November 13, 2025

Legal Options for Addressing Challenges with Land Matters in Thailand

The Land Department in Thailand’s Ministry of the Interior (MOI) plays a central role in ensuring the stability and legality of real estate transactions in the country. Its core responsibilities include issuing land title deeds, registering transactions (e.g., sales, mortgages, leases), conducting surveys for subdivision or consolidation of land, and providing information and guidance on land and property development laws.

These administrative functions secure investor confidence and support transparency in the Thai property market, so any delay can have a significant impact. This is especially true for investors who depend on timely registration to secure or transfer property rights. Delays can create liquidity risks, postpone project timelines, and even reduce Thailand’s attractiveness as a real estate investment destination.

This article explores the nature of these challenges, the legal framework governing the timelines for administrative actions, and remedies available under Thai law.

Sources of Delay

Procedural delays at land offices can arise for a variety of structural and operational reasons. These include approval processes that require several levels of internal review, heavy staff workloads, and occasional communication gaps within the bureaucratic chain. Many processes still rely upon manual documentation, which can prolong administrative steps and increase the likelihood of bottlenecks.

Some delays stem from ongoing investigations into the legality of land titles. For example, a land title deed may have an annotation indicating that the title deed is under investigation to verify its legality. Even though this annotation does not legally prohibit the sale or transfer of the land, in practice, most prospective purchasers are reluctant to proceed with a transaction until the annotation is removed. As a result, the land can become effectively illiquid during the investigation period, leading to significant investment delays.

While such investigations are essential to maintaining the integrity of Thailand’s land registration system, prolonged inquiries without clear timelines can affect investor confidence and obstruct legitimate commercial activity.

Timelines for Administrative Action

Thailand has taken important steps to address concerns about bureaucratic delays by enacting legal instruments that impose procedural timelines on government agencies, including the Land Department. Two of these are outlined below.

Act on the Determination of Timeframes in the Justice Process B.E. 2565 (2022)

The Act on the Determination of Timeframes in the Justice Process B.E. 2565 (2022) requires all government agencies under the MOI, including the Land Department, to establish and publicly announce clear timelines for the completion of administrative tasks. Affected agencies must ensure that these timelines are accessible and understandable to the public. If an official cannot complete a process within a prescribed timeline, he or she must record the reason for the delay, specify the estimated completion date, and notify relevant parties. A record must also be available for verification and audit.

Land Code

The Land Code sets a specific timeline for investigations concerning irregularities in land title issuance. Once an investigation has been ordered, it must be completed within sixty days. An investigation committee may recommend extending this period for up to an additional sixty days, if necessary, by issuing a report, after which a Land Department Officer or authorized delegate must issue a final decision within fifteen days.

These provisions are designed to ensure that inquiries do not remain pending indefinitely. However, the law also allows the investigation period to be extended when deemed “necessary,” and the law does not explicitly specify how many times such an extension may be granted. In practice, therefore, officers may consider granting an extension more than once.  This discretionary flexibility can contribute to prolonged or unpredictable delays.

Available Remedies

If the Land Department’s action or inaction causes undue delay, affected parties have the right to claim damages and seek revocation of unlawful orders issued by officials. Thai law provides several administrative and judicial remedies to expedite or rectify such a situation.

 Administrative Complaints to Expedite the Process

  • Damrongdhama Center: Individuals can submit complaints through the MOI’s Damrongdhama Center (a complaint-handling unit) either in person, by post, via telephone hotline, through a mobile application, or online.
  • Direct complaint to the Land Department: Parties may file a petition directly with a Land Department officer or with the provincial or branch Land Office responsible for the area in which the matter arose.

These channels can prompt internal reviews and often help move pending matters forward.

Civil and Administrative Claims for Damages

  • Civil liability: Under Thailand’s Civil and Commercial Code, a person who suffers loss due to a wrongful act by an official may claim compensation. The Supreme Administrative Court has affirmed this principle.
  • Administrative liability: The State Officials Liability Act B.E. 2539 (1996) allows for claims against the state for wrongful acts (e.g., asking the court to revoke unlawful orders) committed by government officers in the course of their duties. Under the Administrative Procedure Act B.E. 2539 (1996), parties may also challenge unlawful or unreasonable administrative decisions or delays. The Administrative Court has ruled in several cases that excessive or unjustified delays can amount to administrative misconduct subject to judicial review.

Criminal Proceedings for Misconduct

In severe cases involving intentional wrongdoing or abuse of authority, criminal prosecution may be available under the Thai Penal Code, together with the Land Code.

Outlook: Remedies and Reform

The primary focus of legal remedies is to address individual cases rather than systemic inefficiencies. Delays involving land matters in Thailand, however, often reflect broader administrative challenges, such as limited resources, complex procedural requirements, and the need for modernization.

Sustainable reform therefore requires a systemic approach, as timely and predictable land administration will be able to sustain investor confidence and support the continued growth of Thailand’s real estate sector. Although legal mechanisms are in place to address delays, true efficiency depends on long-term administrative reform and digital modernization within the related government agencies.

Mindful of this broader context, investors or property owners facing prolonged delays or legal uncertainty should prepare necessary documentation, maintain clear communication with authorities, and seek proper professional legal assistance.

