August 19, 2020

PTIT Focus: Extension of the Schedule of Operation Date to Distribute Power to the Commercial Network Due to Force Majeure

Petroleum Institute of Thailand: PTIT Focus

On 28 November 2018, the Energy Regulatory Commission (ERC) passed a resolution to extend the Schedule of Operation Date (SCOD) due to force majeure. Subsequently, the ERC issued the Notification Regarding Methods of Considering the Extension of SCOD to Distribute Power to a Commercial Network Due to Force Majeure. However, the notification did not stipulate specific types or sizes of power plants under energy purchase agreements.

Under the notification, a force majeure  event that can be a justification for the extension of SCOD must be a force majeure  event as defined under the Civil and Commercial Code, and as set out under the regulations regarding power purchases and power purchase agreements. Accordingly, a force majeure  event is one in which the occurrence, or consequences, could not be prevented even though the victim (or near-victim) took appropriate care as might be expected from him or her in that situation and in such condition.

Force majeure  also refers to government actions. These could include changes in energy policies or in the law that result in the project owner, the project sponsor, or the Electricity Sales Department being unable to comply with any provision of the regulations regarding power purchase agreements, as well as seizure of the project, assets or any rights, shares, or benefits from the contracted energy producer by a government entity. Also covered are blockades or other acts of war; uprisings, rebellions, disturbances, and strikes; as well as accidents such as earthquakes, storms, fires, floods, and unusually bad weather conditions. Also considered force majeure  would be accidental disruptions to the power distribution system caused by accident. All of these scenarios could severely impact the project or the performance of the energy producer’s duties under the power purchase agreement.

Furthermore, when determining force majeure, both the nature of the facts and the circumstances must both be considered, and the following factors must be met: (1) The party claiming force majeure  must not have been the cause (or have contributed to) the facts or circumstances resulting in that party’s inability to comply with regulations regarding energy purchase agreements. (2) The party claiming force majeure  must have taken appropriate care as might be expected from them in that situation and in those conditions, despite the facts or circumstances of the events that occurred being unforeseeable or unpreventable, or beyond the party’s control. (3) The party claiming force majeure  must have made attempts to satisfy the energy purchase agreement. (4) The party claiming force majeure  must have made efforts to mitigate the possible impacts as appropriate for a person in that situation and in those conditions.

When determining the extension of a SCOD for distributing power to a commercial network due to force majeure, the factors must include the project’s preparedness under four areas: the preparedness of the property, the preparedness of the technology, the preparedness of the source of investment funds, and the preparedness of obtaining approvals under the relevant laws and regulations. The determination of the extension of the SCOD must also be such that the extension is only as is necessary and suitable, and must take into account the significance and impact of the force majeure  event. Officials must also periodically report to the Energy Policy Executive Committee and the National Energy Policy Council.

In conclusion, force majeure  is a general legal basis wherein a contracting party is unable to perform their duties under the agreement due to a force majeure  event, whereby that party is not held to be at fault for the inability to perform their duties. Nevertheless, the extent to which force majeure  can be used in determining the extension of the SCOD must be considered in accordance with the factors stipulated in the notification referenced above, including the combined nature of the facts and circumstances, as well as the preparedness of the project with regard to the four areas described above. This notification serves as a guideline to be used at the discretion of the government authorities in extending the SCOD in a manner that displays good governance, and following it will result in the highest fairness for commercial operators and other persons affected by the extension of the SCOD.

 

This article first appeared in the August 2019 edition of PTIT Focus, the Petroleum Institute of Thailand’s monthly newsletter. The article was published in both English and Thai. 

