December 30, 2014

New Law Puts Public-Private Partnerships on Solid Ground

Bangkok Post, Corporate Counsellor Column

There was much fanfare last year about the enactment of the Private Investment in State Undertaking Act of 2013. Many commentators forecasted an era of renewed vigor for public-private partnerships (PPPs) in Thailand.

In reality, the Act made only incremental changes relative to the older Public Participation in State Undertaking Act of 1992, at least in terms of approval procedures. However, it did set out a much stronger framework for comprehensive planning and quality of public-private ventures. This was evident in sections calling for a PPP Policy Committee, a PPP Fund, and a PPP Strategic Plan, as well as regulations on the use of experts and consultants.

The PPP Policy Committee in particular has broad authority, from preparing the PPP Strategic Plan for cabinet approval to approving projects, proposing measures to support PPPs, considering approval of no-bid selection processes, and issuing a variety of regulatory notifications.

The PPP Strategic Plan will be the main driver of PPP policy, identifying sectors appropriate for PPPs, setting priorities, identifying areas where investment is urgent, and setting targets and time frames. A new plan is to be produced every five years, with evaluations in the interim.

To ensure the plan reflects public needs, the PPP Policy Committee must hold hearings to obtain input from state agencies and members of the public. Prior to each hearing, the State Enterprise Policy Office (Sepo), as the secretariat, will prepare a framework setting out the draft strategic plan, goals, target audience, and other details for the approval of the committee. This will help it to produce an effective PPP Strategic Plan for submission to the cabinet.

The PPP Fund, meanwhile, is envisaged to be used for developing the strategic plan, hiring consultants, and helping state agencies to develop PPPs consistent with the plan. The money will come from state budget appropriations as well as fees charged to bidders. A PPP Fund Committee, separate from the policy panel, set out rules for the fund’s operation and expenditure earlier this year.

The new law also sets out clearer guidelines for the use of experts and consultants. By law, a state agency pursuing a PPP must appoint a selection committee to address tendering and a supervisory committee to handle oversight. Each is required to include some experts with knowledge, expertise, and experience that would be directly beneficial to consideration or oversight of a project. With the necessary regulations having been promulgated, Sepo has already begun compiling a list of approved experts.

As for consultants, the law envisages they will have various roles. At the very least, government agencies are required to hire consultants to produce reports about particular projects they wish to pursue. In addition, consultants can help to prepare tendering documents, analyze and propose solutions to manage risks, analyze and propose solutions to implementation problems, and/or advise on contract amendments.

Given the important role of consultants, the law requires the PPP Policy Committee to promulgate regulations on their qualifications. These regulations were promulgated early this year and address both individual consultants and firms. Among the requirements, a consultant must have at least three years’ experience and consulted on at least three projects, although these requirements can be reduced in the event of necessity with prescribed approvals.

Among the prohibited characteristics, the regulations exclude those who have specified conflicts of interest, abandoned work or been bankrupt, dismissed for malpractice, or sentenced to imprisonment, except for offenses committed through negligence or petty offenses.

A government agency pursuing a project must hire a consultant to prepare a project appraisal report, which must meet the requirements set out by the PPP Policy Committee. The regulations require the appraisal report to comprise a study and analysis addressing such matters as technical benefits, operating costs, estimated gains, a comparison of costs, and cost-effectiveness of different budget alternatives; alternative models for private sector investment; impacts of the project and means of mitigating negative impacts (environmental, national security, legal compliance, and others); results of the required hearings; identification of risks and their management; and the financial status and other relevant information on the agency pursuing the project.

Once the appraisal report is done, the government agency must submit it to the responsible minister for consideration and approval and then to Sepo, after which consideration will continue in accordance with the procedure specified in law.

With a solid legal foundation laid, the success of PPPs in Thailand will depend on both project champions within the government and private-sector operators that have the flexibility to meet the requirements of their public-sector counterparts. If both of these come together, PPPs can be an excellent solution for Thailand’s infrastructure needs.