RELATED INSIGHTS​ 

December 19, 2025
Prior to the dissolution of the House of Representatives, Thailand’s cabinet approved a draft amendment to the Administrative Procedure Act, following review by the Council of State. If enacted, this reform will fundamentally change how state agencies process business applications and appeals by imposing enforceable timelines and legal consequences for inaction. The draft directly targets a longstanding commercial frustration: applications and appeals that vanish into administrative silence, stalling investment and foreclosing judicial review across sectors ranging from real estate and manufacturing to healthcare and finance. The “Silence Means Yes” Rule for Applications At the core of the reform is a new automatic “approval by implication” for applications subject to statutory processing deadlines. If an official fails to notify an applicant of a decision within the legally prescribed period, the application will be deemed approved as a matter of law. This presumption shifts the costs of delay from businesses to the bureaucracy and gives applicants a definitive legal position once time expires. The mechanism applies to routine licensing and registration matters governed by explicit consideration periods in existing statutes or ministerial regulations. Officials may extend the decision period by up to thirty days, but only if they notify the applicant before the original deadline and substantiate that the delay arises from genuinely exceptional circumstances beyond their control. Certain sensitive applications are expressly excluded from automatic approval, including those that may significantly affect national security or defense, public safety and health, the environment or natural resources, or national cultural heritage. Once the deadline passes without a decision, businesses can proceed with deployment of capital and operations—construction, hiring, procurement, and market entry—without waiting for formal permission that may never arrive. For time-sensitive projects, this materially reduces regulatory timing risk. The “Deemed Rejection” Rule for Appeals The draft introduces a parallel “deemed rejection”
December 16, 2025
Tilleke & Gibbins has contributed the Cambodia, Laos, Myanmar, Thailand, and Vietnam chapters to Infrastructure and Construction in Southeast Asia, a comparative guide developed by Drew Network Asia (DNA). The publication brings together insights from leading ASEAN law firms to address common legal and practical issues faced by participants in the construction and engineering sector across the region. Covering nine major Southeast Asian jurisdictions, the guide provides concise answers to frequently encountered questions relating to infrastructure and construction projects. Topics addressed include the regulatory environment, procurement practices, project structuring, risk allocation, contracting terms, dispute resolution mechanisms, and the enforcement of arbitral awards. Each jurisdictional chapter follows a consistent question-and-answer format, enabling readers to compare legal approaches and market practices across countries. This structure highlights both areas of convergence and key differences between jurisdictions, supporting more informed decision-making in cross-border projects and investments. While the guide offers a practical regional overview, it also underscores that legal frameworks and market practices vary significantly between jurisdictions and may be shaped by local principles and industry norms. Readers seeking jurisdiction-specific advice are encouraged to contact the practitioners listed at the end of each chapter. The full guide is available for download through the button below or directly from the DNA website.
December 15, 2025
On December 10, 2025, the National Assembly of Vietnam officially passed the amended Law on Construction, marking the culmination of a multiyear reform process aimed at modernizing Vietnam’s construction legal framework, streamlining administrative procedures, and aligning with digital transformation and sustainability goals. The amended law, which replaces the current Law on Construction No. 50/2014/QH13, will take effect on July 1, 2026. The Ministry of Construction (MOC) is also preparing several guiding decrees covering project classification, digital submissions and database management, and technical standards for design documentation. Key Changes in the Amended Law While the executed version of the amended Law on Construction has yet to be released to the public, reports have confirmed that it includes the following key changes introduced under the latest draft submitted by the MOC in September: Project classification: The amended Law on Construction classifies construction projects by investment form (public, PPP, business investment, and others), which aligns with the Law on Public Investment, the Law on Investment, and the Law on PPP Investment. This reduces regulatory overlap and clarifies responsibilities. Project preparation and appraisal: The requirement for prefeasibility reports for business investment projects is abolished, as this requirement is now governed by the Law on Investment and the Law on Public Investment. This change shortens the preparation timeline and reduces duplication of procedures. In addition, the authority’s appraisal is streamlined to a single feasibility stage. Also eliminated is the appraisal process conducted following basic design approval, shifting more responsibility to investors and consultants, with targeted post-audit mechanisms for high-risk projects. Construction permits: One of the most significant new changes of the amended Law on Construction is the expansion of exemptions from construction permit requirements to the following eight distinct groups of construction works: State-secret works, emergency or urgent constructions, works under special public investment
December 12, 2025
Similar to other types of corporate disputes, tax-related conflicts often begin with an earnest attempt to resolve matters outside the courtroom. The prospect of engaging in tax litigation can be daunting, given the potential strain on commercial relationships, the legal expenses, and the uncertainty surrounding its resolution. However, there are instances when tax litigation becomes the sole avenue for seeking redress. For individuals and entities contemplating the pursuit of tax-related legal remedies, the Thai legal system offers an accessible, impartial, and equitable platform for dispute resolution. Tilleke & Gibbins’ latest update to Tax Litigation in Thailand provides an outline for navigating tax-related disputes within the Thai legal framework. It aims to equip readers with a fundamental understanding of procedures and practices within the Thai tax litigation landscape. The full guide is available through the button below.