Public-Private Partnerships: Thailand’s Plan for Infrastructure Development

Bangkok Post, Corporate Counsellor Column

The government of Thailand has made it clear that it intends to fully utilize public-private partnerships (PPPs) in order to implement the country’s upcoming infrastructure development goals. The adoption of the Private Investment in State Undertakings Act B.E. 2556 (2013) (PISUA) and the announcement of the Strategic Plan on Private Investment in State Undertakings in 2015 demonstrate the specific policy objectives the government intends to achieve through using PPPs.

In Thailand, for PPP projects that fall under the PISUA, the governmental work units in charge of a particular project are required to offer terms of a joint investment agreement which have been approved by the State Enterprise Policy Office and the Policy Board on Allowing Private Entities to Make Joint Investment in the State’s Business. At minimum, the joint investment agreement is required to contain the period of the project, details concerning the implementation of the project or services to be performed, rates on the service fees and method of payment, assets of the project company and land ownership, as well as other standard clauses such as force majeure, termination and liquidated damages, guarantee and insurance, and dispute resolution.

Although the discussion around PPPs makes it seem as though there is a common contractual framework for each type of project, the reality is that the terms of the agreement between the government agency or ministry and the private investor are quite varied. The agreement form and structure will depend largely on the existence and allocation of various risk factors inherent in PPP projects.

Demand Risk

For instance, the demand by end users for a particular project may be less than what is originally projected—this is often referred to as “demand risk.” For motorway or railroad projects, there is always a great deal of uncertainty surrounding the degree to which the public will make use of additional transport infrastructure. Although part of the technical due diligence of any project will be an assessment of likely demand, it is impossible to predict with absolute certainty the actual demand by consumers once the project is operational. By contrast, demand for power generation in specific geographical areas tends to be more predictable, as current shortfalls and forecasts for increased energy consumption are often more readily apparent. Private parties to energy PPP agreements often mitigate against demand risk by insisting on guaranteed feed-in-tariff rates, or “take-or-pay” terms in the power purchase agreement.

In the concession model—which in Thailand is utilized in a number of sectors such as upstream petroleum production—the agreement allocates the majority of the risks and benefits of successful project implementation to the private entity. This generally includes complete assumption of the demand risk by the concessionaire. By contrast, when the PPP agreement takes the form of an operating and maintenance agreement, the demand risk remains with the public sector while the private entity acts mainly as a service contractor.

In comparison to these more extreme types of PPP arrangements, a “Design-Build” or “Design-Build-Operate” (DBO) model allows the public sector to maintain ownership over the project while allocating the design and construction tasks to a private entity. If the private sector entity is operating the project, it often does so in exchange for fixed fees while the public sector recoups its costs through pay-as-you-go fees from the public. The DBO is a common structure—though not the only structure available—in toll-road projects.

A “Build-Operate-Transfer” (BOT), “Build-Transfer-Operate” (BTO), or “Build-Operate-Own” (BOO) structure shifts ownership, either temporarily or indefinitely, to the private party. Along with the shift in ownership comes greater risk and the potential for greater rewards. The private partners in BOT or BOO contracts are generally responsible for financing the project development. Such structures are commonly used in greenfield power generation projects, particularly when the government or a state-owned entity acts as the off-taker.

According to a report released earlier this year by the ASEAN Secretariat, the Thai Department of Highways (DOH) has been considering the trade-offs between alternative PPP structures with respect to highway toll projects. The DOH is conscious that tolls collected by private investors under a BTO model may be insufficient to cover the costs of the project, and may therefore not be sufficiently attractive to the private sector. On the other hand, a DBO model, or a modification thereof, requires the government to assume a greater degree of risk in the event the highway is underused by the public.

Other Risks

There are other risks which a private investor must consider when bidding on a PPP contract. Political risk and regulatory risk often refer to the possibility of expropriation to the detriment of the private investor, or a change in regulations which would adversely affect the profitability of the private participant. It is difficult to completely mitigate this in the PPP agreement, since these risks are more fundamental to the host state’s capacity and willingness to promote private investment, particularly with regard to public infrastructure works. Thailand has been a model for a number of developing economies, as successive Thai governments have actively encouraged both private investment and PPP projects in general.

Additional risks include environmental risk, insurance risk, social risk, and exchange rate risk. These are only some of the factors which both public and private parties must consider when entering into PPP agreements. Since the public sector generally develops the contractual framework for a particular project prior to offering the tender, it will need to carefully consider which contractual form will best promote the public policy objective while attracting sufficient interest for private investment. Terms which allocate most risks to the private party may be unattractive in some situations, particularly where the rewards of successful project implementation cannot justify the assumption of such risks.

The use of PPPs by states to promote infrastructure development is increasing in popularity not only in Southeast Asia, but across the world. When properly executed, PPPs can be an efficient means to allocate state resources in order to promote economic growth and benefit the public at large. For private investors, the increased use of PPPs in Thailand represents an economic opportunity. Understanding the allocation of risk in PPP agreements and developing strategies to mitigate is a key component to a successful project.