RELATED INSIGHTS​ 

January 25, 2023
Thailand’s Energy Regulatory Commission (ERC) has issued four new regulations under the Energy Business Act B.E. 2550 (2007) setting forth competition regimes to control both anticompetitive conduct and market structure in the energy business sector. The regulations were published in the Government Gazette on December 19, 2022, and took effect the following day. The key provisions of these ERC competition regulations largely mirror those articulated in the Trade Competition Act B.E. 2560 (2017) and its subordinate legislation. The most significant features of these competition regulations are summarized below. Market Definition Regulation The ERC’s market definition regulation (officially the ERC Regulation re: Market Definition and Relevant Market of Related Energy Services B.E. 2565) outlines the general framework for defining relevant markets in the energy sector. The factors to be taken into consideration include types of energy licenses, geographical areas, competition conditions, and interchangeability of energy services. In the annex to this regulation, the ERC has classified the relevant energy service markets as follows: Power business activities include power generation, power transmission system services, power distribution system services, power distribution services, and power system control services. Natural gas business activities include natural gas transmission through pipelines via natural gas transmission systems, natural gas procurement and wholesale via natural gas distribution systems, natural gas retail via natural gas distribution systems, and storage and regasification of liquefied natural gas. The ERC will review its market definitions and relevant energy service markets from time to time, taking into account changes in technology and competition conditions as well as feedback from public hearings. Market Dominance Regulation Under the ERC’s market dominance regulation (officially the ERC Regulation re: Criteria on Business Operator having a Market Dominance B.E. 2565), the ERC is empowered to proactively determine and declare which license-holding energy business operators have a dominant position
August 31, 2022
Thailand’s Draft Climate Change Act Countries around the world have given significant attention to climate change legislation, with many national, regional, and global attempts to slow the momentum of climate change. The most notable of these multilateral efforts is the Paris Agreement, a legally binding international treaty on climate change currently adopted by 193 parties. Its goal is to limit the global average temperature to well below 2°C (preferably below 1.5°C) above preindustrial levels, and the treaty’s coordinated efforts to combat climate change are much more ambitious than previous global agreements and discussions. Article 4 of the Paris Agreement requires countries to provide “nationally determined contributions” (NDCs), consisting of their action plans for climate action. Thailand, as a party to the Paris Agreement, has put forth an NDC that pledges to achieve an unconditional greenhouse gas (GHG) emission reduction target of 20% from the business-as-usual projection for 2030, with the possibility of increasing that target to 25% subject to adequate and enhanced access to technology development and transfer, financial resources, and other support. To enable the accomplishment of this pledge, Thailand is looking to enact climate change legislation that functions as a key mechanism for domestic climate action. In 2018, the Office of Natural Resources and Environmental Policy and Planning (ONEP) under the Ministry of Natural Resources and Environment was assigned to prepare a draft Climate Change Act. The draft is now complete, and according to news reports it is set to be submitted to the cabinet for further consideration. The draft Climate Change Act lays out Thailand’s action plan for climate change mitigation and adaptation, including emissions reductions. Some of the key sections in the draft law involve citizen rights, the National Climate Change Policy Committee, and a national GHG database. Rights of Citizens The draft establishes the
August 26, 2022
Thailand’s Board of Investment (BOI) has extended its previously announced period for reduction of import duty on imported raw and essential materials for battery manufacturing for electric vehicles and other applications. The BOI’s announcement No. 5/2565 dated August 8, 2022, extended the reduction period to a maximum of five years. The BOI’s promoted activities list includes two battery-manufacturing business activities: Activity 4.8.3.1 – Battery manufacturing Activity 5.2.6.1 – High energy density battery manufacturing Qualifying battery manufacturers who have cell or module manufacturing processes are eligible for 90% import duty reductions on raw and essential materials that cannot be produced in Thailand. These reductions will be available on an annual basis, and are renewable for five years in total—up from the original two years. Existing projects (i.e., those which have the original two-year duration in their BOI certificate) can also benefit from the extension by preparing a project amendment form, along with a clarification letter and supporting documents, for submission to the BOI office. For more details on these customs duty reductions, or on any aspect of investment promotion in Thailand, please contact Charuwan Charoonchitsathian at [email protected] or +66 2056 5657, or Napassorn Lertussavavivat at [email protected] or +66 2056 5662.
August 16, 2022
On July 21, 2022, Vietnam’s Ministry of Industry and Trade (MOIT) submitted Report No. 126/BC-BCT to the Prime Minister regarding the mechanism for transitional wind and solar power projects. In this report, the MOIT proposed some recommendations to explicitly address difficulties for outstanding wind and solar power projects (“Transitional Projects”) which have been developed under the Prime Minister’s Decision No. 13/2020/QD-TTg dated April 6, 2020, on the development of solar power projects (Decision 13) and Decision No. 37/2011/QD-TTg dated June 29, 2011, on the development of wind power projects (Decision 37), as amended by Decision No. 39/2018/QD-TTg dated September 10, 2018 (Decision 39). The Transitional Projects primarily include those which have completed construction but have not yet been put into operation, and those which have been put into operation but for which the power price has not yet been decided, due to missing the deadline set forth under the aforementioned decisions to be eligible for the feed-in-tariff (FIT). In particular, the MOIT has proposed the following key recommendations to the Prime Minister: Mechanism for Transitional Projects The MOIT proposes two options: Option 1: Developers of the Transitional Projects negotiate and sign power purchase agreements (PPA) with Vietnam Electricity (EVN) within the price framework issued by the MOIT in accordance with the Law on Electricity, the Law on Prices, and their subordinate guiding legislation; or Option 2: The Prime Minister formulates a new decision specifying the mechanism for bidding on the purchase of power produced by the Transitional Projects, estimated to be implemented for the time limit of three years and within the price framework issued by the MOIT. Mechanism for future wind and solar power projects The MOIT proposes to apply the mechanism that developers of future wind and solar projects negotiate the power price and sign the PPA