The European Power Outage: What Happened and Why It Matters for Thailand

On April 28, 2025, a massive power outage swept across the Iberian Peninsula, plunging Portugal, Spain, and parts of southwestern France into darkness for up to ten hours. As Thailand advances its energy transition by increasing renewable integration and regional interconnections, the European blackout serves as a stark reminder of the grid vulnerabilities that still exist.

This article marks the first installment of From Crisis to Clarity, a three-part series analyzing the recent European blackout and its implications for Thailand. In this article, we examine the root causes of the outage in the Iberian Peninsula. The second article will assess the likelihood of a similar event occurring in Thailand, considering the country’s current energy infrastructure and its increasing reliance on renewables. The final article will present key lessons and recommendations that Thailand can adopt to strengthen its energy system and prevent comparable disruptions in the future.

Root Causes of the European Power Outage

At approximately 12:30 p.m. on April 28, 2025, Spain experienced a sudden and severe drop in electricity generation, with output falling from around 27 gigawatts to slightly over 12 gigawatts. While investigations are still ongoing, preliminary reports suggest a cascading failure triggered by a fault in a high-voltage cross-border transmission line. The abrupt and precipitous drop in supply created significant instability in the national grid, which relies on maintaining a constant frequency of 50 hertz to ensure operational balance. The resulting frequency deviation triggered automatic safety systems. As a result, some power plants, including nuclear plants, were disconnected. This also led to the disconnection of the interconnection line between Spain and France via the Pyrenees. Ultimately, these events caused a complete collapse of Spain’s power system for up to ten hours.

Speculation persists about the exact cause of the Iberian blackout. While Spanish authorities have ruled out a cyberattack, one possible contributor is a lack of so-called “grid inertia”—the property of a power grid that enables it to resist changes in frequency, typically provided by the rotating mass of conventional generators. In other words, grid inertia is the grid’s ability to keep the frequency stable. Traditional grids powered by gas and nuclear plants have high inertia, making them more resistant to frequency changes. In contrast, grids with a high share of renewables, such as wind and solar, have low inertia unless specific measures are taken to compensate.

On May 1, 2025, the Association of European Transmission System Operators (ENTSO-E) announced the establishment of a panel of experts tasked with conducting a thorough inquiry into the causes and consequences of the blackout. This panel is expected to deliver a final report within six months of the incident. Interim publications, including event analyses, developing conclusions, and recommendations, are scheduled to be released at the end of each two-month period following the incident, providing updates on the investigation’s progress. Spain and Portugal have been given three months to submit their data, reflecting the complexity and scale of the event.

Takeaways

The recent European blackout demonstrates how quickly low-inertia power systems can spiral out of control when frequency stability is compromised. This scenario is increasingly relevant to Thailand, whose traditionally gas-based, centrally managed grid still benefits from a buffer of rotational inertia but is rapidly integrating renewable energy sources and expanding interconnections with neighboring countries. As Bangkok looks toward a future where renewables may account for more than half of installed capacity, the Iberian lesson highlights that strengthening and enhancing the reliability of the grid are no longer optional.

 

For more on this topic, read the second article in the series: “Could a Similar Outage Happen in Thailand?

