Investment Incentives for Solar and Wind Energy Projects in Vietnam

Informed Counsel

Solar and wind energy are clean, renewable sources that are becoming increasingly popular in many countries, especially in developing economies such as Vietnam. Realizing the importance, advantages, and benefits of such sustainable sources of energy, and facing an increasing demand for electricity supply for further economic development (with consistent annual electricity consumption increases of 10–15 percent), Vietnam decided recently to give greater scrutiny to studying, surveying, encouraging, and supporting investors, both foreign and domestic, investing in renewable energy projects.

Development of new and renewable energy was included in Vietnam’s national energy development strategy through 2020, with a vision towards 2050, as promulgated in Decision 1855. This strategy sets specific targets to increase the proportion of new and renewable energy sources to 3 percent of total commercial primary power by 2010, 5 percent by 2020, and 11 percent by 2050. To reach these targets, Decision 1855 also guides the direction and orientation for development together with policies, incentives, and governmental support to attract investors. These goals are reflected in various pieces of legislation.

Advantages for Investors

Under current legislation, investors are entitled to maximum incentives for every aspect related to solar or wind energy projects, such as land or water surface lease terms and fees, corporate income tax, value-added tax, import and export duties, land site clearance, and depreciation of fixed assets, among others. In addition, solar and wind power projects are considered clean investments under the country’s clean development mechanism (see Decision 130). Accordingly, investors are subsidized by the state through the Environmental Protection Fund of Vietnam for the difference between the real input costs and the sales price of power as agreed to in the contract to provide power generated by solar or wind energy (see Decree 58).

Challenges for Investors

Although enjoying a variety of incentives, investors also face several challenges when investing in these kinds of projects. First, at present, Vietnam has not yet conducted any official or comprehensive surveys, studies, or assessments on the potential of solar or wind energy in Vietnam. Thus, prospective investors may lack necessary information when seeking investment opportunities.

Second, Vietnam does not have a cohesive legal framework governing policies related to solar or wind energy projects. Such policies are now stipulated separately in various statutes. In some instances, there are conflicting rules and regulations between different laws governing the same issues. To overcome these difficulties, the deputy prime minister recently requested and assigned the Ministry of Industry and Trade to fast-track a draft decision of the prime minister’s office on the strategy and general planning for development of renewable energy in Vietnam up to 2030, with a vision towards 2050. The draft plan is awaiting the prime minister’s approval.

Third, and most importantly, Vietnam lacks an effective and feasible mechanism for investor financing as it relates to the sales price of wind power. Currently, the Vietnam Electricity Group (EVN) is the exclusive transmitter, purchaser, and distributor of power. The sales price for power in Vietnam is always the highest hurdle for investors to overcome, and in practice, the set prices for power purchase by the EVN monopoly are always much lower than the actual input costs. As encouragement, the state assists investors by providing a subsidy for the difference in contract price (see Decision 130). But these subsidies are often insufficient and limited to the amount set aside in the state fund. As a result, investors remain cautious of their risks when investing in this field.

To calm investors’ anxieties, the Ministry of Industry and Trade very recently completed and submitted to the government, for its consideration and approval, a draft decision on promulgating regulations on investment and construction of wind power projects in Vietnam. The draft indicates EVN will assist in the connection of wind-generated power to the power grid and be liable for purchasing and distributing all products from wind power projects. In particular, EVN will pay VND 1,317 (approximately USD 0.07) for each kilowatt of wind-generated power, and the state will subsidize an amount of VND 185 (approximately USD 0.01).

Furthermore, under the draft plan, wind power investors will enjoy import tax exemption on machinery and equipment, corporate income tax at 10 percent for the life of the project, land-use tax exemption for the duration of the project, and access loans up to 80 percent of the total investment capital along with preferential interest rates.

Project Restrictions

At present, there are no statutory prohibitions relating to the development of coastal areas as it pertains to energy investors, either foreign or Vietnamese. Legislation on investments only prohibits projects that:

  • Are detrimental to national defense and security and/or the public interest.
  • Are detrimental to historical and cultural traditions and ethics, and Vietnamese fine customs.
  • Harm the people’s health, or destroy natural resources and the environment.
  • Treat toxic wastes brought into Vietnam, or are projects for the manufacture of any type of toxic chemicals or for the use of chemical agents prohibited by international treaties.

