New PPP Law Encourages Private Investment in the Railway Sector

Informed Counsel

Two years ago, the Private Investment in State Undertaking Act B.E. 2556 (2013) (PISUA) replaced the Private Participation in State Undertaking Act B.E. 2535 (1992) (PPSUA), which set out the criteria for a private party to jointly operate a government project. There were calls to replace the PPSUA because the law had a convoluted project approval process that discouraged private investment. During its 21-year lifespan, only 40 projects were completed under the PPSUA.

The PISUA aims to streamline and simplify the project approval process to attract more private investors. An increase in private sector investment would lessen the need for government loans and reduce the impact of financial restrictions caused by limited government budgets. In turn, this would improve the efficiency of developing infrastructure and providing public services to citizens.

Thailand’s railway sector would benefit tremendously from an increase in private sector investment. According to the Global Competitiveness Report 2015-2016, Thailand’s quality of railroad infrastructure ranks 78th out of 140 countries, indicating that there is scope for improvement. In light of this potential for improvement, this article will discuss the impact of the PISUA on Thailand’s railway sector.

Strategic Plan

The PISUA has proposed a draft Strategic Plan on Private Investment in State Undertakings (Strategic Plan), which sets out a five-year investment and policy plan that explicitly details the subsectors that are suitable for public–private partnerships.

The draft Strategic Plan was approved by the Thai Cabinet on May 26, 2015, and it was published in the Royal Gazette  on June 25, 2015. State agencies are therefore bound to prepare and approve projects that fall within the ambit of the Strategic Plan.

The Strategic Plan distinguishes between subsectors that require  private sector investment, such as certain infrastructure sectors, and subsectors in which the government only encourages  private sector participation. The railway sector largely falls within the former category and thus explicitly requires private sector investment.

Project Pipeline

On May 26, the Cabinet also acknowledged the Strategic Plan’s Project Pipeline, which lists all of the public projects with private sector investment. In the urban rail transit area, the Project Pipeline includes eight projects with an overall investment volume of approximately THB 568 billion. Twenty-five percent of this amount, which equates to THB 142 billion, shall be covered by private investors. Two of these projects are already under construction; five projects are undergoing feasibility studies; and for one project, the search for a suitable private investor is ongoing.

A feasibility study must be conducted for projects that exceed THB 1 billion. It has to be prepared by an external consultant who is in the State Enterprise Policy Office’s list of qualified consultants. A feasibility study aims to identify project costs, risks, and impacts, as well as the legal issues and potential problems in implementing the project through examination of Thailand’s current legal and regulatory framework. For PPPs in the railway sector, this includes railway-related laws and regulations.

In addition, the Project Pipeline outlines two projects in the high-speed rail sector with a total investment amount of THB 234 billion. One of these projects, a Bangkok-Rayong high-speed rail, requires a total investment of THB 152 billion, but the amount of private sector investment has not been determined yet. The other project, a Bangkok-Hua Hin high-speed rail, requires THB 81 billion of investment, and 11 percent of this amount, which equates to THB 9 billion, will be covered by private investors. Both of these projects are currently undergoing feasibility studies.

In total, private sector investment in the railway sector amounts to THB 802 billion. Nineteen percent of this amount, which is THB 154 billion, will be covered by private investors, excluding the Bangkok-Rayong high-speed rail. For capital-intensive railway projects, the government budget is the main source of funding, as private sector investment in infrastructure projects is limited to THB 500 billion. 

Acquiring Land or Immovable Assets

In order to construct new railways or railway accessories, it may become necessary to acquire land or immovable assets. The State Railway of Thailand is allowed to acquire land or immovable assets under the Railway Authority of Thailand Act B.E. 2494 (1951) (with amendments), which refers to the Expropriation of Immovable Property Act B.E. 2530 (1987). Under this Act, the state may acquire immovable property for the purpose of any public utility or for other public purposes. An appointed committee will appraise the estimated price of the immovable property to be expropriated and the amount of compensation to be provided.

The Mass Rapid Transit Authority of Thailand Act B.E. 2543 (2000) and the Act on Arrangement of Immovable Property for Mass Transit Undertaking B.E. 2540 (1997) apply to mass rapid transit systems within the Greater Bangkok Area and other provinces as stipulated by Royal Decree. They set out an independent procedure regarding the acquisition of immovable property for infrastructure projects.

Environmental Impact

The potential environmental impact of a project must also be considered. Under the Enhancement and Conservation of National Environmental Quality Act B.E. 2535 (1992), an environmental impact assessment report must be prepared at the stage of conducting a feasibility study on a specific project. This report must be approved by the Office of Environmental Policy and Planning. In the case of a public–private partnership, the government agency or state enterprise has the duty to prepare an impact assessment report.

With more streamlined project approval procedures and clearer guidelines, the PISUA is poised become a powerful tool in strengthening Thailand’s infrastructure sectors. It sets out a stronger framework for private investment in public sectors, and the recently enacted Strategic Plan may drive increased private investment in the railway sector. The development of private investment in the railway sector, however, will remain to be seen over the next five years as the impact of the PISUA evolves in practice.

