Seven Things to Look for in Your Private Power Purchase Agreement

Bangkok Post, Corporate Counsellor Column

As the costs of solar photovoltaic (PV) panels decrease, new business opportunities are emerging. In addition to the traditional model of independent power producers establishing large-scale power generating facilities to sell electricity directly to public utilities, a new dynamic model of direct electricity selling is beginning to take shape.

Solar PV panels can be installed on roofs to supply electricity directly to the building’s occupants, bypassing the need for a local electricity utility. Under a contract between private parties, the customer and power producer are able to negotiate directly on the cost of the electricity to be supplied. The resulting increase in competition has the potential to reduce energy costs across the market.

Typically, the electricity seller will remain the owner of the PV panels, the inverter, and other components of the generating system. As the seller will be financing the installation of the system, this will allow the purchaser to sign up with minimal initial costs.

The principal contractual document governing the relationship between the seller and purchaser is the power purchase agreement (PPA). PPAs are traditionally executed between independent power producers and the local electricity utility, which in Thailand has been the Provincial Electricity Authority (PEA), the Metropolitan Electricity Authority (MEA), or the Electricity Generating Authority of Thailand (EGAT).

The form PPAs from the MEA, PEA, and EGAT generally do not allow for much negotiation on the part of the independent power producers. But with rooftop solar installations, both the seller and the purchaser of the electricity being generated are private parties, meaning there is greater room for flexibility.

Here are seven issues that both parties should be aware of from the outset:

1. Ownership of the facilities: Ideally, the purchaser will be the owner of both the building and the land. However, if the purchaser is leasing the property, it is important to ensure that installation of the system will not violate the lease agreement, or will not result in the system becoming attached to the building as a permanent fixture. If the building and/or land are being leased, the term of the lease should also be confirmed in order to ensure that installation of the system will be economical for the seller.

2. Minimum purchase requirements: The purchaser should ideally be required to purchase a minimum amount of electricity each month, failing which, it will still be required to compensate the seller. This “take or pay” model is optimal for ensuring financial predictability on the part of the seller and its financiers. The purchaser should take care to ensure that its minimum commitments are not excessive and can easily be managed in light of anticipated future use.

3. Clear lines between Force Majeure and Events of Default: A key issue to consider in the PPA is how to address changes to the environment which are beyond the control of the purchaser. If the purchaser’s neighbor to the south erects a tall building, trees, or other obstructions, the solar PV system may be rendered effectively worthless. It will be important to ensure that the PPA clearly outlines whether the purchaser is entitled to terminate the agreement in such circumstances.

4. Ownership of the system: Since the seller will retain ownership of the system, it will want to affix conspicuous markings on all equipment to ensure that its ownership interests are clear. The PPA should contain a clause which requires the purchaser to assist the seller in the event the seller wishes to register its ownership interests at any relevant government agencies. Furthermore, the PPA should contain covenants on the part of the purchaser that it will take no actions which will result in the system being deemed a fixture.

5. Mortgages and encumbrances: The seller must be aware if the land and/or building on which the panels will be placed has been mortgaged. Additionally, the PPA may contain a negative covenant on the part of the purchaser not to mortgage the building, or an undertaking to notify the seller in the event it mortgages the building. The seller’s lenders may consider securing their loans to the seller by taking the solar PV system as collateral.

6. Regulatory environment: As this is a new area of business, the regulatory framework is still in the process of being devised. The purchaser and seller must stay apprised of new rules and regulations promulgated by the Energy Regulatory Commission, and the PPA must envision how new rules affecting the transaction will be addressed.

7. Payment terms: Delayed payment by the purchaser should ideally result in automatic interest payments being levied. It will not be in the seller’s best interests to terminate the agreement immediately in the event of non-payment; however, the purchaser must have a clear disincentive to delay on making its regular payments.

Private PPAs for solar PV systems are still in their infancy in Thailand, and best practices will continue to develop. It is important that both purchasers and sellers of electricity are aware of the legal risks involved when negotiating PPAs and have taken all appropriate steps to maximize their bargaining position.

