Potential Impact of Vietnam’s New Land Law on the Energy Sector

On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly.

One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector.

Annual payment of land rental

Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment.

As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning.

Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged.

Obtaining land

Under the Land Law 2024, investors can obtain land through a lease without any auction or bidding process; through an auction process (for selecting the land user of a land site); or through a bidding process (for selecting the investor implementing an investment project with the need to use land).

Investors in energy projects using public investment capital and public-private partnership (PPP) projects can lease a land site from the state without an auction or bidding process. Further details on these conditions are to be provided by the government.

An auction process will apply to energy projects that intend to use land obtained from the land fund managed by the state if the following conditions are satisfied: (i) the land site is clean and does not require compensation or site-clearance work; (ii) the land site is included in the annual land-use plans approved for auction; and (iii) a 1/500 plan and auction plan are approved by the competent authorities.

A bidding process will apply to energy projects that must conduct bidding to select investors according to specialized laws, such as the laws on electricity, if the following conditions are satisfied: (i) the land is on the list of land sites subject to bidding for selection of investors for an investment project as decided by the provincial People’s Council; (ii) a detailed plan or a 1/2000 zoning plan is approved by the competent authorities; and (iii) other conditions under the laws on bidding are met.

Compared to the Land Law 2013, the Land Law 2024 supplements the bidding for projects using land as a new method for investors to gain access to land. This addition aims to increase competition and fairness for investors.

Compensation, support, and resettlement procedure

If the land for implementing an energy project is currently occupied, a compensation, support and resettlement procedure must be carried out. Under the current Land Law 2013, the decision on land recovery and the decision on the plan for compensation, support and resettlement are issued concurrently. Under the new Land Law 2024, the decision on land recovery will only be issued within 10 days after, among other conditions, the plan on compensation, support, and resettlement has been issued, if resettlement is not required; or the person whose land is recovered has had another land site allocated or handed over by a competent authority to build their own resettlement housing.

These new regulations will extend the length of the land clearance procedure considerably when the recovered land requires resettlement, as the decision on land recovery will only be issued after the resettlement is deemed completed.

Commercial arbitration as a dispute resolution mechanism

Another crucial aspect of the new law is that commercial arbitration is clearly recognized as a dispute resolution mechanism for land-related disputes. Previously, there was uncertainty surrounding whether disputes relating to land could be adjudicated by arbitration. Pursuant to the Land Law 2024, Vietnamese commercial arbitration can resolve disputes arising from commercial activities related to land in accordance with the law on commercial arbitration.

Outlook

The new Land Law aims to address overlapping and conflicting issues of related land policies and laws, while tackling practical challenges in land management and land use. It promotes the commercialization of land-use rights, fostering transparent real estate markets, modernizing land management systems, and implementing administrative and digital reforms to improve land accessibility, especially for energy projects.

