Multilaw website.