April 28, 2017

Seven Things to Look for in Your Private Power Purchase Agreement

Bangkok Post, Corporate Counsellor Column

As the costs of solar photovoltaic (PV) panels decrease, new business opportunities are emerging. In addition to the traditional model of independent power producers establishing large-scale power generating facilities to sell electricity directly to public utilities, a new dynamic model of direct electricity selling is beginning to take shape.

Solar PV panels can be installed on roofs to supply electricity directly to the building’s occupants, bypassing the need for a local electricity utility. Under a contract between private parties, the customer and power producer are able to negotiate directly on the cost of the electricity to be supplied. The resulting increase in competition has the potential to reduce energy costs across the market.

Typically, the electricity seller will remain the owner of the PV panels, the inverter, and other components of the generating system. As the seller will be financing the installation of the system, this will allow the purchaser to sign up with minimal initial costs.

The principal contractual document governing the relationship between the seller and purchaser is the power purchase agreement (PPA). PPAs are traditionally executed between independent power producers and the local electricity utility, which in Thailand has been the Provincial Electricity Authority (PEA), the Metropolitan Electricity Authority (MEA), or the Electricity Generating Authority of Thailand (EGAT).

The form PPAs from the MEA, PEA, and EGAT generally do not allow for much negotiation on the part of the independent power producers. But with rooftop solar installations, both the seller and the purchaser of the electricity being generated are private parties, meaning there is greater room for flexibility.

Here are seven issues that both parties should be aware of from the outset:

1. Ownership of the facilities: Ideally, the purchaser will be the owner of both the building and the land. However, if the purchaser is leasing the property, it is important to ensure that installation of the system will not violate the lease agreement, or will not result in the system becoming attached to the building as a permanent fixture. If the building and/or land are being leased, the term of the lease should also be confirmed in order to ensure that installation of the system will be economical for the seller.

2. Minimum purchase requirements: The purchaser should ideally be required to purchase a minimum amount of electricity each month, failing which, it will still be required to compensate the seller. This “take or pay” model is optimal for ensuring financial predictability on the part of the seller and its financiers. The purchaser should take care to ensure that its minimum commitments are not excessive and can easily be managed in light of anticipated future use.

3. Clear lines between Force Majeure and Events of Default: A key issue to consider in the PPA is how to address changes to the environment which are beyond the control of the purchaser. If the purchaser’s neighbor to the south erects a tall building, trees, or other obstructions, the solar PV system may be rendered effectively worthless. It will be important to ensure that the PPA clearly outlines whether the purchaser is entitled to terminate the agreement in such circumstances.

4. Ownership of the system: Since the seller will retain ownership of the system, it will want to affix conspicuous markings on all equipment to ensure that its ownership interests are clear. The PPA should contain a clause which requires the purchaser to assist the seller in the event the seller wishes to register its ownership interests at any relevant government agencies. Furthermore, the PPA should contain covenants on the part of the purchaser that it will take no actions which will result in the system being deemed a fixture.

5. Mortgages and encumbrances: The seller must be aware if the land and/or building on which the panels will be placed has been mortgaged. Additionally, the PPA may contain a negative covenant on the part of the purchaser not to mortgage the building, or an undertaking to notify the seller in the event it mortgages the building. The seller’s lenders may consider securing their loans to the seller by taking the solar PV system as collateral.

6. Regulatory environment: As this is a new area of business, the regulatory framework is still in the process of being devised. The purchaser and seller must stay apprised of new rules and regulations promulgated by the Energy Regulatory Commission, and the PPA must envision how new rules affecting the transaction will be addressed.

7. Payment terms: Delayed payment by the purchaser should ideally result in automatic interest payments being levied. It will not be in the seller’s best interests to terminate the agreement immediately in the event of non-payment; however, the purchaser must have a clear disincentive to delay on making its regular payments.

Private PPAs for solar PV systems are still in their infancy in Thailand, and best practices will continue to develop. It is important that both purchasers and sellers of electricity are aware of the legal risks involved when negotiating PPAs and have taken all appropriate steps to maximize their bargaining position.