RELATED INSIGHTS​ 

June 25, 2025
In April 2025, a massive power outage plunged Portugal, Spain, and parts of southwestern France into darkness for up to ten hours. As Thailand advances its energy transition by increasing renewable integration and regional interconnections, the European blackout serves as a stark reminder of the grid vulnerabilities that still exist. In this first article of a three-part series, energy specialists from Tilleke & Gibbins examine the root causes of the outage in the Iberian Peninsula.
May 28, 2025
Tilleke & Gibbins attorneys in Vietnam have contributed the 2025 edition of Doing Business in Vietnam, a comprehensive Q&A-style resource from Thomson Reuters Practical Law that provides essential insights for companies navigating business operations in Vietnam. The guide presents a detailed overview of the country’s legal framework and regulatory environment, reflecting recent updates in Vietnamese legislation and practice. This annually updated guide offers key information on the following areas: Legal system: Structure of the Vietnamese judiciary and the role of codified law. Foreign investment: Conditions for market access, licensing requirements, foreign ownership restrictions, and investment incentives. Business vehicles: Formation and operation of legal entities, including limited liability companies, joint-stock companies, and representative offices. Employment: Employment contracts, social insurance, labor rights, and procedures for hiring foreign nationals. Tax: Overview of corporate income tax, personal income tax, value-added tax, and other tax obligations. Intellectual property: Procedures for protecting and enforcing patents, trademarks, copyrights, and other IP rights. Data protection: Compliance requirements under Vietnam’s data privacy laws, including the Personal Data Protection Decree. Competition law: Antitrust rules and regulatory oversight under the Law on Competition. Anti-bribery and corruption: Legal framework and enforcement practices aimed at curbing corrupt activities. E-commerce and digital business: Regulations governing online platforms, digital content, and cross-border services. Marketing and advertising: Laws and guidelines on advertising standards and consumer protection. Product regulation and liability: Safety requirements, product liability issues, and roles of relevant authorities. Doing Business in Vietnam is part of Practical Law’s global series of legal guides designed to support international practitioners and businesses. To access the most recent edition of the Vietnam guide, visit the Practical Law website and sign up for a free trial.
May 2, 2025
Attorneys from Tilleke & Gibbins have updated the latest edition of Doing Business in Thailand, a Q&A-style guide from Thomson Reuters Practical Law that offers an overview of key legal considerations for companies operating in jurisdictions worldwide. The contribution outlines the country’s legal and regulatory framework for foreign investment and business operations and reflects the latest legislative developments. The chapter addresses the following core topics: Legal system: Structure of the courts and the codified nature of Thai law. Foreign investment: Business restrictions under the Foreign Business Act, sector-specific regulations, exchange control rules, and investment incentives. Business vehicles: Overview of partnerships, private and public limited companies, and other legal entities. Employment: Labor protections, employment contracts, foreign worker requirements, and termination procedures. Tax: Corporate and personal income tax, indirect taxes, and tax obligations for residents and non-residents. Intellectual property: Registration and enforcement of patents, trademarks, designs, and copyrights. Data protection: Key provisions of the Personal Data Protection Act and related compliance obligations. Competition law: Regulatory framework under the Trade Competition Act. Anti-bribery and corruption: Relevant legislation and enforcement mechanisms. E-commerce and digital business: Legal regime for online transactions and digital platforms. Marketing and advertising: Consumer protection laws and regulations affecting advertising and marketing practices. Product regulation and liability: Safety standards, liability regimes, and roles of enforcement authorities. Practical Law, a legal reference resource from Thomson Reuters, publishes a range of guides for hundreds of jurisdictions and practice areas. The insurance and reinsurance guide is a valuable resource for legal practitioners, covering numerous jurisdictions worldwide. To view the latest version of the guide, please visit the Practical Law website and enroll in the free Practical Law trial to gain full access.
April 10, 2025
On March 3, 2025, the government of Vietnam issued Decree No. 57/2025/ND-CP, regulating the direct power purchase agreement (DPPA) mechanism between renewable energy generators and large electricity consumers (“Decree 57”). Decree 57 took immediate effect and replaces Decree No. 80/2024/ND-CP on the same subject. The new regulations enable investors to kickstart their investment plans for DPPAs in Vietnam. Below are the key changes and provisions of Decree 57. Participants in On-Grid DPPAs Decree 57 expands the eligibility criteria for participating in DPPAs via the national grid (on-grid DPPAs): Sellers: In addition to wind and solar power generators, biomass energy generators with a capacity of 10 MW or more can now participate. Buyers: Electric vehicle charging businesses are now eligible to participate, broadening the scope beyond just production businesses. Large Electricity Consumers Instead of setting definite criteria at the government decree level, Decree 57 defines large electricity consumers based on average electricity consumption as set out in wholesale electricity market regulations to be issued by the Ministry of Industry and Trade (MOIT). Although the threshold for DPPA participation remains for now at 200,000 kWh per month, Decree 57 will allow the MOIT to adjust this threshold as deemed necessary. Decree 57 also provides specific guidance for large electricity consumers based on their consumption period. To participate in both private off-grid DPPA (selling electricity directly via a grid system separate from the national grid) and on-grid DPPA models, large electricity consumers must meet the minimum threshold for electricity consumption set by the MOIT under the Vietnam wholesale electricity market regulations (“Minimum Consumption Threshold”). Consumers with a consumption history of at least 12 months must have already met the Minimum Consumption Threshold at the time of registration or notification, while those whose consumption period is less than 12 months must commit to