New Law Puts Public-Private Partnerships on Solid Ground

Bangkok Post, Corporate Counsellor Column

There was much fanfare last year about the enactment of the Private Investment in State Undertaking Act of 2013. Many commentators forecasted an era of renewed vigor for public-private partnerships (PPPs) in Thailand.

In reality, the Act made only incremental changes relative to the older Public Participation in State Undertaking Act of 1992, at least in terms of approval procedures. However, it did set out a much stronger framework for comprehensive planning and quality of public-private ventures. This was evident in sections calling for a PPP Policy Committee, a PPP Fund, and a PPP Strategic Plan, as well as regulations on the use of experts and consultants.

The PPP Policy Committee in particular has broad authority, from preparing the PPP Strategic Plan for cabinet approval to approving projects, proposing measures to support PPPs, considering approval of no-bid selection processes, and issuing a variety of regulatory notifications.

The PPP Strategic Plan will be the main driver of PPP policy, identifying sectors appropriate for PPPs, setting priorities, identifying areas where investment is urgent, and setting targets and time frames. A new plan is to be produced every five years, with evaluations in the interim.

To ensure the plan reflects public needs, the PPP Policy Committee must hold hearings to obtain input from state agencies and members of the public. Prior to each hearing, the State Enterprise Policy Office (Sepo), as the secretariat, will prepare a framework setting out the draft strategic plan, goals, target audience, and other details for the approval of the committee. This will help it to produce an effective PPP Strategic Plan for submission to the cabinet.

The PPP Fund, meanwhile, is envisaged to be used for developing the strategic plan, hiring consultants, and helping state agencies to develop PPPs consistent with the plan. The money will come from state budget appropriations as well as fees charged to bidders. A PPP Fund Committee, separate from the policy panel, set out rules for the fund’s operation and expenditure earlier this year.

The new law also sets out clearer guidelines for the use of experts and consultants. By law, a state agency pursuing a PPP must appoint a selection committee to address tendering and a supervisory committee to handle oversight. Each is required to include some experts with knowledge, expertise, and experience that would be directly beneficial to consideration or oversight of a project. With the necessary regulations having been promulgated, Sepo has already begun compiling a list of approved experts.

As for consultants, the law envisages they will have various roles. At the very least, government agencies are required to hire consultants to produce reports about particular projects they wish to pursue. In addition, consultants can help to prepare tendering documents, analyze and propose solutions to manage risks, analyze and propose solutions to implementation problems, and/or advise on contract amendments.

Given the important role of consultants, the law requires the PPP Policy Committee to promulgate regulations on their qualifications. These regulations were promulgated early this year and address both individual consultants and firms. Among the requirements, a consultant must have at least three years’ experience and consulted on at least three projects, although these requirements can be reduced in the event of necessity with prescribed approvals.

Among the prohibited characteristics, the regulations exclude those who have specified conflicts of interest, abandoned work or been bankrupt, dismissed for malpractice, or sentenced to imprisonment, except for offenses committed through negligence or petty offenses.

A government agency pursuing a project must hire a consultant to prepare a project appraisal report, which must meet the requirements set out by the PPP Policy Committee. The regulations require the appraisal report to comprise a study and analysis addressing such matters as technical benefits, operating costs, estimated gains, a comparison of costs, and cost-effectiveness of different budget alternatives; alternative models for private sector investment; impacts of the project and means of mitigating negative impacts (environmental, national security, legal compliance, and others); results of the required hearings; identification of risks and their management; and the financial status and other relevant information on the agency pursuing the project.

Once the appraisal report is done, the government agency must submit it to the responsible minister for consideration and approval and then to Sepo, after which consideration will continue in accordance with the procedure specified in law.

With a solid legal foundation laid, the success of PPPs in Thailand will depend on both project champions within the government and private-sector operators that have the flexibility to meet the requirements of their public-sector counterparts. If both of these come together, PPPs can be an excellent solution for Thailand’s infrastructure needs.

