You are using an outdated browser and your browsing experience will not be optimal. Please update to the latest version of Microsoft Edge, Google Chrome or Mozilla Firefox. Install Microsoft Edge

December 9, 2016

Public-Private Partnerships: Thailand’s Plan for Infrastructure Development

Bangkok Post, Corporate Counsellor Column

The government of Thailand has made it clear that it intends to fully utilize public-private partnerships (PPPs) in order to implement the country’s upcoming infrastructure development goals. The adoption of the Private Investment in State Undertakings Act B.E. 2556 (2013) (PISUA) and the announcement of the Strategic Plan on Private Investment in State Undertakings in 2015 demonstrate the specific policy objectives the government intends to achieve through using PPPs.

In Thailand, for PPP projects that fall under the PISUA, the governmental work units in charge of a particular project are required to offer terms of a joint investment agreement which have been approved by the State Enterprise Policy Office and the Policy Board on Allowing Private Entities to Make Joint Investment in the State’s Business. At minimum, the joint investment agreement is required to contain the period of the project, details concerning the implementation of the project or services to be performed, rates on the service fees and method of payment, assets of the project company and land ownership, as well as other standard clauses such as force majeure, termination and liquidated damages, guarantee and insurance, and dispute resolution.

Although the discussion around PPPs makes it seem as though there is a common contractual framework for each type of project, the reality is that the terms of the agreement between the government agency or ministry and the private investor are quite varied. The agreement form and structure will depend largely on the existence and allocation of various risk factors inherent in PPP projects.

Demand Risk

For instance, the demand by end users for a particular project may be less than what is originally projected—this is often referred to as “demand risk.” For motorway or railroad projects, there is always a great deal of uncertainty surrounding the degree to which the public will make use of additional transport infrastructure. Although part of the technical due diligence of any project will be an assessment of likely demand, it is impossible to predict with absolute certainty the actual demand by consumers once the project is operational. By contrast, demand for power generation in specific geographical areas tends to be more predictable, as current shortfalls and forecasts for increased energy consumption are often more readily apparent. Private parties to energy PPP agreements often mitigate against demand risk by insisting on guaranteed feed-in-tariff rates, or “take-or-pay” terms in the power purchase agreement.

In the concession model—which in Thailand is utilized in a number of sectors such as upstream petroleum production—the agreement allocates the majority of the risks and benefits of successful project implementation to the private entity. This generally includes complete assumption of the demand risk by the concessionaire. By contrast, when the PPP agreement takes the form of an operating and maintenance agreement, the demand risk remains with the public sector while the private entity acts mainly as a service contractor.

In comparison to these more extreme types of PPP arrangements, a “Design-Build” or “Design-Build-Operate” (DBO) model allows the public sector to maintain ownership over the project while allocating the design and construction tasks to a private entity. If the private sector entity is operating the project, it often does so in exchange for fixed fees while the public sector recoups its costs through pay-as-you-go fees from the public. The DBO is a common structure—though not the only structure available—in toll-road projects.

A “Build-Operate-Transfer” (BOT), “Build-Transfer-Operate” (BTO), or “Build-Operate-Own” (BOO) structure shifts ownership, either temporarily or indefinitely, to the private party. Along with the shift in ownership comes greater risk and the potential for greater rewards. The private partners in BOT or BOO contracts are generally responsible for financing the project development. Such structures are commonly used in greenfield power generation projects, particularly when the government or a state-owned entity acts as the off-taker.

According to a report released earlier this year by the ASEAN Secretariat, the Thai Department of Highways (DOH) has been considering the trade-offs between alternative PPP structures with respect to highway toll projects. The DOH is conscious that tolls collected by private investors under a BTO model may be insufficient to cover the costs of the project, and may therefore not be sufficiently attractive to the private sector. On the other hand, a DBO model, or a modification thereof, requires the government to assume a greater degree of risk in the event the highway is underused by the public.

Other Risks

There are other risks which a private investor must consider when bidding on a PPP contract. Political risk and regulatory risk often refer to the possibility of expropriation to the detriment of the private investor, or a change in regulations which would adversely affect the profitability of the private participant. It is difficult to completely mitigate this in the PPP agreement, since these risks are more fundamental to the host state’s capacity and willingness to promote private investment, particularly with regard to public infrastructure works. Thailand has been a model for a number of developing economies, as successive Thai governments have actively encouraged both private investment and PPP projects in general.

Additional risks include environmental risk, insurance risk, social risk, and exchange rate risk. These are only some of the factors which both public and private parties must consider when entering into PPP agreements. Since the public sector generally develops the contractual framework for a particular project prior to offering the tender, it will need to carefully consider which contractual form will best promote the public policy objective while attracting sufficient interest for private investment. Terms which allocate most risks to the private party may be unattractive in some situations, particularly where the rewards of successful project implementation cannot justify the assumption of such risks.

The use of PPPs by states to promote infrastructure development is increasing in popularity not only in Southeast Asia, but across the world. When properly executed, PPPs can be an efficient means to allocate state resources in order to promote economic growth and benefit the public at large. For private investors, the increased use of PPPs in Thailand represents an economic opportunity. Understanding the allocation of risk in PPP agreements and developing strategies to mitigate is a key component to a successful project.

