PTIT Focus: Providing Reports and Plans in Accordance with Environmental Management Procedures for the Decommissioning of Installations Used in the Petroleum Industry

Petroleum Institute of Thailand: PTIT Focus

Providing Reports and Plans in Accordance with Environmental Management Procedures for the Decommissioning of Installations Used in the Petroleum Industry

Clause 4 of the Ministerial Regulations Prescribing the Plan, Estimated Cost and Security for Decommissioning Installations Used in the Petroleum Industry B.E. 2559 (2016), which is issued under Section 14 (5), Section 80/1, and Section 80/2 of the Petroleum Act B.E. 2514 (1971), as amended by the Petroleum Act B.E.2514 (1971) (No.6) B.E.2550 (2007), provides that a concessionaire has the responsibility to proceed with environmental management procedures for the decommissioning of installations used in the petroleum industry, in order to effectively promote and preserve the quality of the environment. In addition, the procedures also cover research on environmental impact. The principles, procedures, and conditions of such reports and plans must be pursuant to the announcement of the Department of Mineral Fuels (DMF).

On 26 June 2018, the DMF issued the Announcement Prescribing the Principles, Procedures and Conditions for Providing the Reports and Plans in Regard to the Environmental Management Procedures for the Decommissioning of Installations Used. This announcement aims to ensure that the quality of the environment is effectively nurtured and preserved in the event that the installations or the area used for petroleum operations is decommissioned; it also covers research on environmental impact. The announcement prescribes that the concessionaire has the responsibility to provide a report and plan in accordance with a set of four environmental management procedures to the director-general of the DMF for approval, as follows:

  1. Decommissioning Environmental Assessment Report (DEA report): The DEA report must include (1) the installations that will be decommissioned; (2) procedures; (3) duration; (4) environmental information; (5) impact; and (6) the protection policy and monitoring plan. The DEA report must be prepared by a person who is licensed by the Office of Natural Resources and Environmental Policy and Planning to provide environmental impact assessment reports. Prior to providing the DEA report, the concessionaire will have to provide a report defining the scope of the research and the stakeholder plan for the approval of the director-general of the DMF.
  2. Best Practical Environmental Option Report (BPEO report): The concessionaire must consider the best and most suitable option for proceeding with the decommissioning, from all the options prescribed in the DEA report that was approved by the director-general of the DMF. The BPEO report must include important details such as the options and methods for decommissioning, procedures and criteria, and a summary of the most suitable option for proceeding with the decommissioning.
  3. Decommissioning Activity Environmental Management Plan (DEM plan): The DEM plan is related to the permanent closure and abandonment of the well, or the decommissioning, withdrawal, transportation, or demolition of the unused installation. The concessionaire has to lay out, among other things, (1) measures for protection and mitigation of environmental impact, (2) a cleaning plan, (3) removal of any contamination, and (4) a waste management plan. During the decommissioning process, the concessionaire must deliver an audit report on the operations in accordance with the aforementioned plans to the General Director of the DMF within 180 days of finishing the decommissioning activities.
  4. Post-Decommissioning Activity Monitoring Plan: When the decommissioning activities have been completed and the concessionaire has received general environmental information relating to Post-Decommissioning Activity Monitoring, the concessionaire must submit the Progress of Post-Decommissioning Activity Monitoring Report of environmental quality to the director-general of the DMF within the specified time limit. Moreover, the concessionaire also has to deliver the Post-Decommissioning Activity Monitoring Report for the DMF’s approval within the time limit specified in the above plan.

In conclusion, the government agencies not only stipulate the principles for decommissioning and security, but they also stipulate the responsibilities for the concessionaire in respect to providing the research and environmental impact assessment reports, which cover the pre-decommissioning assessment of environmental impact and the management plan during the decommissioning, as well as follow-up, auditing, and post-decommissioning assessment. These helpful measures protecting against environmental impacts help to ensure that decommissioning activities are carried out in a manner that promotes efficient and sustainable environmental protection in the future.

 

This article first appeared in the July 2019 edition of PTIT Focus, the Petroleum Institute of Thailand’s monthly newsletter. The article was published in both English and Thai. 

RELATED INSIGHTS​ 

February 2, 2021
The application period for very small power producers (VSPPs) aiming to participate in the community power plant project is fast drawing to a close, with the deadline set for February 4, 2021. February 4 is also the closing date of the period for public comments on the two draft regulations outlining the pilot project to procure electricity from community power plants. These draft regulations are being finalized by the Energy Regulation Commission (ERC)  as part of an effort to boost the economy at a grassroots level. The community power plant project will procure 150 MW from VSPPs producing electricity from either biomass or biogas. 75 MW will be obtained from biomass VSPPs, with a limit of 6 MW to each biomass VSPP, while 75 MW of the electricity procurement will be obtained from biogas VSPPs with a limit of 3 MW each. VSPPs wishing to apply for the community power plant project must be 90%-owned by a private company, while 10% of ownership must be under a community enterprise or community enterprise network—consisting of at least 200 households—registered with the Department of Agricultural Extension. Furthermore, the fuel used by the VSPP must be either biogas or biomass obtained from the community enterprise or community enterprise network, and must not include fossil fuels. Once VSPPs have submitted their applications, they will be subject to a technical assessment to determine power production readiness, and will undergo a process of competitive bidding. VSPPs will be compared and selected based on a number of factors, including power production capacity, ability to operate for duration of the 20-year project, and the proposed fixed feed-in tariff (FiT). VSPPs that are chosen to participate in this pilot project will be subject to the following FiTs per unit of electricity, based on the type of fuel and
October 15, 2020
Practical Law has published the 2020 online version of Electricity Regulation in Thailand: Overview, a Q&A-style guide that provides detailed overviews of power issues and regulations for operators in the Thai electricity market. The Thailand overview is one of 22 such guides to jurisdictions worldwide, covering key practical issues related to the legal environment for agricultural operations.
October 13, 2020
On September 9, 2020, Vietnam’s Ministry of Industry and Trade (MOIT) issued Circular No. 21/2020/TT-BCT on the order and procedures for issuance of electricity operating licenses (Circular 21). Circular 21 will take effect on October 26, 2020, replacing Circular No. 36/2018/TT-BCT as amended by Circular No. 15/2019/TT-BCT (together, Circular 36).
October 1, 2020
Partner Vinh Quoc Nguyen and senior associate Tu Ngoc Trinh have contributed a chapter on electricity regulations in Vietnam, with a focus on the emerging renewable energy field, for the 2020 edition of the Practical Law Energy and Natural Resources Global Guide . The guide provides a comparative high-level overview, in a concise Q&A format, of energy laws and regulations in multiple jurisdictions around the world, and is split into three sections featuring regulations on (i) electricity, (ii) oil and gas, and (iii) mining. The Vietnam electricity chapter covers a range of topics, including the following: Recent trends in Vietnam’s electricity market and regulatory structure Companies involved in electricity generation, transmission, distribution and supply Import and export of electricity Electricity generation and renewable energy sources, including government policies and incentives Electricity transmission, distribution, and supply Proposals for reform, including privatization Practical Law Company is owned by Thomson Reuters and provides global guides covering legal know-how for corporate lawyers, including Global Guides to electricity regulation. Tilleke & Gibbins also contributes the Thailand chapter of this guide, as well as guides to numerous other practice areas. The full chapter can be viewed on the Practical Law website or downloaded using the button below.