June 4, 2024

Recent Solar Power Developments in Vietnam

As Vietnam continues its rapid economic development, the demand for sustainable and reliable energy sources has never been more critical. Solar power has emerged as a key component of Vietnam’s strategy to diversify its energy portfolio and reduce its carbon footprint. Recent developments of the regulatory framework governing solar power projects in Vietnam, as discussed below, highlight the country’s commitment to renewable energy and its efforts to create a conducive environment for solar power investments.

Objectives for the Development of Solar Power Projects

On May 15, 2023, the Prime Minister issued Decision No. 500/QD-TTg, approving the National Power Development Plan for 2021-2030 with a vision to 2050 (“PDP VIII”). Following this, on April 1, 2024, the Prime Minister promulgated the Implementation Plan for PDP VIII (“Implementation Plan”). These documents underscore Vietnam’s commitment to promoting renewable energy, particularly solar. They emphasize self-production and self-consumption of solar power, the development of rooftop solar systems, and the promulgation of the direct power purchase mechanism. The integration of solar power with battery storage is also encouraged, contingent upon economic viability.

PDP VIII sets ambitious capacity targets for solar power. By 2030, the capacity is projected to reach approximately 12,836 MW, accounting for 8.5% of the total power capacity. This includes 10,236 MW from concentrated solar power and 2,600 MW from self-production and self-consumption solar power. By 2050, the capacity is expected to rise to between 168,594 MW and 189,294 MW, representing 33.0-34.4% of the total power capacity. Additionally, PDP VIII and the Implementation Plan list 27 solar power projects, totaling 4,136.25 MW, slated for implementation after 2030. However, these projects may be advanced under self-production and self-consumption arrangements.

Draft Decree on Direct Power Purchase Agreements

On April 15, 2024, the Ministry of Industry and Trade (“MOIT”) released a draft decree on direct power purchase agreements (“DPPA”) for public consultation. The draft decree introduces mechanisms for direct power purchases between renewable energy generators, including wind and solar power, and large electricity users, through either private power lines or the national grid. Two mechanisms are proposed under the draft decree:

Physical DPPA: This mechanism allows for direct electricity transactions between power generators and large electricity users through private power lines. The power purchase agreements between the parties must include mandatory content.

Virtual DPPA: Under this mechanism, the power generator sells electricity to large electricity users via the national grid. In terms of structure arrangements:

  • Power generators sell all produced electricity to Vietnam Electricity (EVN) under a model agreement prescribed in the draft decree;
  • Large electricity users purchase electricity from EVN under a power purchase agreement containing mandatory contents; and
  • Large electricity users and power generators sign contracts for differences to manage related risks (e.g., contract term, price, and production output). Generally, the parties have broad discretion to agree to detailed terms and conditions of the contracts.

Draft Decree Encouraging Rooftop Solar Power

The MOIT is also soliciting public feedback on a draft decree aimed at promoting the development of rooftop solar power for self-production and self-consumption. The draft decree distinguishes between two models of rooftop solar systems:

Grid-Connected Systems: These systems must adhere to the capacity limit set in the Implementation Plan, which is 2,600 MW until 2030. They are permitted to inject excess power into the national grid without payment by EVN.

Off-the-Grid Systems: These systems are not subject to capacity limits but cannot transfer surplus electricity to the national grid.

Outlook

Solar power is expected to play a vital role in providing electricity to household and business operations in the near future. The evolution of Vietnam’s regulatory framework, designed to stimulate the growth of solar power in the country, align with national sustainability goals, and enhance energy security through the diversification of renewable energy sources, is a promising sign for investors looking to do business in this space.

RELATED INSIGHTS​ 

January 27, 2025
Thailand’s Ministry of Energy (MOE) has announced the launch of the 25th bidding round for petroleum exploration and production. This round offers nine greenfield onshore blocks—seven in northeastern Thailand and two in central Thailand—encompassing over 33,000 km². The bids can be submitted from July 1 to July 16, 2025. The sizes and locations of these blocks are: Northeast Thailand Block L1/66: 3,223.51 km² (Khon Kaen, Nong Bua Lam Phu, Udon Thani) Block L2/66: 3,917.03 km² (Kalasin, Sakon Nakhon, Udon Thani) Block L3/66: 3,918.22 km² (Kalasin, Khon Kaen, Maha Sarakham, Udon Thani) Block L4/66: 3,656.65 km² (Amnat Charoen, Mukdahan, Nakhon Phanom, Yasothon) Block L5/66: 3,436.01 km² (Chaiyaphum, Khon Kaen, Nakhon Ratchasima) Block L7/66: 3,438.51 km² (Buri Ram, Maha Sarakham, Nakhon Ratchasima, Roi Et, Surin, Khon Kaen) Block L9/66: 3,885.44 km² (Nakhon Ratchasima) Central Thailand Block L6/66: 3,966.86 km² (Chaiyaphum, Lop Buri, Phetchabun) Block L8/66: 3,957.41 km² (Kanchanaburi, Nakhon Pathom, Ratchaburi, Suphan Buri) Bidding Process Interested companies must submit their bids to the Department of Mineral Fuels (DMF) between July 1 and July 16, 2025. Bids should include: Application form (ChorThor/Por1) Proof of eligibility: Corporate documentation, audited financial statements, and proof of resources Technical and commercial proposals: Exploration plans, geological surveys, financial and work commitments, and special benefits such as signing bonuses of at least USD 100,000. There is a nonrefundable THB 50,000 application fee per block, and applicants must provide a bid bond of THB 3 million per block via an unconditional bank guarantee from a commercial bank with branches in Thailand, valid for at least one year from the bidding submission date. The guarantee will be returned to unsuccessful bidders upon request and to successful bidders upon the signing of the concession agreement. Eligibility Bidders must meet the following main eligibility criteria: Bidders must be limited companies with the following qualifications: The company must have the objective of
January 23, 2025
In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges. In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports. The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models. Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include: Allowing additional planning where projects do not violate national security. Allowing rectification of projects’ violations in land and construction process as per law. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered. For items (iv) and (v), the authority will issue regulations
January 14, 2025
Thailand’s Department of Industrial Works (DIW) has issued a new regulation (Ministerial Regulation Re: Designation of Type, Kind, and Size of Factories (No. 3) B.E. 2567 (2024)), which removes the factory license requirement for electricity generation from solar energy installations on rooftops, roof decks, or any part of a building used for residential or other purposes, regardless of capacity. The new rules took effect on December 28, 2024. Under the previous regulations, solar rooftop installations had to seek approval from the DIW if their capacity exceeded 1,000 kW (1 MW), which added time and administrative costs when adopting renewable energy solutions. Benefits and Further Compliance The updated regulation benefits industrial operators by facilitating faster installation times and lower costs, as solar rooftops can now be installed without the need for prior approval of a factory license from the DIW. Operators can now more easily contribute to environmental sustainability and carbon reduction efforts. Despite the lifting of the factory licensing requirement, other compliance obligations, such as an energy business license (or exemption from an energy business license), a controlled energy production license, and a construction permit, may still apply. Reason for the Change Removing the classification of rooftop or building-installed solar power plants as factories aligns with Thailand’s renewable energy goals and reduces regulatory burdens for industrial operators. Additionally, it supports the achievement of energy policies aligned with the UN’s Sustainable Development Goals and Thailand’s international commitments to reduce greenhouse gas emissions through the participation of all sectors. For further details on how this change affects business operations or to explore strategies for renewable energy implementation, please contact Supasit Boonsanong at [email protected], Charuwan Charoonchitsathian at [email protected], or Phareeya Yongpanich at [email protected].
December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.