The European Power Outage: What Happened and Why It Matters for Thailand

On April 28, 2025, a massive power outage swept across the Iberian Peninsula, plunging Portugal, Spain, and parts of southwestern France into darkness for up to ten hours. As Thailand advances its energy transition by increasing renewable integration and regional interconnections, the European blackout serves as a stark reminder of the grid vulnerabilities that still exist.

This article marks the first installment of From Crisis to Clarity, a three-part series analyzing the recent European blackout and its implications for Thailand. In this article, we examine the root causes of the outage in the Iberian Peninsula. The second article will assess the likelihood of a similar event occurring in Thailand, considering the country’s current energy infrastructure and its increasing reliance on renewables. The final article will present key lessons and recommendations that Thailand can adopt to strengthen its energy system and prevent comparable disruptions in the future.

Root Causes of the European Power Outage

At approximately 12:30 p.m. on April 28, 2025, Spain experienced a sudden and severe drop in electricity generation, with output falling from around 27 gigawatts to slightly over 12 gigawatts. While investigations are still ongoing, preliminary reports suggest a cascading failure triggered by a fault in a high-voltage cross-border transmission line. The abrupt and precipitous drop in supply created significant instability in the national grid, which relies on maintaining a constant frequency of 50 hertz to ensure operational balance. The resulting frequency deviation triggered automatic safety systems. As a result, some power plants, including nuclear plants, were disconnected. This also led to the disconnection of the interconnection line between Spain and France via the Pyrenees. Ultimately, these events caused a complete collapse of Spain’s power system for up to ten hours.

Speculation persists about the exact cause of the Iberian blackout. While Spanish authorities have ruled out a cyberattack, one possible contributor is a lack of so-called “grid inertia”—the property of a power grid that enables it to resist changes in frequency, typically provided by the rotating mass of conventional generators. In other words, grid inertia is the grid’s ability to keep the frequency stable. Traditional grids powered by gas and nuclear plants have high inertia, making them more resistant to frequency changes. In contrast, grids with a high share of renewables, such as wind and solar, have low inertia unless specific measures are taken to compensate.

On May 1, 2025, the Association of European Transmission System Operators (ENTSO-E) announced the establishment of a panel of experts tasked with conducting a thorough inquiry into the causes and consequences of the blackout. This panel is expected to deliver a final report within six months of the incident. Interim publications, including event analyses, developing conclusions, and recommendations, are scheduled to be released at the end of each two-month period following the incident, providing updates on the investigation’s progress. Spain and Portugal have been given three months to submit their data, reflecting the complexity and scale of the event.

Takeaways

The recent European blackout demonstrates how quickly low-inertia power systems can spiral out of control when frequency stability is compromised. This scenario is increasingly relevant to Thailand, whose traditionally gas-based, centrally managed grid still benefits from a buffer of rotational inertia but is rapidly integrating renewable energy sources and expanding interconnections with neighboring countries. As Bangkok looks toward a future where renewables may account for more than half of installed capacity, the Iberian lesson highlights that strengthening and enhancing the reliability of the grid are no longer optional.

 

For more on this topic, read the second article in the series: “Could a Similar Outage Happen in Thailand?

