August 19, 2020

PTIT Focus: Extension of the Schedule of Operation Date to Distribute Power to the Commercial Network Due to Force Majeure

Petroleum Institute of Thailand: PTIT Focus

On 28 November 2018, the Energy Regulatory Commission (ERC) passed a resolution to extend the Schedule of Operation Date (SCOD) due to force majeure. Subsequently, the ERC issued the Notification Regarding Methods of Considering the Extension of SCOD to Distribute Power to a Commercial Network Due to Force Majeure. However, the notification did not stipulate specific types or sizes of power plants under energy purchase agreements.

Under the notification, a force majeure  event that can be a justification for the extension of SCOD must be a force majeure  event as defined under the Civil and Commercial Code, and as set out under the regulations regarding power purchases and power purchase agreements. Accordingly, a force majeure  event is one in which the occurrence, or consequences, could not be prevented even though the victim (or near-victim) took appropriate care as might be expected from him or her in that situation and in such condition.

Force majeure  also refers to government actions. These could include changes in energy policies or in the law that result in the project owner, the project sponsor, or the Electricity Sales Department being unable to comply with any provision of the regulations regarding power purchase agreements, as well as seizure of the project, assets or any rights, shares, or benefits from the contracted energy producer by a government entity. Also covered are blockades or other acts of war; uprisings, rebellions, disturbances, and strikes; as well as accidents such as earthquakes, storms, fires, floods, and unusually bad weather conditions. Also considered force majeure  would be accidental disruptions to the power distribution system caused by accident. All of these scenarios could severely impact the project or the performance of the energy producer’s duties under the power purchase agreement.

Furthermore, when determining force majeure, both the nature of the facts and the circumstances must both be considered, and the following factors must be met: (1) The party claiming force majeure  must not have been the cause (or have contributed to) the facts or circumstances resulting in that party’s inability to comply with regulations regarding energy purchase agreements. (2) The party claiming force majeure  must have taken appropriate care as might be expected from them in that situation and in those conditions, despite the facts or circumstances of the events that occurred being unforeseeable or unpreventable, or beyond the party’s control. (3) The party claiming force majeure  must have made attempts to satisfy the energy purchase agreement. (4) The party claiming force majeure  must have made efforts to mitigate the possible impacts as appropriate for a person in that situation and in those conditions.

When determining the extension of a SCOD for distributing power to a commercial network due to force majeure, the factors must include the project’s preparedness under four areas: the preparedness of the property, the preparedness of the technology, the preparedness of the source of investment funds, and the preparedness of obtaining approvals under the relevant laws and regulations. The determination of the extension of the SCOD must also be such that the extension is only as is necessary and suitable, and must take into account the significance and impact of the force majeure  event. Officials must also periodically report to the Energy Policy Executive Committee and the National Energy Policy Council.

In conclusion, force majeure  is a general legal basis wherein a contracting party is unable to perform their duties under the agreement due to a force majeure  event, whereby that party is not held to be at fault for the inability to perform their duties. Nevertheless, the extent to which force majeure  can be used in determining the extension of the SCOD must be considered in accordance with the factors stipulated in the notification referenced above, including the combined nature of the facts and circumstances, as well as the preparedness of the project with regard to the four areas described above. This notification serves as a guideline to be used at the discretion of the government authorities in extending the SCOD in a manner that displays good governance, and following it will result in the highest fairness for commercial operators and other persons affected by the extension of the SCOD.

 

This article first appeared in the August 2019 edition of PTIT Focus, the Petroleum Institute of Thailand’s monthly newsletter. The article was published in both English and Thai. 

RELATED INSIGHTS​ 

January 28, 2020
Tilleke & Gibbins authors have provided the latest update to the Thailand Q&A section of Doing Business in… , a Q&A-style guide published by Thomson Reuters Practical Law that presents an overview of recent legal developments affecting doing business in 59 jurisdictions worldwide. The Thailand chapter of the guide was written by attorneys from Tilleke & Gibbins and presents an overview of Thailand’s legal system and key laws applicable to foreign companies doing business in the country.
December 4, 2019
Introduction    A series of perhaps unrelated drivers have resulted in a renewed emphasis on decommissioning obligations within the energy industry, from government mandates for renewable energy to the end-of-life of many oil and gas concessions and product sharing contracts around Asia and throughout the world. These circumstances have spurred governments and oil and gas interest holders to begin the robust debate on decommissioning obligations and related processes and security arrangements.    
October 10, 2019
Most of the operators in the petroleum or oil and gas industries are large international companies that correspond and coordinate with their parent companies or contractors, subcontractors, suppliers or vendors who are based around the globe. In addition, such petroleum or oil and gas operators may employ a significant number of employees, and therefore, they may need to collect, use or disclose personal data relating to their contracting parties, or their employees, in their business operations.
October 9, 2019
With reference to the concession agreement form, as issued under the Ministerial Regulations of the Ministry of Energy regarding the Form for the Designation of a Concession Agreement B.E. 2555 (2012) (“Ministerial Regulations re: the Concession Agreement Form”), the form includes a provision that is related to dispute resolution by arbitration, as set out in Clause 13 of the Concession Agreement.