Public-Private Partnerships: Thailand’s Plan for Infrastructure Development

Bangkok Post, Corporate Counsellor Column

The government of Thailand has made it clear that it intends to fully utilize public-private partnerships (PPPs) in order to implement the country’s upcoming infrastructure development goals. The adoption of the Private Investment in State Undertakings Act B.E. 2556 (2013) (PISUA) and the announcement of the Strategic Plan on Private Investment in State Undertakings in 2015 demonstrate the specific policy objectives the government intends to achieve through using PPPs.

In Thailand, for PPP projects that fall under the PISUA, the governmental work units in charge of a particular project are required to offer terms of a joint investment agreement which have been approved by the State Enterprise Policy Office and the Policy Board on Allowing Private Entities to Make Joint Investment in the State’s Business. At minimum, the joint investment agreement is required to contain the period of the project, details concerning the implementation of the project or services to be performed, rates on the service fees and method of payment, assets of the project company and land ownership, as well as other standard clauses such as force majeure, termination and liquidated damages, guarantee and insurance, and dispute resolution.

Although the discussion around PPPs makes it seem as though there is a common contractual framework for each type of project, the reality is that the terms of the agreement between the government agency or ministry and the private investor are quite varied. The agreement form and structure will depend largely on the existence and allocation of various risk factors inherent in PPP projects.

Demand Risk

For instance, the demand by end users for a particular project may be less than what is originally projected—this is often referred to as “demand risk.” For motorway or railroad projects, there is always a great deal of uncertainty surrounding the degree to which the public will make use of additional transport infrastructure. Although part of the technical due diligence of any project will be an assessment of likely demand, it is impossible to predict with absolute certainty the actual demand by consumers once the project is operational. By contrast, demand for power generation in specific geographical areas tends to be more predictable, as current shortfalls and forecasts for increased energy consumption are often more readily apparent. Private parties to energy PPP agreements often mitigate against demand risk by insisting on guaranteed feed-in-tariff rates, or “take-or-pay” terms in the power purchase agreement.

In the concession model—which in Thailand is utilized in a number of sectors such as upstream petroleum production—the agreement allocates the majority of the risks and benefits of successful project implementation to the private entity. This generally includes complete assumption of the demand risk by the concessionaire. By contrast, when the PPP agreement takes the form of an operating and maintenance agreement, the demand risk remains with the public sector while the private entity acts mainly as a service contractor.

In comparison to these more extreme types of PPP arrangements, a “Design-Build” or “Design-Build-Operate” (DBO) model allows the public sector to maintain ownership over the project while allocating the design and construction tasks to a private entity. If the private sector entity is operating the project, it often does so in exchange for fixed fees while the public sector recoups its costs through pay-as-you-go fees from the public. The DBO is a common structure—though not the only structure available—in toll-road projects.

A “Build-Operate-Transfer” (BOT), “Build-Transfer-Operate” (BTO), or “Build-Operate-Own” (BOO) structure shifts ownership, either temporarily or indefinitely, to the private party. Along with the shift in ownership comes greater risk and the potential for greater rewards. The private partners in BOT or BOO contracts are generally responsible for financing the project development. Such structures are commonly used in greenfield power generation projects, particularly when the government or a state-owned entity acts as the off-taker.

According to a report released earlier this year by the ASEAN Secretariat, the Thai Department of Highways (DOH) has been considering the trade-offs between alternative PPP structures with respect to highway toll projects. The DOH is conscious that tolls collected by private investors under a BTO model may be insufficient to cover the costs of the project, and may therefore not be sufficiently attractive to the private sector. On the other hand, a DBO model, or a modification thereof, requires the government to assume a greater degree of risk in the event the highway is underused by the public.

Other Risks

There are other risks which a private investor must consider when bidding on a PPP contract. Political risk and regulatory risk often refer to the possibility of expropriation to the detriment of the private investor, or a change in regulations which would adversely affect the profitability of the private participant. It is difficult to completely mitigate this in the PPP agreement, since these risks are more fundamental to the host state’s capacity and willingness to promote private investment, particularly with regard to public infrastructure works. Thailand has been a model for a number of developing economies, as successive Thai governments have actively encouraged both private investment and PPP projects in general.

Additional risks include environmental risk, insurance risk, social risk, and exchange rate risk. These are only some of the factors which both public and private parties must consider when entering into PPP agreements. Since the public sector generally develops the contractual framework for a particular project prior to offering the tender, it will need to carefully consider which contractual form will best promote the public policy objective while attracting sufficient interest for private investment. Terms which allocate most risks to the private party may be unattractive in some situations, particularly where the rewards of successful project implementation cannot justify the assumption of such risks.

The use of PPPs by states to promote infrastructure development is increasing in popularity not only in Southeast Asia, but across the world. When properly executed, PPPs can be an efficient means to allocate state resources in order to promote economic growth and benefit the public at large. For private investors, the increased use of PPPs in Thailand represents an economic opportunity. Understanding the allocation of risk in PPP agreements and developing strategies to mitigate is a key component to a successful project.