RELATED INSIGHTS​ 

June 3, 2024
Nearly a year after Vietnam’s issuance of its National Power Development Plan for 2021-2030, with a vision to 2050 (“PDP VIII”), the Prime Minister issued Decision No. 262/QD-TTg dated April 1, 2024, approving the Implementation Plan for PDP VIII (“Implementation Plan”). Among other contents, the Implementation Plan sets forth the list of prioritized power source projects through 2030, and the capacity of renewable energy sources through 2030, as detailed below. Prioritized Power Source Projects through 2030 The Implementation Plan lists out six types of power source projects prioritized for development through 2023 according to the capacity approved under PDP VIII. They include: Domestic gas-fired power (14,930 MW) LNG-fired power (22,400 MW) Coal-fired power (30,127 MW) Cogeneration power using residual heat, blast furnace gas, and by-products of technological lines in industrial facilities (2,700 MW) Hydropower (29,346 MW) Pumped storage hydropower (2,400 MW) With respect to each type, the Implementation Plan provides details of projects by location and their operational progress. Such information is set out in Schedule III of the Implementation Plan. For power source projects not included in this list, the provincial People’s Committees will consult with the Ministry of Industry and Trade (“MOIT”) and relevant agencies on compliance with the planning prior to appraisal and issuance of in-principle investment approval. Renewable Energy Projects through 2030 The Implementation Plan allocates the capacity of the following renewable energy sources by locality/region: Offshore wind power (6,000 MW) Onshore wind power (21,880 MW) Hydroelectric power (29,346 MW) Biomass electricity (1,088 MW) Electricity produced from waste (1,182 MW) Rooftop solar power for self-production and self-consumption (2,600 MW) Battery storage (300 MW) With respect to each renewable energy source, the Implementation Plan provides a list of certain renewable energy projects through 2030, including the expected life cycle of the projects, and the allocated capacity
April 29, 2024
On November 4, 2021, Cambodia’s Ministry of Mines and Energy (MME) issued a Prakas No. 0305 on Management of the Steam Energy Subsector within the Energy Sector. The prakas aims to regulate steam energy operations, and requires companies wishing to develop, build, install, or operate steam energy to apply for a steam energy license. As this is the first prakas regulating steam energy operations in Cambodia, all relevant companies operating in steam energy must apply for a steam energy license with the MME. Prakas 0305 discusses permits for three types of activities: Development, Construction, Installation, and Operation of Steam Energy. Companies wishing to develop, build, install, and operate steam energy production facilities must first apply for a permit from the MME. Steam Energy Service Provision. Companies wishing to develop, build, install, and operate steam energy for the purpose of supplying steam energy to consumers must apply for a permit for steam energy service provider in addition to a permit for development, construction, installation, and operation of steam energy. Two-in-One Steam Energy and Electricity Production. Companies wishing to develop and operate both steam energy and electricity production activities must also apply for a permit for two-in-one steam energy and electricity production. Companies operating without the necessary permits are subject to a daily fine of KHR 400,000–4,000,000 (approx. USD 100–1,000). In addition, they may face other penalties, including: An order to halt business activities; Permit suspension; Permit revocation; Judicial action; and Other legal measures as the MME deems fit. For more information on regulations and requirements for steam energy licenses in Cambodia, please contact Tilleke & Gibbins at [email protected].
January 25, 2024
Thailand’s Department of Mineral Fuels (DMF) has developed a framework to regulate carbon capture and storage (CCS) and related activities by introducing “carbon business” to the draft amendment to the Petroleum Act B.E. 2514 (1971). CCS involves the capture, treatment, transport, and underground storage of carbon dioxide produced from industrial power generation. The captured carbon can be used to enhance oil recovery, converted into fuel such as methane or DME (dimethyl ether), or converted to higher-value products. In Thailand, various companies have carried out CCS feasibility studies. Carbon Business and Licensing Under the draft amendment to the Petroleum Act, “carbon business” is defined as exploration for purposes of carbon storage or compression of carbon into carbon storage, while “carbon” is defined as carbon dioxide in the state of gas or supercritical fluid generated as a byproduct or captured from other sources and transported for storage. Any concessionaire, product-sharing contractor, or service contract holder that has been granted permission to explore for or produce petroleum under the Petroleum Act can apply for a carbon business license from the director-general of the DMF with the approval of the Petroleum Committee. Licenses are also available to any other parties who meet the eligibility criteria to be prescribed later by a ministerial regulation. Licenses for these parties will be allocated through competitive bidding according to procedures to be announced by the minister of the Ministry of Energy (MOE). In granting a license, the minister of the MOE and the director-general of the DMF will consider the geological suitability of carbon storage, storage systems, surrounding areas of carbon storage, risk of carbon leakage and movement, environmental impacts, and the applicant’s financial potential and ability in environmental management. Responsibilities of Carbon Business Operators Carbon business operators are required to monitor and inspect their installations, structures,
January 10, 2024
On December 15, 2023, the Electricity Authority of Cambodia (EAC) issued a notification requiring all owners of solar power systems to report their systems to their local electricity supplier by January 31, 2024. Systems that have already been reported under existing regulations are exempt from this requirement. Systems that remain unreported after the deadline will be deemed illegal and subject to penalties, including possible disconnection from the national grid. The rationale for the reporting requirement is that the EAC expects to adopt a new solar power regulation soon. Electricite du Cambodge (the main state-owned utility provider in Cambodia) and EAC-licensed private electricity providers are now gathering data on the current use of solar power systems in order to prepare for, adopt, and execute the upcoming regulation. The reporting requirement is to facilitate this gathering of data. The upcoming regulation, planned for early 2024 according to the notification, follows last year’s Prakas No. 159, which contained the Ministry of Mines and Energy’s guidelines and principles for rooftop solar systems. The EAC now needs to issue implementing regulations that are in line with the ministry’s guidelines and principles. Although stand-alone solar power systems that did not have a connection to the national grid were previously not regulated and did not require any authorizations, the EAC is now stating that all types of solar power systems need to adhere to the reporting requirement under the notification. According to the EAC, the upcoming regulation will address all types of systems, and the December 15 notification clearly announces that all types of solar power systems will need to obtain EAC approval under the upcoming regulation. Solar power system operators in Cambodia should report their systems to their local electricity providers by January 31, 2024, to avoid any penalties, while remaining vigilant for the upcoming