Seven Things to Look for in Your Private Power Purchase Agreement

Bangkok Post, Corporate Counsellor Column

As the costs of solar photovoltaic (PV) panels decrease, new business opportunities are emerging. In addition to the traditional model of independent power producers establishing large-scale power generating facilities to sell electricity directly to public utilities, a new dynamic model of direct electricity selling is beginning to take shape.

Solar PV panels can be installed on roofs to supply electricity directly to the building’s occupants, bypassing the need for a local electricity utility. Under a contract between private parties, the customer and power producer are able to negotiate directly on the cost of the electricity to be supplied. The resulting increase in competition has the potential to reduce energy costs across the market.

Typically, the electricity seller will remain the owner of the PV panels, the inverter, and other components of the generating system. As the seller will be financing the installation of the system, this will allow the purchaser to sign up with minimal initial costs.

The principal contractual document governing the relationship between the seller and purchaser is the power purchase agreement (PPA). PPAs are traditionally executed between independent power producers and the local electricity utility, which in Thailand has been the Provincial Electricity Authority (PEA), the Metropolitan Electricity Authority (MEA), or the Electricity Generating Authority of Thailand (EGAT).

The form PPAs from the MEA, PEA, and EGAT generally do not allow for much negotiation on the part of the independent power producers. But with rooftop solar installations, both the seller and the purchaser of the electricity being generated are private parties, meaning there is greater room for flexibility.

Here are seven issues that both parties should be aware of from the outset:

1. Ownership of the facilities: Ideally, the purchaser will be the owner of both the building and the land. However, if the purchaser is leasing the property, it is important to ensure that installation of the system will not violate the lease agreement, or will not result in the system becoming attached to the building as a permanent fixture. If the building and/or land are being leased, the term of the lease should also be confirmed in order to ensure that installation of the system will be economical for the seller.

2. Minimum purchase requirements: The purchaser should ideally be required to purchase a minimum amount of electricity each month, failing which, it will still be required to compensate the seller. This “take or pay” model is optimal for ensuring financial predictability on the part of the seller and its financiers. The purchaser should take care to ensure that its minimum commitments are not excessive and can easily be managed in light of anticipated future use.

3. Clear lines between Force Majeure and Events of Default: A key issue to consider in the PPA is how to address changes to the environment which are beyond the control of the purchaser. If the purchaser’s neighbor to the south erects a tall building, trees, or other obstructions, the solar PV system may be rendered effectively worthless. It will be important to ensure that the PPA clearly outlines whether the purchaser is entitled to terminate the agreement in such circumstances.

4. Ownership of the system: Since the seller will retain ownership of the system, it will want to affix conspicuous markings on all equipment to ensure that its ownership interests are clear. The PPA should contain a clause which requires the purchaser to assist the seller in the event the seller wishes to register its ownership interests at any relevant government agencies. Furthermore, the PPA should contain covenants on the part of the purchaser that it will take no actions which will result in the system being deemed a fixture.

5. Mortgages and encumbrances: The seller must be aware if the land and/or building on which the panels will be placed has been mortgaged. Additionally, the PPA may contain a negative covenant on the part of the purchaser not to mortgage the building, or an undertaking to notify the seller in the event it mortgages the building. The seller’s lenders may consider securing their loans to the seller by taking the solar PV system as collateral.

6. Regulatory environment: As this is a new area of business, the regulatory framework is still in the process of being devised. The purchaser and seller must stay apprised of new rules and regulations promulgated by the Energy Regulatory Commission, and the PPA must envision how new rules affecting the transaction will be addressed.

7. Payment terms: Delayed payment by the purchaser should ideally result in automatic interest payments being levied. It will not be in the seller’s best interests to terminate the agreement immediately in the event of non-payment; however, the purchaser must have a clear disincentive to delay on making its regular payments.

Private PPAs for solar PV systems are still in their infancy in Thailand, and best practices will continue to develop. It is important that both purchasers and sellers of electricity are aware of the legal risks involved when negotiating PPAs and have taken all appropriate steps to maximize their bargaining position.