RELATED INSIGHTS​ 

August 2, 2022
The Ministry of Energy is preparing to open a bidding round for the right to explore and produce petroleum in three offshore exploration blocks in the Gulf of Thailand: Exploration Block Nos. G1/65, G2/65, and G3/65. Announced in April 2022 with an eye toward national energy sustainability and security, this is the first opportunity for exploration of new offshore areas in 15 years. The total area of the three exploration blocks is 35,164.01 square kilometers, and operations in the exploration blocks will be subject to the terms and conditions of the required production sharing contract (PSC). Under the PSC, the Thai government is entitled to receive royalty payments against profits, any applicable cost recovery, and profit petroleum. The government also has the authority to monitor the petroleum operations in collaboration with the successful bidder. On July 27, 2022, the Department of Mineral Fuels (DMF) held a conference for prospective investors in order to clarify general information regarding the petroleum bidding round. Currently, interested investors can request the right to enter the bidding-round data room located at the DMF by emailing [email protected] by September 2, 2022. To participate in the bidding round, interested investors must submit an application together with required documents to the DMF during the period of September 5–16, 2022. For further information on the bidding round, or on any aspect of energy law in Thailand, please contact Tilleke & Gibbins at [email protected] or +66 2056 5555.
February 28, 2022
On February 9, 2022, the Director-General of the Department of Mineral Fuels (DMF) stated that the DMF is planning to request that the Deputy Prime Minister and the Minister of Energy sign an invitation to open bids for Petroleum Exploration and Production Licenses in the Gulf of Thailand for the first time in 15 years. The DMF’s Chief Department expects that this auction, which will cover three offshore areas, could increase Thailand’s petroleum reserves, and it could lead to the possible discovery of new sources of petroleum for Thailand, which would boost the country’s energy resources, and reduce losses from energy imports. The plots in the Gulf of Thailand that will be auctioned in the 24th bid round are as follows: Plot No. G1/65 with a total area of 8,487 square kilometers. This area is divided into 2 sub-areas: Area A totaling 8,298.49 square kilometers, and Area B totaling 188.71 square kilometers; Plot G2/65 with a total area of 15,030 square kilometers; and Plot No. G3/65 with a total area of 11,646.67 square kilometers. This area is divided into 2 sub-areas: Area A totaling 11,028.22 square kilometers, and Area B totaling 618.45 square kilometers. Generally, Thailand initiates its concession and production sharing contract process with the announcement of an exploration area or a plot in the Government Gazette. Thereafter, the DMF Committee will consider and announce the invitation, so that private sector firms can submit their applications to receive respective rights. The DMF’s sub-committee will consider the applications by: checking the qualifications stipulated under Section 24 of the Petroleum Act; assessing the suitability of the exploration project; and determining the benefits which are offered by the applicant. After considering the requests, the DMF’s sub-committee will consider the petroleum laws and regulations, before submitting the matter to the Petroleum Committee—under
February 22, 2022
The many new and unique challenges in recent years—from epidemics, to travel restrictions, to supply chain disruptions and energy-related reactions to all of the above, we have all had to adjust to a new status quo. The energy industry has felt these impacts acutely, and as the industry seeks to meet the current challenges and move forward toward a more sustainable future, it is helpful to take stock of where things stand and where they might be headed in the coming years. In the midst of this uncertainty, Energy Law in Southeast Asia by the Tilleke & Gibbins Energy Industry Team seeks to provide clarity on the legal and regulatory environment surrounding energy industry activities. Each chapter of Energy Law in Southeast Asia takes the reader through the essential information surrounding energy and environmental regulations in general and the specific laws and practices for the major areas of energy projects—both in terms of the current energy mix and the sources taking on a larger role as we transition toward a lower-carbon future. These chapter subsections are: Regulatory Structure Oil and Gas Coal Solar Wind Hydropower Biomass and Biogas Environmental Regulations In providing this legal overview of major areas across the spectrum of energy projects in Southeast Asia, we have sought to create a resource for all involved in the energy industry, regardless of their specific area of interest or the different obstacles or challenges they seek to resolve. Energy Law in Southeast Asia is written by specialists on Tilleke & Gibbins’ Energy Industry Team, who together have over 200 years of accumulated energy experience. Spread throughout Tilleke & Gibbins’ offices in Southeast Asia, they function both as an integrated regional team to advise multinational enterprises on their regional energy project portfolios, and as experts for investors and companies looking
January 27, 2022
The Energy Generating Authority of Thailand (EGAT) has launched a pilot project to study the energy consumption and the economic, social, and environmental impact of electric motorcycle taxis, as well as the behavior of drivers and passengers. The project, which was launched on December 27, 2021, as part of EGAT’s Carbon Neutrality Policy, will continue for a year, after which EGAT will consider the data and decide whether electric motorcycle taxis should be introduced nationwide. EGAT is also currently encouraging the use of electric bikes within their own organization, and they initially expect this to help reduce annual carbon dioxide emissions by 37 tons and prevent the release of about 838,000 milligrams of dust per year. EGAT expects additional significant reductions from electric motorcycle taxi pilot projects in multiple locations. A study conducted in Kenya in 2015 by that country’s energy regulator found that sub-150cc motorcycles emit approximately 46.5 grams of carbon dioxide per kilometer, and these emissions increase proportionally in accordance with engine size. According to Thailand’s Office of Industrial Economics, citing data collected by the Federation of Thai Industries Automotive Industry Group, a total of 1,516,096 motorcycles were sold in Thailand in 2020—a surprisingly robust figure in light of the impact of the COVID-19 pandemic. Assuming that public motorcycles travel an average of 15,000 kilometers per year, each motorcycle is therefore producing approximately 0.7 tons of carbon dioxide per year. If Thailand is able to change 50% of its yearly sales of standard motorcycle to electric motorcycles, annual carbon dioxide emissions could decrease by approximately 530,000 tons. Furthermore, since 28.8% of carbon dioxide emissions in Thailand are generated from the transport sector, the transition to electric mobility vehicles looks to be one of the most promising solutions for lowering carbon dioxide emissions in the country. Considering developments