Subject to the above exceptions, investors enjoy the right to invest in other projects without restrictions as to location within Vietnam, provided that the investor satisfies all conditions and procedures in accordance with the law.

Wind Projects in Vietnam

Among alternative energy sources, wind power may represent the strongest growth opportunity in Vietnam. Surveys have shown that approximately 85 percent of Vietnam’s land has an elevation and average wind speed that is suitable for generating wind power. Experts from the World Bank have concluded that Vietnam has the ability to generate 513,360 megawatts annually through wind power—10 times the projected national electricity capacity for 2020.

The coastal provinces of Binh Thuan and Ninh Thuan, in particular, are considered to have the greatest potential for wind power in large plots of land that are arid and not agriculturally fertile. At present, there are more than 20 wind power projects in Vietnam, mainly located in Binh Thuan (12 projects on the mainland and Phu Quy Island District), Ninh Thuan, Binh Dinh, Phu Yen, and Con Dao Island District of Ba Ria-Vung Tau province, where the volume and average wind speed are highest compared to the rest of the country.

Of these, the wind power projects in Binh Thuan and Ninh Thuan of the Vietnam Renewable Energy Joint Stock Company (REVN) stand out because of their size. REVN is the owner of Tuy Phong Wind Power Factory located in Binh Thanh commune, Tuy Phong district, Binh Thuan province. Phase 1, consisting of 20 turbines, was just completed with a capacity of 30 megawatts. The project was put into operation (i.e., began generating power) as of March 2011 with a total investment capital of VND 1.5 billion. REVN is now carrying out phase 2 of this project at both Binh Thanh and Chi Cong communes, with an anticipated capacity of 90 megawatts, and total investment capital of VND 4.5 billion. The project, which is now being implemented,will be concluded by 2015.

In Ninh Thuan province, REVN is building Wind Power Factory 1 located at Phuoc Minh commune, Thuan Nam district, with an anticipated capacity of 30 megawatts, including 15 turbines, and a total investment capital of VND 1.35 billion. Operations are expected to begin in 2012. All remaining projects are either in the surveying stage or under construction.

Outlook

Based on projected energy consumption levels, Vietnam will need to secure new sources of energy to maintain its economic growth. The state has given positive signals that it is committed to solar and wind energy over the long term, and these signals have been backed up by the implementation of a wide range of incentives and commitments to a more cohesive plan for renewable energy development in the years to come. As this legal framework develops, solar and wind projects may emerge as one of the most attractive fields for foreign investment in Vietnam.