RELATED INSIGHTS​ 

January 25, 2023
Thailand’s Energy Regulatory Commission (ERC) has issued four new regulations under the Energy Business Act B.E. 2550 (2007) setting forth competition regimes to control both anticompetitive conduct and market structure in the energy business sector. The regulations were published in the Government Gazette on December 19, 2022, and took effect the following day. The key provisions of these ERC competition regulations largely mirror those articulated in the Trade Competition Act B.E. 2560 (2017) and its subordinate legislation. The most significant features of these competition regulations are summarized below. Market Definition Regulation The ERC’s market definition regulation (officially the ERC Regulation re: Market Definition and Relevant Market of Related Energy Services B.E. 2565) outlines the general framework for defining relevant markets in the energy sector. The factors to be taken into consideration include types of energy licenses, geographical areas, competition conditions, and interchangeability of energy services. In the annex to this regulation, the ERC has classified the relevant energy service markets as follows: Power business activities include power generation, power transmission system services, power distribution system services, power distribution services, and power system control services. Natural gas business activities include natural gas transmission through pipelines via natural gas transmission systems, natural gas procurement and wholesale via natural gas distribution systems, natural gas retail via natural gas distribution systems, and storage and regasification of liquefied natural gas. The ERC will review its market definitions and relevant energy service markets from time to time, taking into account changes in technology and competition conditions as well as feedback from public hearings. Market Dominance Regulation Under the ERC’s market dominance regulation (officially the ERC Regulation re: Criteria on Business Operator having a Market Dominance B.E. 2565), the ERC is empowered to proactively determine and declare which license-holding energy business operators have a dominant position
August 31, 2022
Thailand’s Draft Climate Change Act Countries around the world have given significant attention to climate change legislation, with many national, regional, and global attempts to slow the momentum of climate change. The most notable of these multilateral efforts is the Paris Agreement, a legally binding international treaty on climate change currently adopted by 193 parties. Its goal is to limit the global average temperature to well below 2°C (preferably below 1.5°C) above preindustrial levels, and the treaty’s coordinated efforts to combat climate change are much more ambitious than previous global agreements and discussions. Article 4 of the Paris Agreement requires countries to provide “nationally determined contributions” (NDCs), consisting of their action plans for climate action. Thailand, as a party to the Paris Agreement, has put forth an NDC that pledges to achieve an unconditional greenhouse gas (GHG) emission reduction target of 20% from the business-as-usual projection for 2030, with the possibility of increasing that target to 25% subject to adequate and enhanced access to technology development and transfer, financial resources, and other support. To enable the accomplishment of this pledge, Thailand is looking to enact climate change legislation that functions as a key mechanism for domestic climate action. In 2018, the Office of Natural Resources and Environmental Policy and Planning (ONEP) under the Ministry of Natural Resources and Environment was assigned to prepare a draft Climate Change Act. The draft is now complete, and according to news reports it is set to be submitted to the cabinet for further consideration. The draft Climate Change Act lays out Thailand’s action plan for climate change mitigation and adaptation, including emissions reductions. Some of the key sections in the draft law involve citizen rights, the National Climate Change Policy Committee, and a national GHG database. Rights of Citizens The draft establishes the
August 26, 2022
Thailand’s Board of Investment (BOI) has extended its previously announced period for reduction of import duty on imported raw and essential materials for battery manufacturing for electric vehicles and other applications. The BOI’s announcement No. 5/2565 dated August 8, 2022, extended the reduction period to a maximum of five years. The BOI’s promoted activities list includes two battery-manufacturing business activities: Activity 4.8.3.1 – Battery manufacturing Activity 5.2.6.1 – High energy density battery manufacturing Qualifying battery manufacturers who have cell or module manufacturing processes are eligible for 90% import duty reductions on raw and essential materials that cannot be produced in Thailand. These reductions will be available on an annual basis, and are renewable for five years in total—up from the original two years. Existing projects (i.e., those which have the original two-year duration in their BOI certificate) can also benefit from the extension by preparing a project amendment form, along with a clarification letter and supporting documents, for submission to the BOI office. For more details on these customs duty reductions, or on any aspect of investment promotion in Thailand, please contact Charuwan Charoonchitsathian at [email protected] or +66 2056 5657, or Napassorn Lertussavavivat at [email protected] or +66 2056 5662.
August 16, 2022
On July 21, 2022, Vietnam’s Ministry of Industry and Trade (MOIT) submitted Report No. 126/BC-BCT to the Prime Minister regarding the mechanism for transitional wind and solar power projects. In this report, the MOIT proposed some recommendations to explicitly address difficulties for outstanding wind and solar power projects (“Transitional Projects”) which have been developed under the Prime Minister’s Decision No. 13/2020/QD-TTg dated April 6, 2020, on the development of solar power projects (Decision 13) and Decision No. 37/2011/QD-TTg dated June 29, 2011, on the development of wind power projects (Decision 37), as amended by Decision No. 39/2018/QD-TTg dated September 10, 2018 (Decision 39). The Transitional Projects primarily include those which have completed construction but have not yet been put into operation, and those which have been put into operation but for which the power price has not yet been decided, due to missing the deadline set forth under the aforementioned decisions to be eligible for the feed-in-tariff (FIT). In particular, the MOIT has proposed the following key recommendations to the Prime Minister: Mechanism for Transitional Projects The MOIT proposes two options: Option 1: Developers of the Transitional Projects negotiate and sign power purchase agreements (PPA) with Vietnam Electricity (EVN) within the price framework issued by the MOIT in accordance with the Law on Electricity, the Law on Prices, and their subordinate guiding legislation; or Option 2: The Prime Minister formulates a new decision specifying the mechanism for bidding on the purchase of power produced by the Transitional Projects, estimated to be implemented for the time limit of three years and within the price framework issued by the MOIT. Mechanism for future wind and solar power projects The MOIT proposes to apply the mechanism that developers of future wind and solar projects negotiate the power price and sign the PPA