RELATED INSIGHTS​ 

January 3, 2024
Thailand’s Energy Regulatory Commission (ERC) has issued the Notification on the Criteria for Regulating the Licensed Pool Manager B.E. 2566 (2023), which took effect on November 30, 2023. It followed an earlier notification, which took effect on October 13, 2023, that added the new license for the country’s pool gas manager. The new notification aims to regulate natural gas sale agreements and promote competition among players in the regulated natural gas market—that is, those who utilize natural gas for electricity generation under the Electricity Generating Authority of Thailand (EGAT) scheme, including industrial and NGV (natural gas for vehicles) consumers who rely on natural pool gas. The establishment of the pool gas scheme is aimed at encouraging new shippers to enter the market and providing new natural gas shippers with fair opportunities to compete with existing shippers, as all licensed shippers in the regulated market are subject to the same natural gas costs under this new scheme. Under this pool gas scheme, the pool manager plays a critical part in reselling natural gas in the country. Some of its responsibilities include the following: Purchasing natural gas or liquid natural gas (LNG) from licensed shippers in the regulated market at the rate at which the shippers procured the natural gas, including incidental expenses such as pipeline transportation and LNG station fees; Collecting data on the quantity and price of the gas purchased from the licensed shippers and calculating the pool gas price as specified in the ERC-approved manual, which is basically the average price of the natural gas procurement cost of all shippers in the pool; and Reselling natural gas or LNG to licensed shippers at the pool gas pricing rate in the quantity distributed to the pool by each shipper. Apart from its function in facilitating the primary procedures of
December 15, 2023
As part of its membership in Lex Mundi, Tilleke & Gibbins has published an updated edition of its Guide to Doing Business in Thailand for 2023. This guide outlines the key factors for starting and operating a business in the Thai market. Issues covered include: Investment incentives Financial facilities Exchange controls Import and export regulations Structures for doing business Requirements for the Establishment of a Business Operation of the Business Cessation or Termination of the Business Labor legislation, relations, and supply Tax Immigration requirements This publication is part of Lex Mundi’s Country Guides series prepared by member firms in more than 100 jurisdictions worldwide. The guides serve as a useful resource for planning international business strategy and researching new markets. The full Guide to Doing Business in Thailand is available through the button below.
July 25, 2023
Thailand’s Energy Regulatory Commission (ERC) is in the process of reviewing a draft regulation that updates the nationality qualifications for the ultimate shareholders and directors of applicants for an energy business license. The draft ERC Regulation Re: Qualifications, Documents and Application for Electricity Business—which is intended to replace the ERC Regulation Re: Application and Permission for Electricity Business B.E. 2551 and its amendments—is likely to be adopted soon and will affect licensed companies that are foreign majority owned when they apply for or renew their energy business licenses. The draft regulation requires partnerships, limited companies, and public limited companies to have the following qualifications unless there is an international agreement granting national treatment for a specific commitment (mode 3 or mode 4) or exemption by other laws: Juristic persons must be established under Thai law or registered in Thailand with the objective of carrying out electricity business; For private limited companies, foreign ultimate shareholders must not hold more than 49% of the total shares, and the number of the foreign shareholders must not exceed half of all shareholders; At least half of all directors must have Thai nationality; and Any authorized directors must have Thai nationality. When the draft regulation is adopted, it will not take retroactive effect on previously granted energy business licenses, which will continue to be valid until they expire if there is no material change to the license as defined by the draft regulation. Once the license is up for renewal (energy business licenses are normally issued for a specific period of time), it will be subject to the draft regulation. All license applications submitted prior to the effective date of the draft regulation and under consideration will be deemed applications for a license under the draft regulation. As noted above, the new qualification requirements
July 7, 2023
Cambodia has the potential to be one of the top countries in the world for generating renewable energy through solar, based on the average amount of sunlight hours available per day and the consistent sunshine throughout the year. The Cambodian government has recognized this potential and has made major updates to its energy policies in recent years. Solar power is now taking over a much larger portion of the total energy mix in Cambodia, especially as a number of utility-scale solar power plants have come online in recent years. The long-term Power Development Master Plan 2022–2040 sets out the long-term energy policy for Cambodia and requires a bigger role for renewables. The use of solar power will play a key role in this aim to increase the role of renewables, with the plan foreseeing almost 30% of all national power generated through solar technologies by 2040. Two of the latest legislative and regulatory steps by the government are the Ministry of Mines and Energy’s guidelines for rooftop solar systems, and most recently the long-awaited Environment and Natural Resources Code, which was enacted on June 29, 2023. Rooftop Solar Projects Many companies, from small startups to multinationals, are exploring the potential for rooftop solar in Cambodia. However, despite the favorable natural factors, the regulatory framework was not always clear or friendly to rooftop solar, hampering investment. This started slowly changing with the adoption of the first solar energy regulation in 2018, which provided the country’s first official guidance on both solar power plants and rooftop solar. It provided some much-needed clarity, but the 2018 solar energy regulation—and especially the subsequent electricity tariff schemes—often kept rooftop projects from being financially viable. Many players in the industry voiced their doubts about the regulations and tariffs, focusing especially on the capacity charge—a monthly