RELATED INSIGHTS​ 

August 2, 2022
The Ministry of Energy is preparing to open a bidding round for the right to explore and produce petroleum in three offshore exploration blocks in the Gulf of Thailand: Exploration Block Nos. G1/65, G2/65, and G3/65. Announced in April 2022 with an eye toward national energy sustainability and security, this is the first opportunity for exploration of new offshore areas in 15 years. The total area of the three exploration blocks is 35,164.01 square kilometers, and operations in the exploration blocks will be subject to the terms and conditions of the required production sharing contract (PSC). Under the PSC, the Thai government is entitled to receive royalty payments against profits, any applicable cost recovery, and profit petroleum. The government also has the authority to monitor the petroleum operations in collaboration with the successful bidder. On July 27, 2022, the Department of Mineral Fuels (DMF) held a conference for prospective investors in order to clarify general information regarding the petroleum bidding round. Currently, interested investors can request the right to enter the bidding-round data room located at the DMF by emailing [email protected] by September 2, 2022. To participate in the bidding round, interested investors must submit an application together with required documents to the DMF during the period of September 5–16, 2022. For further information on the bidding round, or on any aspect of energy law in Thailand, please contact Tilleke & Gibbins at [email protected] or +66 2056 5555.
February 28, 2022
On February 9, 2022, the Director-General of the Department of Mineral Fuels (DMF) stated that the DMF is planning to request that the Deputy Prime Minister and the Minister of Energy sign an invitation to open bids for Petroleum Exploration and Production Licenses in the Gulf of Thailand for the first time in 15 years. The DMF’s Chief Department expects that this auction, which will cover three offshore areas, could increase Thailand’s petroleum reserves, and it could lead to the possible discovery of new sources of petroleum for Thailand, which would boost the country’s energy resources, and reduce losses from energy imports. The plots in the Gulf of Thailand that will be auctioned in the 24th bid round are as follows: Plot No. G1/65 with a total area of 8,487 square kilometers. This area is divided into 2 sub-areas: Area A totaling 8,298.49 square kilometers, and Area B totaling 188.71 square kilometers; Plot G2/65 with a total area of 15,030 square kilometers; and Plot No. G3/65 with a total area of 11,646.67 square kilometers. This area is divided into 2 sub-areas: Area A totaling 11,028.22 square kilometers, and Area B totaling 618.45 square kilometers. Generally, Thailand initiates its concession and production sharing contract process with the announcement of an exploration area or a plot in the Government Gazette. Thereafter, the DMF Committee will consider and announce the invitation, so that private sector firms can submit their applications to receive respective rights. The DMF’s sub-committee will consider the applications by: checking the qualifications stipulated under Section 24 of the Petroleum Act; assessing the suitability of the exploration project; and determining the benefits which are offered by the applicant. After considering the requests, the DMF’s sub-committee will consider the petroleum laws and regulations, before submitting the matter to the Petroleum Committee—under
February 22, 2022
The many new and unique challenges in recent years—from epidemics, to travel restrictions, to supply chain disruptions and energy-related reactions to all of the above, we have all had to adjust to a new status quo. The energy industry has felt these impacts acutely, and as the industry seeks to meet the current challenges and move forward toward a more sustainable future, it is helpful to take stock of where things stand and where they might be headed in the coming years. In the midst of this uncertainty, Energy Law in Southeast Asia by the Tilleke & Gibbins Energy Industry Team seeks to provide clarity on the legal and regulatory environment surrounding energy industry activities. Each chapter of Energy Law in Southeast Asia takes the reader through the essential information surrounding energy and environmental regulations in general and the specific laws and practices for the major areas of energy projects—both in terms of the current energy mix and the sources taking on a larger role as we transition toward a lower-carbon future. These chapter subsections are: Regulatory Structure Oil and Gas Coal Solar Wind Hydropower Biomass and Biogas Environmental Regulations In providing this legal overview of major areas across the spectrum of energy projects in Southeast Asia, we have sought to create a resource for all involved in the energy industry, regardless of their specific area of interest or the different obstacles or challenges they seek to resolve. Energy Law in Southeast Asia is written by specialists on Tilleke & Gibbins’ Energy Industry Team, who together have over 200 years of accumulated energy experience. Spread throughout Tilleke & Gibbins’ offices in Southeast Asia, they function both as an integrated regional team to advise multinational enterprises on their regional energy project portfolios, and as experts for investors and companies looking
January 27, 2022
The Energy Generating Authority of Thailand (EGAT) has launched a pilot project to study the energy consumption and the economic, social, and environmental impact of electric motorcycle taxis, as well as the behavior of drivers and passengers. The project, which was launched on December 27, 2021, as part of EGAT’s Carbon Neutrality Policy, will continue for a year, after which EGAT will consider the data and decide whether electric motorcycle taxis should be introduced nationwide. EGAT is also currently encouraging the use of electric bikes within their own organization, and they initially expect this to help reduce annual carbon dioxide emissions by 37 tons and prevent the release of about 838,000 milligrams of dust per year. EGAT expects additional significant reductions from electric motorcycle taxi pilot projects in multiple locations. A study conducted in Kenya in 2015 by that country’s energy regulator found that sub-150cc motorcycles emit approximately 46.5 grams of carbon dioxide per kilometer, and these emissions increase proportionally in accordance with engine size. According to Thailand’s Office of Industrial Economics, citing data collected by the Federation of Thai Industries Automotive Industry Group, a total of 1,516,096 motorcycles were sold in Thailand in 2020—a surprisingly robust figure in light of the impact of the COVID-19 pandemic. Assuming that public motorcycles travel an average of 15,000 kilometers per year, each motorcycle is therefore producing approximately 0.7 tons of carbon dioxide per year. If Thailand is able to change 50% of its yearly sales of standard motorcycle to electric motorcycles, annual carbon dioxide emissions could decrease by approximately 530,000 tons. Furthermore, since 28.8% of carbon dioxide emissions in Thailand are generated from the transport sector, the transition to electric mobility vehicles looks to be one of the most promising solutions for lowering carbon dioxide emissions in the country. Considering developments