January 23, 2025

Potential Challenges and Solutions for Vietnam’s Renewable Energy Projects

In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges.

In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports.

The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models.

Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include:

  1. Allowing additional planning where projects do not violate national security.
  2. Allowing rectification of projects’ violations in land and construction process as per law.
  3. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration.
  4. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions.
  5. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered.
  6. For items (iv) and (v), the authority will issue regulations on electricity prices after FIT revocation for offsetting the electricity payment purpose.

According to the reports, for projects with a COD date before the date of the notice on results of inspection of checking for acceptance of the construction works (CCA) issued by the relevant authority, Vietnam Electricity (EVN) will assess FIT eligibility in collaboration with developers. Based on EVN’s findings, regulations will be issued to govern electricity selling prices for ineligible projects, ensuring compliance and fair practices.

Investors should review the status of their projects to determine if they are impacted. It is essential to stay updated on the official decisions of the MOIT and the government on the detected violations.

RELATED INSIGHTS​ 

January 24, 2017
The 2017 edition of Doing Business In…, a Q&A-style guide published by Practical Law Company in collaboration with Lex Mundi, presents an overview of recent legal developments affecting doing business in 51 jurisdictions worldwide. The Thailand chapter of the guide was written by attorneys from Tilleke & Gibbins and presents an overview of Thailand’s legal system and key laws applicable to foreign companies doing business in the Kingdom. The chapter specifically covers the following main topics:
December 9, 2016
The government of Thailand has made it clear that it intends to fully utilize public-private partnerships (PPPs) in order to implement the country’s upcoming infrastructure development goals. The adoption of the Private Investment in State Undertakings Act B.E. 2556 (2013) (PISUA) and the announcement of the Strategic Plan on Private Investment in State Undertakings in 2015 demonstrate the specific policy objectives the government intends to achieve through using PPPs.
November 28, 2016
The development of a renewable energy project requires, among a range of factors, engineers to design the facility, state-of-the-art equipment, and a reliable construction firm to implement the project. A key factor in a renewable energy project’s long-term success is devising an appropriate contractual framework to construct the facilities. This is a particularly important consideration, given the scale of many renewable energy projects and the financial sums at stake.  
August 26, 2016
Thailand’s Ministry of Energy promulgated the Ministerial Regulation Prescribing Plan and Estimated Cost and Security for Decommissioning of Installations Used in the Petroleum Industry B.E. 2559 (2016) earlier this year. As the specific rules and procedures governing the end of the life cycle for upstream petroleum projects had been somewhat uncertain, the decommissioning regulation adds a great deal of clarity on legal obligations for concessionaires.