RELATED INSIGHTS​ 

June 25, 2025
In April 2025, a massive power outage plunged Portugal, Spain, and parts of southwestern France into darkness for up to ten hours. As Thailand advances its energy transition by increasing renewable integration and regional interconnections, the European blackout serves as a stark reminder of the grid vulnerabilities that still exist. In this first article of a three-part series, energy specialists from Tilleke & Gibbins examine the root causes of the outage in the Iberian Peninsula.
May 28, 2025
Tilleke & Gibbins attorneys in Vietnam have contributed the 2025 edition of Doing Business in Vietnam, a comprehensive Q&A-style resource from Thomson Reuters Practical Law that provides essential insights for companies navigating business operations in Vietnam. The guide presents a detailed overview of the country’s legal framework and regulatory environment, reflecting recent updates in Vietnamese legislation and practice. This annually updated guide offers key information on the following areas: Legal system: Structure of the Vietnamese judiciary and the role of codified law. Foreign investment: Conditions for market access, licensing requirements, foreign ownership restrictions, and investment incentives. Business vehicles: Formation and operation of legal entities, including limited liability companies, joint-stock companies, and representative offices. Employment: Employment contracts, social insurance, labor rights, and procedures for hiring foreign nationals. Tax: Overview of corporate income tax, personal income tax, value-added tax, and other tax obligations. Intellectual property: Procedures for protecting and enforcing patents, trademarks, copyrights, and other IP rights. Data protection: Compliance requirements under Vietnam’s data privacy laws, including the Personal Data Protection Decree. Competition law: Antitrust rules and regulatory oversight under the Law on Competition. Anti-bribery and corruption: Legal framework and enforcement practices aimed at curbing corrupt activities. E-commerce and digital business: Regulations governing online platforms, digital content, and cross-border services. Marketing and advertising: Laws and guidelines on advertising standards and consumer protection. Product regulation and liability: Safety requirements, product liability issues, and roles of relevant authorities. Doing Business in Vietnam is part of Practical Law’s global series of legal guides designed to support international practitioners and businesses. To access the most recent edition of the Vietnam guide, visit the Practical Law website and sign up for a free trial.
May 2, 2025
Attorneys from Tilleke & Gibbins have updated the latest edition of Doing Business in Thailand, a Q&A-style guide from Thomson Reuters Practical Law that offers an overview of key legal considerations for companies operating in jurisdictions worldwide. The contribution outlines the country’s legal and regulatory framework for foreign investment and business operations and reflects the latest legislative developments. The chapter addresses the following core topics: Legal system: Structure of the courts and the codified nature of Thai law. Foreign investment: Business restrictions under the Foreign Business Act, sector-specific regulations, exchange control rules, and investment incentives. Business vehicles: Overview of partnerships, private and public limited companies, and other legal entities. Employment: Labor protections, employment contracts, foreign worker requirements, and termination procedures. Tax: Corporate and personal income tax, indirect taxes, and tax obligations for residents and non-residents. Intellectual property: Registration and enforcement of patents, trademarks, designs, and copyrights. Data protection: Key provisions of the Personal Data Protection Act and related compliance obligations. Competition law: Regulatory framework under the Trade Competition Act. Anti-bribery and corruption: Relevant legislation and enforcement mechanisms. E-commerce and digital business: Legal regime for online transactions and digital platforms. Marketing and advertising: Consumer protection laws and regulations affecting advertising and marketing practices. Product regulation and liability: Safety standards, liability regimes, and roles of enforcement authorities. Practical Law, a legal reference resource from Thomson Reuters, publishes a range of guides for hundreds of jurisdictions and practice areas. The insurance and reinsurance guide is a valuable resource for legal practitioners, covering numerous jurisdictions worldwide. To view the latest version of the guide, please visit the Practical Law website and enroll in the free Practical Law trial to gain full access.
April 10, 2025
On March 3, 2025, the government of Vietnam issued Decree No. 57/2025/ND-CP, regulating the direct power purchase agreement (DPPA) mechanism between renewable energy generators and large electricity consumers (“Decree 57”). Decree 57 took immediate effect and replaces Decree No. 80/2024/ND-CP on the same subject. The new regulations enable investors to kickstart their investment plans for DPPAs in Vietnam. Below are the key changes and provisions of Decree 57. Participants in On-Grid DPPAs Decree 57 expands the eligibility criteria for participating in DPPAs via the national grid (on-grid DPPAs): Sellers: In addition to wind and solar power generators, biomass energy generators with a capacity of 10 MW or more can now participate. Buyers: Electric vehicle charging businesses are now eligible to participate, broadening the scope beyond just production businesses. Large Electricity Consumers Instead of setting definite criteria at the government decree level, Decree 57 defines large electricity consumers based on average electricity consumption as set out in wholesale electricity market regulations to be issued by the Ministry of Industry and Trade (MOIT). Although the threshold for DPPA participation remains for now at 200,000 kWh per month, Decree 57 will allow the MOIT to adjust this threshold as deemed necessary. Decree 57 also provides specific guidance for large electricity consumers based on their consumption period. To participate in both private off-grid DPPA (selling electricity directly via a grid system separate from the national grid) and on-grid DPPA models, large electricity consumers must meet the minimum threshold for electricity consumption set by the MOIT under the Vietnam wholesale electricity market regulations (“Minimum Consumption Threshold”). Consumers with a consumption history of at least 12 months must have already met the Minimum Consumption Threshold at the time of registration or notification, while those whose consumption period is less than 12 months must commit to