PTIT Focus: Settlement of Disputes through Arbitration in a Thai Concession Agreement

Petroleum Institute of Thailand: PTIT Focus

With reference to the concession agreement form, as issued under the Ministerial Regulations of the Ministry of Energy regarding the Form for the Designation of a Concession Agreement B.E. 2555 (2012) (“Ministerial Regulations re: the Concession Agreement Form”), the form includes a provision that is related to dispute resolution by arbitration, as set out in Clause 13 of the Concession Agreement.

The principle here applies to scenarios in which (1) a dispute arises in connection with the Minister’s instructions, which requires the concessionaire to rectify a circumstance that constitutes grounds for revocation of the Concession under Section 52 of the Petroleum Act B.E. 2514 (1971), or (2) a dispute exists in respect to the question of whether or not there has been full compliance with the provisions of the Concession, and the parties cannot reach a mutual settlement within 60 days from the date on which one party issued a notice to the other party. In such a scenario, both parties shall settle the dispute through arbitration in accordance with the Arbitration Rules as prescribed by the United Nations Commission on International Trade Law (“UNCITRAL Arbitration Rules”). The version of the UNCITRAL Arbitration Rules to be used is the version that is valid on the date the dispute was submitted to the arbitrators.

This principle differs from the previous Concession Agreement Form that was issued under Ministerial Regulation no.4 (B.E. 2514) (1971) and Ministerial Regulation no.7 (B.E. 2532) (1989). This stipulated use of the arbitration rules of the International Court of Justice (“ICJ Arbitration Rules”), which still bind the parties that entered into such concession agreement.

Settlement of a dispute through arbitration is a type of dispute resolution whereby the parties can mutually agree to have a third party, which could either be a sole arbitrator or a group of arbitrators who have specific knowledge and expertise about the disputed issue, act as the person(s) who will consider and decide on the civil dispute that has arisen. Settlement of disputes through arbitration has many advantages, such as (1) offering a convenient and fast process; (2) having few complicated steps involved; and (3) enabling decision-making by persons with specific expertise. In addition, arbitration proceedings remain confidential, and therefore, business information and the reputation of the parties are still maintained. Furthermore, arbitration awards are also enforceable in many countries.

In respect to the award rendered by the arbitrators, the Ministerial Regulations also specify conditions in the Concession Agreement Form that require the arbitrators to take into account the laws of Thailand, and the principles of international laws that may be applicable, and also determine whether the expenses and fees of the arbitrators shall be borne solely by either party or shared proportionately by both parties. The award has to be rendered in writing and specify the reasons for the decision. The award shall be final and binding on both parties.

With reference to the Concession Agreement Form, the place of arbitration shall be in Bangkok, Thailand, unless the parties agree otherwise. The language used in the arbitration procedures shall be in Thai, except where both parties mutually agree to use English.

In addition, the Concession Agreement Form also designates those matters that shall not be referred to arbitrators, which are as follows: (1) criminal offences under the Petroleum Act B.E. 2514 (1971); (2) disputes in connection with the Petroleum Act B.E. 2514 (1971) where the concessionaire has initiated proceedings in a Thai court; and (3) disputes on rulings, or orders, which are treated as final under the Petroleum Act B.E. 2514 (1971).

In conclusion, the clause relating to dispute settlement through arbitration in the Concession Agreement Form designates the rules, form, process, place, and language to be used in the proceedings for the purpose of clarity in the dispute resolution. Arbitration procedures also provide advantages that can help expedite dispute settlements, reduce complicated procedures, and experts to issue awards on the disputes in question. In addition, the arbitration proceedings also serve to maintain full confidentiality regarding the business information of the parties involved.

 

This article first appeared in the April 2019 edition of PTIT Focus, the Petroleum Institute of Thailand’s monthly newsletter. The article was published in both English and Thai. For the original publication, please see the PDF below.

