December 30, 2014

New Law Puts Public-Private Partnerships on Solid Ground

Bangkok Post, Corporate Counsellor Column

There was much fanfare last year about the enactment of the Private Investment in State Undertaking Act of 2013. Many commentators forecasted an era of renewed vigor for public-private partnerships (PPPs) in Thailand.

In reality, the Act made only incremental changes relative to the older Public Participation in State Undertaking Act of 1992, at least in terms of approval procedures. However, it did set out a much stronger framework for comprehensive planning and quality of public-private ventures. This was evident in sections calling for a PPP Policy Committee, a PPP Fund, and a PPP Strategic Plan, as well as regulations on the use of experts and consultants.

The PPP Policy Committee in particular has broad authority, from preparing the PPP Strategic Plan for cabinet approval to approving projects, proposing measures to support PPPs, considering approval of no-bid selection processes, and issuing a variety of regulatory notifications.

The PPP Strategic Plan will be the main driver of PPP policy, identifying sectors appropriate for PPPs, setting priorities, identifying areas where investment is urgent, and setting targets and time frames. A new plan is to be produced every five years, with evaluations in the interim.

To ensure the plan reflects public needs, the PPP Policy Committee must hold hearings to obtain input from state agencies and members of the public. Prior to each hearing, the State Enterprise Policy Office (Sepo), as the secretariat, will prepare a framework setting out the draft strategic plan, goals, target audience, and other details for the approval of the committee. This will help it to produce an effective PPP Strategic Plan for submission to the cabinet.

The PPP Fund, meanwhile, is envisaged to be used for developing the strategic plan, hiring consultants, and helping state agencies to develop PPPs consistent with the plan. The money will come from state budget appropriations as well as fees charged to bidders. A PPP Fund Committee, separate from the policy panel, set out rules for the fund’s operation and expenditure earlier this year.

The new law also sets out clearer guidelines for the use of experts and consultants. By law, a state agency pursuing a PPP must appoint a selection committee to address tendering and a supervisory committee to handle oversight. Each is required to include some experts with knowledge, expertise, and experience that would be directly beneficial to consideration or oversight of a project. With the necessary regulations having been promulgated, Sepo has already begun compiling a list of approved experts.

As for consultants, the law envisages they will have various roles. At the very least, government agencies are required to hire consultants to produce reports about particular projects they wish to pursue. In addition, consultants can help to prepare tendering documents, analyze and propose solutions to manage risks, analyze and propose solutions to implementation problems, and/or advise on contract amendments.

Given the important role of consultants, the law requires the PPP Policy Committee to promulgate regulations on their qualifications. These regulations were promulgated early this year and address both individual consultants and firms. Among the requirements, a consultant must have at least three years’ experience and consulted on at least three projects, although these requirements can be reduced in the event of necessity with prescribed approvals.

Among the prohibited characteristics, the regulations exclude those who have specified conflicts of interest, abandoned work or been bankrupt, dismissed for malpractice, or sentenced to imprisonment, except for offenses committed through negligence or petty offenses.

A government agency pursuing a project must hire a consultant to prepare a project appraisal report, which must meet the requirements set out by the PPP Policy Committee. The regulations require the appraisal report to comprise a study and analysis addressing such matters as technical benefits, operating costs, estimated gains, a comparison of costs, and cost-effectiveness of different budget alternatives; alternative models for private sector investment; impacts of the project and means of mitigating negative impacts (environmental, national security, legal compliance, and others); results of the required hearings; identification of risks and their management; and the financial status and other relevant information on the agency pursuing the project.

Once the appraisal report is done, the government agency must submit it to the responsible minister for consideration and approval and then to Sepo, after which consideration will continue in accordance with the procedure specified in law.

With a solid legal foundation laid, the success of PPPs in Thailand will depend on both project champions within the government and private-sector operators that have the flexibility to meet the requirements of their public-sector counterparts. If both of these come together, PPPs can be an excellent solution for Thailand’s infrastructure needs.