RELATED INSIGHTS​ 

August 12, 2024
With the growing prominence of ESG (Environmental, Social, and Governance) factors, businesses in Vietnam are increasingly recognizing their importance in driving global demand, societal impact, and economic value. A comprehensive acknowledgment of ESG-related legal requirements is critical for investors and companies operating in Vietnam to meet stakeholder expectations and ensure compliance. Our guide provides a basic overview of the rapidly evolving ESG landscape in Vietnam, covering a range of key issues for companies doing business in the country: What is ESG, and what does the ESG legal framework look like in Vietnam? Who needs to follow ESG regulations in Vietnam? What are the benefits of ESG compliance? How can enterprises enhance ESG best practices in Vietnam? Please click on the link below to view the full article.
June 6, 2024
On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly. One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector. Annual payment of land rental Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment. As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning. Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged. Obtaining land Under the Land Law 2024,
June 4, 2024
Thailand’s Department of Mineral Fuels (DMF) is in the process of preparing a notification that will open the application period for onshore petroleum exploration and production rights in the country’s 25th bidding round. The 25th round of bidding will cover nine petroleum blocks, including the northeastern areas (blocks L1/66, L2/66, L3/66, L4/66, L5/66, L7/66, and L9/66) and central areas (blocks L6/66 and L8/66). The DMF estimates that application submissions will commence around the middle of 2024, and the successful bidder will be announced at the end of the same year. Based on previous rounds of bidding, applicants must meet the following key criteria: The applicant is a company with the purpose of carrying out petroleum exploration and production; The applicant commands the necessary assets, machinery, equipment, tools, and specialists to explore for, produce, sell, and dispose of petroleum; The applicant has not abandoned its operations under a concession or been subject to revocation of a concession in Thailand; and None of its personnel, shareholders, directors, or authorized directors is listed as a person who has abandoned its operations under a concession, or has been subject to revocation of a concession in Thailand. If the applicant does not itself possess all the qualifications under (2) above, it must have another government-approved company that possesses all the qualifications under (2) and has a capital or management relationship with the applicant, and the applicant must supply guarantees that the company will make available to the applicant all necessary assets, machinery, equipment, tools, and specialists for the applicant to explore for, produce, sell, and dispose of petroleum. Companies with a vested interest in petroleum exploration and production in Thailand must remain vigilant for updates. The DMF is expected to provide an update and more details on the bidding very soon. For more details
June 4, 2024
As Vietnam continues its rapid economic development, the demand for sustainable and reliable energy sources has never been more critical. Solar power has emerged as a key component of Vietnam’s strategy to diversify its energy portfolio and reduce its carbon footprint. Recent developments of the regulatory framework governing solar power projects in Vietnam, as discussed below, highlight the country’s commitment to renewable energy and its efforts to create a conducive environment for solar power investments. Objectives for the Development of Solar Power Projects On May 15, 2023, the Prime Minister issued Decision No. 500/QD-TTg, approving the National Power Development Plan for 2021-2030 with a vision to 2050 (“PDP VIII”). Following this, on April 1, 2024, the Prime Minister promulgated the Implementation Plan for PDP VIII (“Implementation Plan”). These documents underscore Vietnam’s commitment to promoting renewable energy, particularly solar. They emphasize self-production and self-consumption of solar power, the development of rooftop solar systems, and the promulgation of the direct power purchase mechanism. The integration of solar power with battery storage is also encouraged, contingent upon economic viability. PDP VIII sets ambitious capacity targets for solar power. By 2030, the capacity is projected to reach approximately 12,836 MW, accounting for 8.5% of the total power capacity. This includes 10,236 MW from concentrated solar power and 2,600 MW from self-production and self-consumption solar power. By 2050, the capacity is expected to rise to between 168,594 MW and 189,294 MW, representing 33.0-34.4% of the total power capacity. Additionally, PDP VIII and the Implementation Plan list 27 solar power projects, totaling 4,136.25 MW, slated for implementation after 2030. However, these projects may be advanced under self-production and self-consumption arrangements. Draft Decree on Direct Power Purchase Agreements On April 15, 2024, the Ministry of Industry and Trade (“MOIT”) released a draft decree on direct power