RELATED INSIGHTS​ 

May 19, 2023
On May 15, 2023, Vietnam’s Deputy Prime Minister Tran Hong Ha signed Decision No. 500 of the Prime Minister approving the National Power Development Plan for the period 2021-2030, with a vision to 2050 (“PDP VIII”), following extensive public consultations and multiple rounds of review since the first draft version was circulated in 2021. The plan was approved in the context that in the past few years, a number of large power projects have been behind schedule for operation, while new projects have not been able to be implemented due to waiting for additional planning. PDP VIII is the master plan for the development of the power source and transmission grid at 220kV or higher; services in renewable energy and new energy in Vietnam; and works connecting the power grids of Vietnam and neighboring countries. We set out below some quick updates regarding PDP VIII. 1. Development Targets Key development targets are summarized in the table below: Investors in coal, domestic gas, and LNG projects may need to have a conversion plan ready given the 2050 targets to convert to other sources of energy. 2. Solar Projects A list of 27 solar power projects that were planned for the period of 2021-2030 but which have not been assigned to investors are not allowed to be deployed but can be considered after 2030, except in the case of deployment in the form of self-production and self-consumption (Appendix IV). These projects represent 4,136.25 MW of capacity that will be left on the sidelines until 2030. 3. Hydropower Projects A list of 14 potential hydropower projects can be considered if economic and technical conditions allow for more hydropower development (Appendix III). These projects represent 1,244 MW of capacity that can be added to the hydropower targets for 2030. 4. Projects Prioritized for
March 22, 2023
Attorneys from Tilleke & Gibbins have contributed the Cambodia, Laos, Myanmar, and Vietnam sections to DLA Piper’s Global Government Contracting Country by Country guide, which provides essential information for businesses in 75 jurisdictions on how to source and enter into government contracting opportunities. The guide provides procurement information for jurisdictions in Africa, the Americas, Asia-Pacific, Europe, and the Middle East, and includes information on how to find procurement opportunities, the structure of procurement laws, and in-country resources and relevant publications. Each jurisdictional section includes valuable information on procedures for government tenders, bidding, and contract execution, as well as an overview of the legal and regulatory framework governing government procurement. Businesses can refer to the guide to gain a better understanding of procurement processes and regulations in each jurisdiction, which can help them identify potential opportunities and make informed decisions when pursuing government contracts. The guide’s procurement information for Cambodia, Laos, Myanmar, and Vietnam, combined with the online platform’s comprehensive resources, provides businesses and governments with a valuable tool to navigate the complex regulatory landscape of government contracting in the region. The full Global Contracting Country-by-Country guide is available on the DLA Piper website.
February 20, 2023
On December 20, 2022, the Notification re: Rules, Procedures, and Conditions on Transfer of Energy Licenses of the Thailand Energy Regulatory Commission (ERC) became effective. The notification sets out the new standard and procedure for transferring licenses for energy industry operation. The notable changes in the notification are provided below. Anti-Competition Consideration and Impact Assessment Report In considering the transfer of a license, in addition to ensuring the transferee meets all the qualifications for an applicant for the license, the ERC will consider if the transfer would (1) create a monopoly, reduce or restrict competition, or result in market dominance; (2) affect the contracting parties of the transferors or energy users; or (3) affect energy security or the public interest. In this respect, the vetting process for an application for license transfer would be separated into two different approaches. If the ERC believes that the transfer of the energy license would affect competition, energy users, energy security, or the public interest, the transferor will need to submit an impact assessment report on the license transfer to the ERC. In this regard, the ERC may establish a sub-committee or an independent consultant to contemplate the transfer at the transferor’s expense. However, if the ERC believes that the transfer of license would not lead to any impact, the transferor will not be required to submit the impact assessment. Also, if the license transfer is related to any transactions specified under the ERC’s Regulation re: Rules and Procedures on Merger and Cross-Shareholding in Energy Businesses, B.E. 2565, the ERC can combine the license transfer application with the M&A application. After approval, the ERC might require the transferee to periodically report to the ERC and comply with measures stipulated by the ERC. Therefore, an energy license holder which plans to carry out M&A
February 3, 2023
The Federation of Thai Industries (FTI) announced on January 16, 2023, the opening of registration for carbon credit trading on its Renewable Energy and Carbon Credit Exchange Platform. This new online platform supports the domestic carbon market and provides Thai exporters with the ability to purchase carbon credits, allowing them to address demands from importing nations to conform to carbon emission reduction regulations. This is expected to be a positive step forward for the current practice in Thailand, in which the carbon market operates as a voluntary and unregulated buy-sell platform, free from government regulation. Developed in partnership with the Thailand Greenhouse Gas Management Organization (TGO), the FTI: CC/RE/REC X Platform, or FTIX, is intended to increase the promotion of national carbon credits, renewable energy, and renewable energy certificates, thus improving the country’s efforts to mitigate climate change. Entrepreneurs interested in registering for carbon credit trading on the FTIX can do so through the FTIX website at fti-cc.com. The platform initially supports carbon credit trading through over-the-counter methods. In the near future, the FTIX will be developed to support 100% renewable energy (i.e., RE100 energy) and renewable energy certificate trading. However, the related tax and carbon pricing policies have not yet been issued. The TGO is currently in discussions with the Fiscal Policy Office and the Ministry of Finance regarding fiscal policy for the FTIX. For more information on the FTIX, or on any aspect of renewable energy activities in Thailand, please contact Charuwan Charoonchitsathian at [email protected], Napassorn Lertussavavivat at [email protected], or Ratchapat Triteeyaputranonta at [email protected].