RELATED INSIGHTS​ 

December 15, 2023
As part of its membership in Lex Mundi, Tilleke & Gibbins has published an updated edition of its Guide to Doing Business in Thailand for 2023. This guide outlines the key factors for starting and operating a business in the Thai market. Issues covered include: Investment incentives Financial facilities Exchange controls Import and export regulations Structures for doing business Requirements for the Establishment of a Business Operation of the Business Cessation or Termination of the Business Labor legislation, relations, and supply Tax Immigration requirements This publication is part of Lex Mundi’s Country Guides series prepared by member firms in more than 100 jurisdictions worldwide. The guides serve as a useful resource for planning international business strategy and researching new markets. The full Guide to Doing Business in Thailand is available through the button below.
July 25, 2023
Thailand’s Energy Regulatory Commission (ERC) is in the process of reviewing a draft regulation that updates the nationality qualifications for the ultimate shareholders and directors of applicants for an energy business license. The draft ERC Regulation Re: Qualifications, Documents and Application for Electricity Business—which is intended to replace the ERC Regulation Re: Application and Permission for Electricity Business B.E. 2551 and its amendments—is likely to be adopted soon and will affect licensed companies that are foreign majority owned when they apply for or renew their energy business licenses. The draft regulation requires partnerships, limited companies, and public limited companies to have the following qualifications unless there is an international agreement granting national treatment for a specific commitment (mode 3 or mode 4) or exemption by other laws: Juristic persons must be established under Thai law or registered in Thailand with the objective of carrying out electricity business; For private limited companies, foreign ultimate shareholders must not hold more than 49% of the total shares, and the number of the foreign shareholders must not exceed half of all shareholders; At least half of all directors must have Thai nationality; and Any authorized directors must have Thai nationality. When the draft regulation is adopted, it will not take retroactive effect on previously granted energy business licenses, which will continue to be valid until they expire if there is no material change to the license as defined by the draft regulation. Once the license is up for renewal (energy business licenses are normally issued for a specific period of time), it will be subject to the draft regulation. All license applications submitted prior to the effective date of the draft regulation and under consideration will be deemed applications for a license under the draft regulation. As noted above, the new qualification requirements
July 7, 2023
Cambodia has the potential to be one of the top countries in the world for generating renewable energy through solar, based on the average amount of sunlight hours available per day and the consistent sunshine throughout the year. The Cambodian government has recognized this potential and has made major updates to its energy policies in recent years. Solar power is now taking over a much larger portion of the total energy mix in Cambodia, especially as a number of utility-scale solar power plants have come online in recent years. The long-term Power Development Master Plan 2022–2040 sets out the long-term energy policy for Cambodia and requires a bigger role for renewables. The use of solar power will play a key role in this aim to increase the role of renewables, with the plan foreseeing almost 30% of all national power generated through solar technologies by 2040. Two of the latest legislative and regulatory steps by the government are the Ministry of Mines and Energy’s guidelines for rooftop solar systems, and most recently the long-awaited Environment and Natural Resources Code, which was enacted on June 29, 2023. Rooftop Solar Projects Many companies, from small startups to multinationals, are exploring the potential for rooftop solar in Cambodia. However, despite the favorable natural factors, the regulatory framework was not always clear or friendly to rooftop solar, hampering investment. This started slowly changing with the adoption of the first solar energy regulation in 2018, which provided the country’s first official guidance on both solar power plants and rooftop solar. It provided some much-needed clarity, but the 2018 solar energy regulation—and especially the subsequent electricity tariff schemes—often kept rooftop projects from being financially viable. Many players in the industry voiced their doubts about the regulations and tariffs, focusing especially on the capacity charge—a monthly
May 19, 2023
On May 15, 2023, Vietnam’s Deputy Prime Minister Tran Hong Ha signed Decision No. 500 of the Prime Minister approving the National Power Development Plan for the period 2021-2030, with a vision to 2050 (“PDP VIII”), following extensive public consultations and multiple rounds of review since the first draft version was circulated in 2021. The plan was approved in the context that in the past few years, a number of large power projects have been behind schedule for operation, while new projects have not been able to be implemented due to waiting for additional planning. PDP VIII is the master plan for the development of the power source and transmission grid at 220kV or higher; services in renewable energy and new energy in Vietnam; and works connecting the power grids of Vietnam and neighboring countries. We set out below some quick updates regarding PDP VIII. 1. Development Targets Key development targets are summarized in the table below: Investors in coal, domestic gas, and LNG projects may need to have a conversion plan ready given the 2050 targets to convert to other sources of energy. 2. Solar Projects A list of 27 solar power projects that were planned for the period of 2021-2030 but which have not been assigned to investors are not allowed to be deployed but can be considered after 2030, except in the case of deployment in the form of self-production and self-consumption (Appendix IV). These projects represent 4,136.25 MW of capacity that will be left on the sidelines until 2030. 3. Hydropower Projects A list of 14 potential hydropower projects can be considered if economic and technical conditions allow for more hydropower development (Appendix III). These projects represent 1,244 MW of capacity that can be added to the hydropower targets for 2030. 4. Projects Prioritized for