RELATED INSIGHTS​ 

January 27, 2025
Thailand’s Ministry of Energy (MOE) has announced the launch of the 25th bidding round for petroleum exploration and production. This round offers nine greenfield onshore blocks—seven in northeastern Thailand and two in central Thailand—encompassing over 33,000 km². The bids can be submitted from July 1 to July 16, 2025. The sizes and locations of these blocks are: Northeast Thailand Block L1/66: 3,223.51 km² (Khon Kaen, Nong Bua Lam Phu, Udon Thani) Block L2/66: 3,917.03 km² (Kalasin, Sakon Nakhon, Udon Thani) Block L3/66: 3,918.22 km² (Kalasin, Khon Kaen, Maha Sarakham, Udon Thani) Block L4/66: 3,656.65 km² (Amnat Charoen, Mukdahan, Nakhon Phanom, Yasothon) Block L5/66: 3,436.01 km² (Chaiyaphum, Khon Kaen, Nakhon Ratchasima) Block L7/66: 3,438.51 km² (Buri Ram, Maha Sarakham, Nakhon Ratchasima, Roi Et, Surin, Khon Kaen) Block L9/66: 3,885.44 km² (Nakhon Ratchasima) Central Thailand Block L6/66: 3,966.86 km² (Chaiyaphum, Lop Buri, Phetchabun) Block L8/66: 3,957.41 km² (Kanchanaburi, Nakhon Pathom, Ratchaburi, Suphan Buri) Bidding Process Interested companies must submit their bids to the Department of Mineral Fuels (DMF) between July 1 and July 16, 2025. Bids should include: Application form (ChorThor/Por1) Proof of eligibility: Corporate documentation, audited financial statements, and proof of resources Technical and commercial proposals: Exploration plans, geological surveys, financial and work commitments, and special benefits such as signing bonuses of at least USD 100,000. There is a nonrefundable THB 50,000 application fee per block, and applicants must provide a bid bond of THB 3 million per block via an unconditional bank guarantee from a commercial bank with branches in Thailand, valid for at least one year from the bidding submission date. The guarantee will be returned to unsuccessful bidders upon request and to successful bidders upon the signing of the concession agreement. Eligibility Bidders must meet the following main eligibility criteria: Bidders must be limited companies with the following qualifications: The company must have the objective of
January 23, 2025
In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges. In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports. The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models. Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include: Allowing additional planning where projects do not violate national security. Allowing rectification of projects’ violations in land and construction process as per law. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered. For items (iv) and (v), the authority will issue regulations
January 14, 2025
Thailand’s Department of Industrial Works (DIW) has issued a new regulation (Ministerial Regulation Re: Designation of Type, Kind, and Size of Factories (No. 3) B.E. 2567 (2024)), which removes the factory license requirement for electricity generation from solar energy installations on rooftops, roof decks, or any part of a building used for residential or other purposes, regardless of capacity. The new rules took effect on December 28, 2024. Under the previous regulations, solar rooftop installations had to seek approval from the DIW if their capacity exceeded 1,000 kW (1 MW), which added time and administrative costs when adopting renewable energy solutions. Benefits and Further Compliance The updated regulation benefits industrial operators by facilitating faster installation times and lower costs, as solar rooftops can now be installed without the need for prior approval of a factory license from the DIW. Operators can now more easily contribute to environmental sustainability and carbon reduction efforts. Despite the lifting of the factory licensing requirement, other compliance obligations, such as an energy business license (or exemption from an energy business license), a controlled energy production license, and a construction permit, may still apply. Reason for the Change Removing the classification of rooftop or building-installed solar power plants as factories aligns with Thailand’s renewable energy goals and reduces regulatory burdens for industrial operators. Additionally, it supports the achievement of energy policies aligned with the UN’s Sustainable Development Goals and Thailand’s international commitments to reduce greenhouse gas emissions through the participation of all sectors. For further details on how this change affects business operations or to explore strategies for renewable energy implementation, please contact Supasit Boonsanong at [email protected], Charuwan Charoonchitsathian at [email protected], or Phareeya Yongpanich at [email protected].
December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.