Potential Impact of Vietnam’s New Land Law on the Energy Sector

On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly.

One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector.

Annual payment of land rental

Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment.

As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning.

Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged.

Obtaining land

Under the Land Law 2024, investors can obtain land through a lease without any auction or bidding process; through an auction process (for selecting the land user of a land site); or through a bidding process (for selecting the investor implementing an investment project with the need to use land).

Investors in energy projects using public investment capital and public-private partnership (PPP) projects can lease a land site from the state without an auction or bidding process. Further details on these conditions are to be provided by the government.

An auction process will apply to energy projects that intend to use land obtained from the land fund managed by the state if the following conditions are satisfied: (i) the land site is clean and does not require compensation or site-clearance work; (ii) the land site is included in the annual land-use plans approved for auction; and (iii) a 1/500 plan and auction plan are approved by the competent authorities.

A bidding process will apply to energy projects that must conduct bidding to select investors according to specialized laws, such as the laws on electricity, if the following conditions are satisfied: (i) the land is on the list of land sites subject to bidding for selection of investors for an investment project as decided by the provincial People’s Council; (ii) a detailed plan or a 1/2000 zoning plan is approved by the competent authorities; and (iii) other conditions under the laws on bidding are met.

Compared to the Land Law 2013, the Land Law 2024 supplements the bidding for projects using land as a new method for investors to gain access to land. This addition aims to increase competition and fairness for investors.

Compensation, support, and resettlement procedure

If the land for implementing an energy project is currently occupied, a compensation, support and resettlement procedure must be carried out. Under the current Land Law 2013, the decision on land recovery and the decision on the plan for compensation, support and resettlement are issued concurrently. Under the new Land Law 2024, the decision on land recovery will only be issued within 10 days after, among other conditions, the plan on compensation, support, and resettlement has been issued, if resettlement is not required; or the person whose land is recovered has had another land site allocated or handed over by a competent authority to build their own resettlement housing.

These new regulations will extend the length of the land clearance procedure considerably when the recovered land requires resettlement, as the decision on land recovery will only be issued after the resettlement is deemed completed.

Commercial arbitration as a dispute resolution mechanism

Another crucial aspect of the new law is that commercial arbitration is clearly recognized as a dispute resolution mechanism for land-related disputes. Previously, there was uncertainty surrounding whether disputes relating to land could be adjudicated by arbitration. Pursuant to the Land Law 2024, Vietnamese commercial arbitration can resolve disputes arising from commercial activities related to land in accordance with the law on commercial arbitration.

Outlook

The new Land Law aims to address overlapping and conflicting issues of related land policies and laws, while tackling practical challenges in land management and land use. It promotes the commercialization of land-use rights, fostering transparent real estate markets, modernizing land management systems, and implementing administrative and digital reforms to improve land accessibility, especially for energy projects.