RELATED INSIGHTS​ 

June 6, 2024
On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly. One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector. Annual payment of land rental Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment. As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning. Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged. Obtaining land Under the Land Law 2024,
June 4, 2024
Thailand’s Department of Mineral Fuels (DMF) is in the process of preparing a notification that will open the application period for onshore petroleum exploration and production rights in the country’s 25th bidding round. The 25th round of bidding will cover nine petroleum blocks, including the northeastern areas (blocks L1/66, L2/66, L3/66, L4/66, L5/66, L7/66, and L9/66) and central areas (blocks L6/66 and L8/66). The DMF estimates that application submissions will commence around the middle of 2024, and the successful bidder will be announced at the end of the same year. Based on previous rounds of bidding, applicants must meet the following key criteria: The applicant is a company with the purpose of carrying out petroleum exploration and production; The applicant commands the necessary assets, machinery, equipment, tools, and specialists to explore for, produce, sell, and dispose of petroleum; The applicant has not abandoned its operations under a concession or been subject to revocation of a concession in Thailand; and None of its personnel, shareholders, directors, or authorized directors is listed as a person who has abandoned its operations under a concession, or has been subject to revocation of a concession in Thailand. If the applicant does not itself possess all the qualifications under (2) above, it must have another government-approved company that possesses all the qualifications under (2) and has a capital or management relationship with the applicant, and the applicant must supply guarantees that the company will make available to the applicant all necessary assets, machinery, equipment, tools, and specialists for the applicant to explore for, produce, sell, and dispose of petroleum. Companies with a vested interest in petroleum exploration and production in Thailand must remain vigilant for updates. The DMF is expected to provide an update and more details on the bidding very soon. For more details
June 4, 2024
As Vietnam continues its rapid economic development, the demand for sustainable and reliable energy sources has never been more critical. Solar power has emerged as a key component of Vietnam’s strategy to diversify its energy portfolio and reduce its carbon footprint. Recent developments of the regulatory framework governing solar power projects in Vietnam, as discussed below, highlight the country’s commitment to renewable energy and its efforts to create a conducive environment for solar power investments. Objectives for the Development of Solar Power Projects On May 15, 2023, the Prime Minister issued Decision No. 500/QD-TTg, approving the National Power Development Plan for 2021-2030 with a vision to 2050 (“PDP VIII”). Following this, on April 1, 2024, the Prime Minister promulgated the Implementation Plan for PDP VIII (“Implementation Plan”). These documents underscore Vietnam’s commitment to promoting renewable energy, particularly solar. They emphasize self-production and self-consumption of solar power, the development of rooftop solar systems, and the promulgation of the direct power purchase mechanism. The integration of solar power with battery storage is also encouraged, contingent upon economic viability. PDP VIII sets ambitious capacity targets for solar power. By 2030, the capacity is projected to reach approximately 12,836 MW, accounting for 8.5% of the total power capacity. This includes 10,236 MW from concentrated solar power and 2,600 MW from self-production and self-consumption solar power. By 2050, the capacity is expected to rise to between 168,594 MW and 189,294 MW, representing 33.0-34.4% of the total power capacity. Additionally, PDP VIII and the Implementation Plan list 27 solar power projects, totaling 4,136.25 MW, slated for implementation after 2030. However, these projects may be advanced under self-production and self-consumption arrangements. Draft Decree on Direct Power Purchase Agreements On April 15, 2024, the Ministry of Industry and Trade (“MOIT”) released a draft decree on direct power
June 3, 2024
Nearly a year after Vietnam’s issuance of its National Power Development Plan for 2021-2030, with a vision to 2050 (“PDP VIII”), the Prime Minister issued Decision No. 262/QD-TTg dated April 1, 2024, approving the Implementation Plan for PDP VIII (“Implementation Plan”). Among other contents, the Implementation Plan sets forth the list of prioritized power source projects through 2030, and the capacity of renewable energy sources through 2030, as detailed below. Prioritized Power Source Projects through 2030 The Implementation Plan lists out six types of power source projects prioritized for development through 2023 according to the capacity approved under PDP VIII. They include: Domestic gas-fired power (14,930 MW) LNG-fired power (22,400 MW) Coal-fired power (30,127 MW) Cogeneration power using residual heat, blast furnace gas, and by-products of technological lines in industrial facilities (2,700 MW) Hydropower (29,346 MW) Pumped storage hydropower (2,400 MW) With respect to each type, the Implementation Plan provides details of projects by location and their operational progress. Such information is set out in Schedule III of the Implementation Plan. For power source projects not included in this list, the provincial People’s Committees will consult with the Ministry of Industry and Trade (“MOIT”) and relevant agencies on compliance with the planning prior to appraisal and issuance of in-principle investment approval. Renewable Energy Projects through 2030 The Implementation Plan allocates the capacity of the following renewable energy sources by locality/region: Offshore wind power (6,000 MW) Onshore wind power (21,880 MW) Hydroelectric power (29,346 MW) Biomass electricity (1,088 MW) Electricity produced from waste (1,182 MW) Rooftop solar power for self-production and self-consumption (2,600 MW) Battery storage (300 MW) With respect to each renewable energy source, the Implementation Plan provides a list of certain renewable energy projects through 2030, including the expected life cycle of the projects, and the allocated capacity