RELATED INSIGHTS​ 

August 2, 2022
The Ministry of Energy is preparing to open a bidding round for the right to explore and produce petroleum in three offshore exploration blocks in the Gulf of Thailand: Exploration Block Nos. G1/65, G2/65, and G3/65. Announced in April 2022 with an eye toward national energy sustainability and security, this is the first opportunity for exploration of new offshore areas in 15 years. The total area of the three exploration blocks is 35,164.01 square kilometers, and operations in the exploration blocks will be subject to the terms and conditions of the required production sharing contract (PSC). Under the PSC, the Thai government is entitled to receive royalty payments against profits, any applicable cost recovery, and profit petroleum. The government also has the authority to monitor the petroleum operations in collaboration with the successful bidder. On July 27, 2022, the Department of Mineral Fuels (DMF) held a conference for prospective investors in order to clarify general information regarding the petroleum bidding round. Currently, interested investors can request the right to enter the bidding-round data room located at the DMF by emailing [email protected] by September 2, 2022. To participate in the bidding round, interested investors must submit an application together with required documents to the DMF during the period of September 5–16, 2022. For further information on the bidding round, or on any aspect of energy law in Thailand, please contact Tilleke & Gibbins at [email protected] or +66 2056 5555.
February 28, 2022
On February 9, 2022, the Director-General of the Department of Mineral Fuels (DMF) stated that the DMF is planning to request that the Deputy Prime Minister and the Minister of Energy sign an invitation to open bids for Petroleum Exploration and Production Licenses in the Gulf of Thailand for the first time in 15 years. The DMF’s Chief Department expects that this auction, which will cover three offshore areas, could increase Thailand’s petroleum reserves, and it could lead to the possible discovery of new sources of petroleum for Thailand, which would boost the country’s energy resources, and reduce losses from energy imports. The plots in the Gulf of Thailand that will be auctioned in the 24th bid round are as follows: Plot No. G1/65 with a total area of 8,487 square kilometers. This area is divided into 2 sub-areas: Area A totaling 8,298.49 square kilometers, and Area B totaling 188.71 square kilometers; Plot G2/65 with a total area of 15,030 square kilometers; and Plot No. G3/65 with a total area of 11,646.67 square kilometers. This area is divided into 2 sub-areas: Area A totaling 11,028.22 square kilometers, and Area B totaling 618.45 square kilometers. Generally, Thailand initiates its concession and production sharing contract process with the announcement of an exploration area or a plot in the Government Gazette. Thereafter, the DMF Committee will consider and announce the invitation, so that private sector firms can submit their applications to receive respective rights. The DMF’s sub-committee will consider the applications by: checking the qualifications stipulated under Section 24 of the Petroleum Act; assessing the suitability of the exploration project; and determining the benefits which are offered by the applicant. After considering the requests, the DMF’s sub-committee will consider the petroleum laws and regulations, before submitting the matter to the Petroleum Committee—under
February 22, 2022
The many new and unique challenges in recent years—from epidemics, to travel restrictions, to supply chain disruptions and energy-related reactions to all of the above, we have all had to adjust to a new status quo. The energy industry has felt these impacts acutely, and as the industry seeks to meet the current challenges and move forward toward a more sustainable future, it is helpful to take stock of where things stand and where they might be headed in the coming years. In the midst of this uncertainty, Energy Law in Southeast Asia by the Tilleke & Gibbins Energy Industry Team seeks to provide clarity on the legal and regulatory environment surrounding energy industry activities. Each chapter of Energy Law in Southeast Asia takes the reader through the essential information surrounding energy and environmental regulations in general and the specific laws and practices for the major areas of energy projects—both in terms of the current energy mix and the sources taking on a larger role as we transition toward a lower-carbon future. These chapter subsections are: Regulatory Structure Oil and Gas Coal Solar Wind Hydropower Biomass and Biogas Environmental Regulations In providing this legal overview of major areas across the spectrum of energy projects in Southeast Asia, we have sought to create a resource for all involved in the energy industry, regardless of their specific area of interest or the different obstacles or challenges they seek to resolve. Energy Law in Southeast Asia is written by specialists on Tilleke & Gibbins’ Energy Industry Team, who together have over 200 years of accumulated energy experience. Spread throughout Tilleke & Gibbins’ offices in Southeast Asia, they function both as an integrated regional team to advise multinational enterprises on their regional energy project portfolios, and as experts for investors and companies looking
January 27, 2022
The Energy Generating Authority of Thailand (EGAT) has launched a pilot project to study the energy consumption and the economic, social, and environmental impact of electric motorcycle taxis, as well as the behavior of drivers and passengers. The project, which was launched on December 27, 2021, as part of EGAT’s Carbon Neutrality Policy, will continue for a year, after which EGAT will consider the data and decide whether electric motorcycle taxis should be introduced nationwide. EGAT is also currently encouraging the use of electric bikes within their own organization, and they initially expect this to help reduce annual carbon dioxide emissions by 37 tons and prevent the release of about 838,000 milligrams of dust per year. EGAT expects additional significant reductions from electric motorcycle taxi pilot projects in multiple locations. A study conducted in Kenya in 2015 by that country’s energy regulator found that sub-150cc motorcycles emit approximately 46.5 grams of carbon dioxide per kilometer, and these emissions increase proportionally in accordance with engine size. According to Thailand’s Office of Industrial Economics, citing data collected by the Federation of Thai Industries Automotive Industry Group, a total of 1,516,096 motorcycles were sold in Thailand in 2020—a surprisingly robust figure in light of the impact of the COVID-19 pandemic. Assuming that public motorcycles travel an average of 15,000 kilometers per year, each motorcycle is therefore producing approximately 0.7 tons of carbon dioxide per year. If Thailand is able to change 50% of its yearly sales of standard motorcycle to electric motorcycles, annual carbon dioxide emissions could decrease by approximately 530,000 tons. Furthermore, since 28.8% of carbon dioxide emissions in Thailand are generated from the transport sector, the transition to electric mobility vehicles looks to be one of the most promising solutions for lowering carbon dioxide emissions in the country. Considering developments