RELATED INSIGHTS​ 

June 25, 2025
In April 2025, a massive power outage plunged Portugal, Spain, and parts of southwestern France into darkness for up to ten hours. As Thailand advances its energy transition by increasing renewable integration and regional interconnections, the European blackout serves as a stark reminder of the grid vulnerabilities that still exist. In this first article of a three-part series, energy specialists from Tilleke & Gibbins examine the root causes of the outage in the Iberian Peninsula.
May 28, 2025
Tilleke & Gibbins attorneys in Vietnam have contributed the 2025 edition of Doing Business in Vietnam, a comprehensive Q&A-style resource from Thomson Reuters Practical Law that provides essential insights for companies navigating business operations in Vietnam. The guide presents a detailed overview of the country’s legal framework and regulatory environment, reflecting recent updates in Vietnamese legislation and practice. This annually updated guide offers key information on the following areas: Legal system: Structure of the Vietnamese judiciary and the role of codified law. Foreign investment: Conditions for market access, licensing requirements, foreign ownership restrictions, and investment incentives. Business vehicles: Formation and operation of legal entities, including limited liability companies, joint-stock companies, and representative offices. Employment: Employment contracts, social insurance, labor rights, and procedures for hiring foreign nationals. Tax: Overview of corporate income tax, personal income tax, value-added tax, and other tax obligations. Intellectual property: Procedures for protecting and enforcing patents, trademarks, copyrights, and other IP rights. Data protection: Compliance requirements under Vietnam’s data privacy laws, including the Personal Data Protection Decree. Competition law: Antitrust rules and regulatory oversight under the Law on Competition. Anti-bribery and corruption: Legal framework and enforcement practices aimed at curbing corrupt activities. E-commerce and digital business: Regulations governing online platforms, digital content, and cross-border services. Marketing and advertising: Laws and guidelines on advertising standards and consumer protection. Product regulation and liability: Safety requirements, product liability issues, and roles of relevant authorities. Doing Business in Vietnam is part of Practical Law’s global series of legal guides designed to support international practitioners and businesses. To access the most recent edition of the Vietnam guide, visit the Practical Law website and sign up for a free trial.
May 2, 2025
Attorneys from Tilleke & Gibbins have updated the latest edition of Doing Business in Thailand, a Q&A-style guide from Thomson Reuters Practical Law that offers an overview of key legal considerations for companies operating in jurisdictions worldwide. The contribution outlines the country’s legal and regulatory framework for foreign investment and business operations and reflects the latest legislative developments. The chapter addresses the following core topics: Legal system: Structure of the courts and the codified nature of Thai law. Foreign investment: Business restrictions under the Foreign Business Act, sector-specific regulations, exchange control rules, and investment incentives. Business vehicles: Overview of partnerships, private and public limited companies, and other legal entities. Employment: Labor protections, employment contracts, foreign worker requirements, and termination procedures. Tax: Corporate and personal income tax, indirect taxes, and tax obligations for residents and non-residents. Intellectual property: Registration and enforcement of patents, trademarks, designs, and copyrights. Data protection: Key provisions of the Personal Data Protection Act and related compliance obligations. Competition law: Regulatory framework under the Trade Competition Act. Anti-bribery and corruption: Relevant legislation and enforcement mechanisms. E-commerce and digital business: Legal regime for online transactions and digital platforms. Marketing and advertising: Consumer protection laws and regulations affecting advertising and marketing practices. Product regulation and liability: Safety standards, liability regimes, and roles of enforcement authorities. Practical Law, a legal reference resource from Thomson Reuters, publishes a range of guides for hundreds of jurisdictions and practice areas. The insurance and reinsurance guide is a valuable resource for legal practitioners, covering numerous jurisdictions worldwide. To view the latest version of the guide, please visit the Practical Law website and enroll in the free Practical Law trial to gain full access.
April 10, 2025
On March 3, 2025, the government of Vietnam issued Decree No. 57/2025/ND-CP, regulating the direct power purchase agreement (DPPA) mechanism between renewable energy generators and large electricity consumers (“Decree 57”). Decree 57 took immediate effect and replaces Decree No. 80/2024/ND-CP on the same subject. The new regulations enable investors to kickstart their investment plans for DPPAs in Vietnam. Below are the key changes and provisions of Decree 57. Participants in On-Grid DPPAs Decree 57 expands the eligibility criteria for participating in DPPAs via the national grid (on-grid DPPAs): Sellers: In addition to wind and solar power generators, biomass energy generators with a capacity of 10 MW or more can now participate. Buyers: Electric vehicle charging businesses are now eligible to participate, broadening the scope beyond just production businesses. Large Electricity Consumers Instead of setting definite criteria at the government decree level, Decree 57 defines large electricity consumers based on average electricity consumption as set out in wholesale electricity market regulations to be issued by the Ministry of Industry and Trade (MOIT). Although the threshold for DPPA participation remains for now at 200,000 kWh per month, Decree 57 will allow the MOIT to adjust this threshold as deemed necessary. Decree 57 also provides specific guidance for large electricity consumers based on their consumption period. To participate in both private off-grid DPPA (selling electricity directly via a grid system separate from the national grid) and on-grid DPPA models, large electricity consumers must meet the minimum threshold for electricity consumption set by the MOIT under the Vietnam wholesale electricity market regulations (“Minimum Consumption Threshold”). Consumers with a consumption history of at least 12 months must have already met the Minimum Consumption Threshold at the time of registration or notification, while those whose consumption period is less than 12 months must commit to