RELATED INSIGHTS​ 

January 27, 2025
Thailand’s Ministry of Energy (MOE) has announced the launch of the 25th bidding round for petroleum exploration and production. This round offers nine greenfield onshore blocks—seven in northeastern Thailand and two in central Thailand—encompassing over 33,000 km². The bids can be submitted from July 1 to July 16, 2025. The sizes and locations of these blocks are: Northeast Thailand Block L1/66: 3,223.51 km² (Khon Kaen, Nong Bua Lam Phu, Udon Thani) Block L2/66: 3,917.03 km² (Kalasin, Sakon Nakhon, Udon Thani) Block L3/66: 3,918.22 km² (Kalasin, Khon Kaen, Maha Sarakham, Udon Thani) Block L4/66: 3,656.65 km² (Amnat Charoen, Mukdahan, Nakhon Phanom, Yasothon) Block L5/66: 3,436.01 km² (Chaiyaphum, Khon Kaen, Nakhon Ratchasima) Block L7/66: 3,438.51 km² (Buri Ram, Maha Sarakham, Nakhon Ratchasima, Roi Et, Surin, Khon Kaen) Block L9/66: 3,885.44 km² (Nakhon Ratchasima) Central Thailand Block L6/66: 3,966.86 km² (Chaiyaphum, Lop Buri, Phetchabun) Block L8/66: 3,957.41 km² (Kanchanaburi, Nakhon Pathom, Ratchaburi, Suphan Buri) Bidding Process Interested companies must submit their bids to the Department of Mineral Fuels (DMF) between July 1 and July 16, 2025. Bids should include: Application form (ChorThor/Por1) Proof of eligibility: Corporate documentation, audited financial statements, and proof of resources Technical and commercial proposals: Exploration plans, geological surveys, financial and work commitments, and special benefits such as signing bonuses of at least USD 100,000. There is a nonrefundable THB 50,000 application fee per block, and applicants must provide a bid bond of THB 3 million per block via an unconditional bank guarantee from a commercial bank with branches in Thailand, valid for at least one year from the bidding submission date. The guarantee will be returned to unsuccessful bidders upon request and to successful bidders upon the signing of the concession agreement. Eligibility Bidders must meet the following main eligibility criteria: Bidders must be limited companies with the following qualifications: The company must have the objective of
January 23, 2025
In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges. In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports. The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models. Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include: Allowing additional planning where projects do not violate national security. Allowing rectification of projects’ violations in land and construction process as per law. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered. For items (iv) and (v), the authority will issue regulations
January 14, 2025
Thailand’s Department of Industrial Works (DIW) has issued a new regulation (Ministerial Regulation Re: Designation of Type, Kind, and Size of Factories (No. 3) B.E. 2567 (2024)), which removes the factory license requirement for electricity generation from solar energy installations on rooftops, roof decks, or any part of a building used for residential or other purposes, regardless of capacity. The new rules took effect on December 28, 2024. Under the previous regulations, solar rooftop installations had to seek approval from the DIW if their capacity exceeded 1,000 kW (1 MW), which added time and administrative costs when adopting renewable energy solutions. Benefits and Further Compliance The updated regulation benefits industrial operators by facilitating faster installation times and lower costs, as solar rooftops can now be installed without the need for prior approval of a factory license from the DIW. Operators can now more easily contribute to environmental sustainability and carbon reduction efforts. Despite the lifting of the factory licensing requirement, other compliance obligations, such as an energy business license (or exemption from an energy business license), a controlled energy production license, and a construction permit, may still apply. Reason for the Change Removing the classification of rooftop or building-installed solar power plants as factories aligns with Thailand’s renewable energy goals and reduces regulatory burdens for industrial operators. Additionally, it supports the achievement of energy policies aligned with the UN’s Sustainable Development Goals and Thailand’s international commitments to reduce greenhouse gas emissions through the participation of all sectors. For further details on how this change affects business operations or to explore strategies for renewable energy implementation, please contact Supasit Boonsanong at [email protected], Charuwan Charoonchitsathian at [email protected], or Phareeya Yongpanich at [email protected].
December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.