RELATED INSIGHTS​ 

December 15, 2023
As part of its membership in Lex Mundi, Tilleke & Gibbins has published an updated edition of its Guide to Doing Business in Thailand for 2023. This guide outlines the key factors for starting and operating a business in the Thai market. Issues covered include: Investment incentives Financial facilities Exchange controls Import and export regulations Structures for doing business Requirements for the Establishment of a Business Operation of the Business Cessation or Termination of the Business Labor legislation, relations, and supply Tax Immigration requirements This publication is part of Lex Mundi’s Country Guides series prepared by member firms in more than 100 jurisdictions worldwide. The guides serve as a useful resource for planning international business strategy and researching new markets. The full Guide to Doing Business in Thailand is available through the button below.
July 25, 2023
Thailand’s Energy Regulatory Commission (ERC) is in the process of reviewing a draft regulation that updates the nationality qualifications for the ultimate shareholders and directors of applicants for an energy business license. The draft ERC Regulation Re: Qualifications, Documents and Application for Electricity Business—which is intended to replace the ERC Regulation Re: Application and Permission for Electricity Business B.E. 2551 and its amendments—is likely to be adopted soon and will affect licensed companies that are foreign majority owned when they apply for or renew their energy business licenses. The draft regulation requires partnerships, limited companies, and public limited companies to have the following qualifications unless there is an international agreement granting national treatment for a specific commitment (mode 3 or mode 4) or exemption by other laws: Juristic persons must be established under Thai law or registered in Thailand with the objective of carrying out electricity business; For private limited companies, foreign ultimate shareholders must not hold more than 49% of the total shares, and the number of the foreign shareholders must not exceed half of all shareholders; At least half of all directors must have Thai nationality; and Any authorized directors must have Thai nationality. When the draft regulation is adopted, it will not take retroactive effect on previously granted energy business licenses, which will continue to be valid until they expire if there is no material change to the license as defined by the draft regulation. Once the license is up for renewal (energy business licenses are normally issued for a specific period of time), it will be subject to the draft regulation. All license applications submitted prior to the effective date of the draft regulation and under consideration will be deemed applications for a license under the draft regulation. As noted above, the new qualification requirements
July 7, 2023
Cambodia has the potential to be one of the top countries in the world for generating renewable energy through solar, based on the average amount of sunlight hours available per day and the consistent sunshine throughout the year. The Cambodian government has recognized this potential and has made major updates to its energy policies in recent years. Solar power is now taking over a much larger portion of the total energy mix in Cambodia, especially as a number of utility-scale solar power plants have come online in recent years. The long-term Power Development Master Plan 2022–2040 sets out the long-term energy policy for Cambodia and requires a bigger role for renewables. The use of solar power will play a key role in this aim to increase the role of renewables, with the plan foreseeing almost 30% of all national power generated through solar technologies by 2040. Two of the latest legislative and regulatory steps by the government are the Ministry of Mines and Energy’s guidelines for rooftop solar systems, and most recently the long-awaited Environment and Natural Resources Code, which was enacted on June 29, 2023. Rooftop Solar Projects Many companies, from small startups to multinationals, are exploring the potential for rooftop solar in Cambodia. However, despite the favorable natural factors, the regulatory framework was not always clear or friendly to rooftop solar, hampering investment. This started slowly changing with the adoption of the first solar energy regulation in 2018, which provided the country’s first official guidance on both solar power plants and rooftop solar. It provided some much-needed clarity, but the 2018 solar energy regulation—and especially the subsequent electricity tariff schemes—often kept rooftop projects from being financially viable. Many players in the industry voiced their doubts about the regulations and tariffs, focusing especially on the capacity charge—a monthly
May 19, 2023
On May 15, 2023, Vietnam’s Deputy Prime Minister Tran Hong Ha signed Decision No. 500 of the Prime Minister approving the National Power Development Plan for the period 2021-2030, with a vision to 2050 (“PDP VIII”), following extensive public consultations and multiple rounds of review since the first draft version was circulated in 2021. The plan was approved in the context that in the past few years, a number of large power projects have been behind schedule for operation, while new projects have not been able to be implemented due to waiting for additional planning. PDP VIII is the master plan for the development of the power source and transmission grid at 220kV or higher; services in renewable energy and new energy in Vietnam; and works connecting the power grids of Vietnam and neighboring countries. We set out below some quick updates regarding PDP VIII. 1. Development Targets Key development targets are summarized in the table below: Investors in coal, domestic gas, and LNG projects may need to have a conversion plan ready given the 2050 targets to convert to other sources of energy. 2. Solar Projects A list of 27 solar power projects that were planned for the period of 2021-2030 but which have not been assigned to investors are not allowed to be deployed but can be considered after 2030, except in the case of deployment in the form of self-production and self-consumption (Appendix IV). These projects represent 4,136.25 MW of capacity that will be left on the sidelines until 2030. 3. Hydropower Projects A list of 14 potential hydropower projects can be considered if economic and technical conditions allow for more hydropower development (Appendix III). These projects represent 1,244 MW of capacity that can be added to the hydropower targets for 2030. 4. Projects Prioritized for